Questions and Answers
1. Davis Bacon Act apply on this job? If yes, the $10.20 hourly includes fringes? The EO does not apply to projects performed in Puerto Rico.
2. The wood floor on the bridge is part of this job? It is an option (see item No. 1 of the alternates)
3.On page 2 Section-B on the chart the descriptions looks like is duplicate on the four items, and in the space where we going to put the prices will be duplicate. Another thing is that, in that description there are areas that we dont discuss to be repair on the site visit last week. Please let us know the areas to bid. It just the areas painted in the drawing? Revised Pay Schedule has been submitted to FBO.
4. Is there any restriction to sub contract part of the job? Subs must adhere to rules and regulations identified in solicitation. Subs cannot be debarred.
5. We have to take portable bathrooms or we can use the facilities bathrooms? Yes, Contractors can use bathrooms.