Section_C__LaupahoehoeAsphalt_and_Concrete_Statement_of_Work.docx
DOCX document 15 KB Posted
- Solicitation number
- AG-9AD6-S-15-0001
About this file
Section C - Statement of Work
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AG-9AD6-S-15-0001_amendment_P0001.pdf | ||
| SECTION_L_Laupahoehoe_Asphalt_and_Concrete.docx | DOCX document | |
| Part_III_-_List_of_Documents _Exhibits _and_other_Attachments.docx | DOCX document | |
| Section_B_-__Schedule_of_Items_Laupahoehoe_Asphalt_and_Concrete.doc | DOC document | |
| Section_J-1_-Definition_of_Bid_Items_and_Measurement_and_Payment.docx | DOCX document | |
| Part_II_-_Section_I_-_Contract_Clauses.docx | DOCX document | |
| SF1442-Hilo_concrete_and_asphalt.pdf | ||
| Section_J-3_-_Drawings.pdf | ||
| SECTION_E_LaupahoehoeAsphalt_and_Concrete.docx | DOCX document | |
| Section_J-2_-__Davis_Bacon_Wage_Rates_for_Laupahoehoe_Asphalt_and_Concrete.docx | DOCX document | |
| PART_IV__Laupahoehoe_Ashphalt_and_Concrete.docx | DOCX document | |
| SECTION_F__Laupahoehoe_Asphalt_and_Concrete.docx | DOCX document | |
| Section_M_-_Evaluation_factors_for_Award.docx | DOCX document | |
| SECTION_G_Laupahoehoe_Asphalt_and_Concrete.docx | DOCX document |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section C – Description/Specifications/Statement of Work For Laupahoehoe Asphalt & Concrete
Statement of Work/Specifications (AGAR 452.211-72)(FEB 1988)
The contractor shall furnish the necessary personnel, material, equipment, services facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
Description of Work
Work for this project consists of, but not limited to, providing all manpower, equipment, and materials to complete the construction of the concrete, facilities, and retaining wall features including obliteration of an existing concrete drainage dip and concrete waste pile; site grading; construction of new 6-inch thick reinforced concrete driveway at the main house; precast concrete wheelstops; construction of new 6-inch reinforced concrete apron at the warehouse; construction of new 4-inch sidewalks around the main house courtyard; concrete curb and gutter; concrete chase drains; concrete retaining wall with stone veneer and cap; and modular concrete retaining wall with cap.
In addition providing all manpower, equipment, and materials to complete the reconstruction and construction of roads and parking including, but not limited to selective clearing and grubbing, drainage excavation, site grading, aggregate base, road reconditioning, hot asphalt concrete pavement, wheelstops, gates, and pavement markings.
Location
This project is located at the Laupahoehoe Science and Education Center, 36-645 Spencer Road, Laupahoehoe, Hawaii 96764.
Use of Premises
General: Contractor shall have limited use of premises for construction operations during construction period. Contractor’s use of premises is limited only by the Government’s right to perform work or to retain other contractors on portions of Project.
Contractor shall at all times conduct his operations to ensure the least inconvenience to the public and employees.
Confine storage of materials to areas as approved by the CO.
Contractor shall provide adequate signing and barricades and take necessary safety measures to protect the public during all construction operations. Contractor shall minimize disturbance of all undisturbed areas.
Field Verification
Field verifies all new and existing dimensions affecting the work of this contract before ordering products.
Permits
Special permits for electrical work or any other permits required by county, State, or Federal Laws or regulations shall be obtained by the Contractor.
Traffic during Work
Perform work in a manner that ensures the safety and convenience of the public and protects the residents and property adjacent to the project. Accommodate public traffic on roads adjacent to and within the project until the project is accepted.
Work by Others
Construction of concrete work will be occurring during the construction of this project. It shall be the responsibility of the contractor to coordinate all work schedules with others involved in the construction of facilities at this site. It is anticipated that the majority of work under this contract will occur after the concrete work has been finished and accepted by the Government. No material cost increases will be allowed while the concrete work is being completed and the Contractor shall plan accordingly.