SECTION_G.Installation_of_Aquion_Energy's_Aqueous_Hybrid_Ion_(AHI) _Salt_Water_Batteries_and_Removal_and_Disposal__of_12_Existing_Lead_Acid_Batteries.docx

DOCX document 14 KB Posted

Attached to
Installation of Aquion Energy's Aqueous Hybrid Ion Salt Water Batteries and Removal/Disposal of Existing Lead Acid Batteries
Solicitation number
AG-9AD6-S-16-0003
Issued by

About this file

Section G Contract Administration Data

View the file

Other files

File Type Posted
PART_IV.Section_K.Installation_of_Aquion_Energy's_Aqueous_Hybrid_Ion_(AHI) _Salt_Water_Batteries_and_Removal_and_Disposal_of_the_Existing_Lead_Acid_Batteries.docx DOCX document
Section_C-_Installation_of_Aquion_Energy's_Aqueous_Hybrid_Ion_(AHI) _PV_Solar_Batteries.docx DOCX document
SF1449.Installing_Aquion_Energy's_Aqueous_Hybrid_Ion_(AHI) _Salt_Water_Batteries_and_Removal_and_Disposal_of_the_Existing_Lead_Acid_Batteries.pdf PDF
Section_J_-_Installation_of_Aquion_Batteries.pdf PDF
SECTION_F.Installation_of_Aquion_Energy's_Aqueous_Hybrid_Ion_(AHI) _Salt_Water_Batteries_and_Removal_and_Disposal_of_12_Lead_Acid_Batteries.docx DOCX document
SECTION_M.Installation_of_Aquion_Energy's_Aqueous_Hybrid_Ion_(AHI) _Salt_Water_Batteries_and_Removal_and_Disposal_of_the_Existing_Lead_Acid_Batteries.docx DOCX document
SECTION_L.Installation_of_Aquion_Energy's_Aqueous_Hybrid_Ion_(AHI) _Salt_Water_Batteries_and_Removal_and_Disposal_of_the_Existing_Lead_Acid_Batteries.docx DOCX document
Section_I.Installation_of_Aquion_Energy's_Aqueous_Hybrid_Ion_(AHI) _Salt_Water_Batteries_and_Remove_and_Dispose_of_12_Existing_Lead_Acid_Batteries.docx DOCX document
Section_J_-__Table_of_Contents_for_Installation_of_Aquion_Energy's_Aqueous_Hybrid_Ion.docx DOCX document
SECTION_E.Installation_of_Aquion_Energy's_Aqueous_Hybrid_Ion_(AHI) _Salt_Water_Batteries_and_Remove_and_Dispose_of_12_Existing_Lead_Acid_Batteries.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION G – CONTRACT ADMINISTRATION DATA

GOVERNMENT – FURNISHED PROPERTY

The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the “Government Property” FAR clause contained elsewhere in the contract.

NONE

INVOICES

Invoices must be submitted electronically through the Invoice Processing Platform (IPP) via www.ipp.gov. A copy of the invoice should be submitted to Dean Oshiro by email: deanyoshiro@fs.fed.us for task completion verification, once verified Mr. Oshiro will email invoice to Ella Whitfield at ewhitfield@fs.fed.us to be approved in IPP by the Contracting Officer.

INCIDENTAL ITEMS

The intent of the contract is to provide for the completion of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment of items shown.