Northern California Service Center Ops Building Roof Replacement
Solicitation number
AG-9AC7-S-17-0046
Issued by

About this file

Amendment 6 Revised Solicitation

View the file

Other files

File Type Posted
Q_and_A_as_of_6-20.pdf PDF
SF24_Bid.pdf PDF
Davis_Bacon_WD.pdf PDF
Plans.pdf PDF
Project_Specifications.pdf PDF
Amendment_5.pdf PDF
AG-9AC7-S-17-0046_Amendment_4.pdf PDF
Questions_and_Comments_from_Site_Visit.pdf PDF
Amendment_3.pdf PDF
AG-9AC7-S-17-0046_Amendment_000003.pdf PDF
CA9_mod_9,_051217.pdf PDF
SF-30.pdf PDF
Q_and_A_5-11.pdf PDF
Sol_AG-9AC7-S-17-0046_Amd_000001.pdf PDF
AG-9AC7-S-17-0046_Final.pdf PDF
2._NCSC_Roof_Plans_&_Photos.pdf PDF
4._CA9,_mod_5,_04072017.pdf PDF
5._SF24_Bid.pdf PDF
1.Project_Specifications_update.pdf PDF
3._Fabric_Reinforced_Spec.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

AG-9AC7-S-17-0046

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

9AC7

REDDING CA 96002

3644 AVTECH PARKWAY SUITE 180

R5 NO-CAL ACQ SERVICE AREA NCASA

USDA FOREST SERVICE

06/08/2017000006

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

03/27/2017

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Roof Replacement - Northern California Service Center Operations Building

The purpose of this amendment is to extend the due date for proposals to 6/22/2017 1300PD.

Amendment 6 replaces the solicitation package in it's entirety. Please use all the updated documents in this amendment for your proposal submission. See attached updated documents.

All other terms and conditions remain unchanged.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

PAUL M. WOOD

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

6/8/2017

X 1

NCSC Ops Roofing Project, Northern California Service Center - 4 -

AG-9AC7-S-17-0046

TABLE OF CONTENTS

PART I - SCHEDULE OF ITEMS

SECTION B - SUPPLIES OR SERVICES AND PRICES/COSTS SCHEDULE OF ITEMS

B.1 Note Regarding Bond Premiums

B.2 Availability of Funds – (FS Procurement Note 17-001) (JAN 2017)

SECTION C - DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF WORK

C.2 LOCATION OF PROJECT

C.3 CONTRACT TIME AND ESTIMATED START WORK DATE

C.4 PRICE RANGE

C.5 ESTIMATED START DATE

C.7 Attachments to Statement of Work/Specifications, AGAR 452.211-73 (FEB 1988)

C.8 Special Project Specification List

SECTION D – GOVERNMENT FURNISHED PROPERTY

SECTION E - INSPECTION AND ACCEPTANCE

E.1 Inspection of Construction FAR 52.246-12 (AUG 1996)

SECTION F - DELIVERIES OR PERFORMANCE

F.1 Clauses Incorporated by Reference, FAR 52.252-2 (FEB 1998)

F.2 Commencement, Prosecution, and Completion of Work, FAR 52.211-10 (APR 1984)

F.3 Schedules for Construction Contracts, FAR 52.236-15 (APR 1984)

SECTION G - CONTRACT ADMINISTRATION DATA

G.1 Postaward Conference, AGAR 452.215-73 (NOV 1996)

SECTION H - SPECIAL CONTRACT REQUIREMENTS

H.1 Emergency Response, AGAR 452.236-77 (NOV 1996)

H.2 Invoice Processing Platform (IPP)

PART II – CONTRACT CLAUSES

SECTION I - CONTRACT CLAUSES

I.1 Clauses Incorporated by Reference, FAR 52.252-2 (FEB 1998)

I.2 Affirmative Procurement of Biobased Products under Service and Construction Contracts, FAR 52.223-2

(SEP 2013)

I.3 Buy American—Construction Materials. FAR 52.225-9 (MAY 2014)

I.4 Bid Guarantee, FAR 52.228-1 (SEP 1996)

PART III – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

SECTION J - LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

NCSC Ops Roofing Project, Northern California Service Center - 5 -

J.1 Attachments to Statements of Work/Specifications, AGAR 452.211-73 (FEB 1988)

PART IV – REPRESENTATIONS AND INSTRUCTIONS

SECTION K - REPRESENTATIONS, CERTIFICATIONS, AND OTHER STATEMENTS OF OFFERORS

K.1 Biobased Product Certification, FAR 52.223-1 (MAY 2012)

K.2 Annual Representations and Certifications, FAR 52.204-8 (JAN 2017)

K.3 Size Standard and NAICS Code Information, AGAR 452.219-70 (SEP 2001)

SECTION L - INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR RESPONDENTS

L.1 Inquiries AGAR 452.204-70 (FEB 1988)

L.2 System for Award Management, FAR 52.204-7 (OCT 2016)

L.4 Instructions to Offerors—Competitive Acquisition, FAR 52.215-1 (JAN 2017)

L.5 Type of Contract, FAR 52.216-1 (APR 1984)

L.6 Notice of Requirement for Affirmative Action to Ensure Equal Employment Opportunity for Construction, FAR 52.222-23 (FEB 1999)

L.7 Notice of Buy American Act Requirement - Construction Materials, FAR 52.225-10 (MAY 2014)

L.8 Service of Protest, FAR 52.233-2 (SEP 2006)

L.9 Preparation of Proposals – Construction, FAR 52.236-28 (OCT 1997)

L.10 Instructions for the Preparation of Technical and Business Proposals

L.11 Site Visit, FAR 52.237-1 (Apr 1984)

SECTION M - EVALUATION FACTORS FOR AWARD

M.1 FAR 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)

NCSC Ops Roofing Project, Northern California Service Center - 6 -

PART I - SCHEDULE OF ITEMS

SECTION B - Supplies or Services and Prices/Costs Schedule of Items

NCSC Operations Roof Replacement Northern California Service Center

Schedule A

Item No. Description Qty Unit Price

01 Roof System Replacement 1 LS

OR

Schedule B

Item No. Description Qty Unit Price

01 Roof System Replacement 1 LS 02 Roof Deck Fire Rating – Class A 1 LS

Total Price

****The Government will only award one of the above schedules at time of award, pricing on both schedules is required or your firm’s proposal will be rejected as unacceptable.

B.1 Note Regarding Bond Premiums Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price. Include bond payments under

151.01 Mobilization. Payment will be made on actual work performed as described in FP-03 109.01 unless otherwise noted

B.2 Availability of Funds – (FS Procurement Note 17-001) (JAN 2017) Notice to Offeror(s)/Supplier(s): Funds are not presently available for this effort. No award will be made under this solicitation until funds are available. The Government reserves the right to cancel this solicitation, either before or after the solicitation’s closing date. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs incurred.”

NCSC Ops Roofing Project, Northern California Service Center - 7 -

SECTION C - Description/Specifications/Statement of Work

C.1 SCOPE OF WORK

The contractor shall provide labor, materials, equipment, and supervision for this project which includes the removal and installation of approximately 31,000 square feet of roof and modifying the existing roof slope for positive discharge into the drains on Northern California Service Center (NCSC) Operations, building number 2240. See Project specifications.

C.2 LOCATION OF PROJECT

The project is located at the Northern California Service Center Compound (40° 30’ 58.68” N, 122° 17’ 56.12” W) 6101 Airport Rd. Redding, CA 96002 in the county of Shasta.

C.3 CONTRACT TIME AND ESTIMATED START WORK DATE

Contract time is 45 calendar days. Notice to Proceed will be issued on or around July 15, 2017 unless arranged otherwise between the contractor and the Contracting Officer.

C.4 PRICE RANGE

The Government's estimate is between $250,000 and $500,000. This range includes all items.

C.5 ESTIMATED START DATE

The estimated start date is July 15, 2017. Contractor must begin work within 10 days of the effective date of the Notice to Proceed. See Section F for additional information.

C.7 Attachments to Statement of Work/Specifications, AGAR 452.211-73 (FEB 1988) The attachments to the Statement of Work/Specifications listed in Section J are hereby made a part of this solicitation and any resultant contract.

C.8 Special Project Specification List The special project specifications applicable to this solicitation are in Section J. as a separate attachment.

See Table of Contents at front of special project specifications for list of included special project specifications.

NCSC Ops Roofing Project, Northern California Service Center - 8 -

SECTION D – Government Furnished Property

Government-Furnished Materials - NONE

SECTION E - Inspection and Acceptance

E.1 Inspection of Construction FAR 52.246-12 (AUG 1996)

(a) Definition. “Work” includes, but is not limited to, materials, workmanship, and manufacture and fabrication of components.

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirements. The Contractor shall maintain complete inspection records and make them available to the Government. All work shall be conducted under the general direction of the Contracting Officer and is subject to Government inspection and test at all places and at all reasonable times before acceptance to ensure strict compliance with the terms of the contract.

(c) Government inspections and tests are for the sole benefit of the Government and do not—

(1) Relieve the Contractor of responsibility for providing adequate quality control measures;

(2) Relieve the Contractor of responsibility for damage to or loss of the material before acceptance;

(3) Constitute or imply acceptance; or

(4) Affect the continuing rights of the Government after acceptance of the completed work under paragraph (i) of this section.

(d) The presence or absence of a Government inspector does not relieve the Contractor from any contract requirement, nor is the inspector authorized to change any term or condition of the specification without the Contracting Officer’s written authorization.

(e) The Contractor shall promptly furnish, at no increase in contract price, all facilities, labor, and material reasonably needed for performing such safe and convenient inspections and tests as may be required by the Contracting Officer. The Government may charge to the Contractor any additional cost of inspection or test when work is not ready at the time specified by the Contractor for inspection or test, or when prior rejection makes reinspection or retest necessary. The Government shall perform all inspections and tests in a manner that will not unnecessarily delay the work. Special, full size, and performance tests shall be performed as described in the contract.

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government consents to accept the work with an appropriate adjustment in contract price. The Contractor shall promptly segregate and remove rejected material from the premises.

(g) If the Contractor does not promptly replace or correct rejected work, the Government may—

(1) By contract or otherwise, replace or correct the work and charge the cost to the Contractor; or

(2) Terminate for default the Contractor’s right to proceed.

(h) If, before acceptance of the entire work, the Government decides to examine already completed work by removing it or tearing it out, the Contractor, on request, shall promptly furnish all necessary facilities, labor, and material. If the work is found to be defective or nonconforming in any material respect due to the fault of the Contractor or its subcontractors, the Contractor shall defray the expenses of the examination and of satisfactory reconstruction. However, if the work is found to meet contract requirements, the Contracting Officer shall make an equitable adjustment for the additional services

NCSC Ops Roofing Project, Northern California Service Center - 9 -involved in the examination and reconstruction, including, if completion of the work was thereby delayed, an extension of time.

(i) Unless otherwise specified in the contract, the Government shall accept, as promptly as practicable after completion and inspection, all work required by the contract or that portion of the work the Contracting Officer determines can be accepted separately. Acceptance shall be final and conclusive except for latent defects, fraud, gross mistakes amounting to fraud, or the Government’s rights under any warranty or guarantee.

SECTION F - Deliveries or Performance

F.1 Clauses Incorporated by Reference, FAR 52.252-2 (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.acquisition.gov/far/ www.usda.gov/procurement/policy/agar.html

Variation in Estimated Quantity, FAR 52.211-18 (APR 1984) Suspension of Work, FAR 52.242-14 (APR 1984)

F.2 Commencement, Prosecution, and Completion of Work, FAR 52.211-10 (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 45 calendar days. If options are awarded there will be an increase in contract time (see Section C). The time stated for completion shall include final cleanup of the premises.

F.3 Schedules for Construction Contracts, FAR 52.236-15 (APR 1984)

(a) The Contractor shall, within five days after the work commences on the contract or another period of time determined by the Contracting Officer, prepare and submit to the Contracting Officer for approval three copies of a practicable schedule showing the order in which the Contractor proposes to perform the work, and the dates on which the Contractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Contractor fails to submit a schedule within the time prescribed, the Contracting Officer may withhold approval of progress payments until the Contractor submits the required schedule.

(b) The Contractor shall enter the actual progress on the chart as directed by the Contracting Officer, and upon doing so shall immediately deliver three copies of the annotated schedule to the Contracting Officer.

If, in the opinion of the Contracting Officer, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules in chart form as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.

(c) Failure of the Contractor to comply with the requirements of the Contracting Officer under this clause http://www.acquisition.gov/far/ http://www.usda.gov/procurement/policy/agar.html

NCSC Ops Roofing Project, Northern California Service Center - 10 -shall be grounds for a determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor’s right to proceed with the work, or any separable part of it, in accordance with the default terms of this contract.

SECTION G - Contract Administration Data

G.1 Postaward Conference, AGAR 452.215-73 (NOV 1996) A post award conference with the successful offeror is required. The conference will be held at a mutually agreeable location and time.

SECTION H - Special Contract Requirements

H.1 Emergency Response, AGAR 452.236-77 (NOV 1996)

(a) Contractor's Responsibility for Fire Fighting. (1) The Contractor, under the provisions of FAR clause 52.236-9, PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS, shall immediately extinguish all fires on the work site other than those fires in use as a part of the work. (2) The Contractor may be held liable for all damages and for all costs incurred by the Government for labor, subsistence, equipment, supplies, and transportation deemed necessary to control or suppress a fire set or caused by the Contractor or the Contractor's agents or employees.

(b) Contractor's Responsibility for Notification in Case of Fire. The Contractor shall immediately notify the Government of any fires sighted on or in the vicinity of the work site.

(c) Contractor's Responsibility for Responding to Emergencies. When directed by the Contracting Officer, the Contractor shall allow the Government to temporarily use employees and equipment from the work site for emergency work (anticipated to be restricted to firefighting). An equitable adjustment for the temporary use of employees and equipment will be made under the CHANGES clause, FAR 52.243-4.

H.2 Invoice Processing Platform (IPP)

INVOICE SUBMISSION PROCEDURES

The "Submit Invoice-to" address for invoices on USDA orders is the Department of Treasury's Invoice Processing Platform (IPP). All invoices for work performed under this contract shall be submitted via the electronic Invoice Processing Platform. This platform is managed by the U.S. Department of Treasury and additional information is available at this website: https://www.ipp.gov/index.htm.

After award of a contract, please make sure your company registers promptly at https://www.ipp.gov/vendors/enrollment-vendors.htm to establish an account, there is no pre-award registration. PRIOR to starting the IPP enrollment process, please verify that the point of contact’s (POC’s) email address is current in the System for Award Management (SAM) account for your company (www.sam.gov). Recent update(s) to a SAM registration need time to process from a “Pending” to in an “Active” status on the SAM account. The one-time enrollment in IPP means a series of emails will be sent to the POC identified in the SAM account. For assistance with questions on the IPP enrollment process, creating invoices, or uploading attachments to IPP please contact the IPP help desk phone number is 1- 866-973-3131.

https://www.ipp.gov/index.htm https://www.ipp.gov/vendors/enrollment-vendors.htm http://www.sam.gov/

NCSC Ops Roofing Project, Northern California Service Center - 11 -

Invoices in IPP are the official request for payment. Supporting information is required for all construction progress payments and shall be attached to the IPP invoice.

• The payment certification required in FAR 52.232-5 Payments under Fixed-Price Construction Contracts must be signed and submitted for each progress payment requested,

• A breakdown of billing, based on the pricing schedule along with the progress schedule, must be included as attachments to the IPP invoice.

Additionally, the government will verify the contractor’s compliance with the submission of certified payrolls for the invoiced timeframe as required in FAR Clause 52.222-8 Payrolls and Basic Records. The Contractor shall submit payrolls weekly for each week in which any contract work is performed by the prime or any subcontractors. The copies shall be sent to the COR. Payrolls submitted shall set out accurately and completely all of the information required in the contract clause (form WH-347 is an optional form compliant with the requirement and is available for download at www.dol.gov). State or County government forms lack the specific certification requirement and are not acceptable without supplementation of the certification statement.

Invoices not complying with contract requirements will be rejected.

http://www.dol.gov/

NCSC Ops Roofing Project, Northern California Service Center - 12 -

PART II – CONTRACT CLAUSES

SECTION I - Contract Clauses

I.1 Clauses Incorporated by Reference, FAR 52.252-2 (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

http://www.acquisition.gov/far https://www.dm.usda.gov/procurement/policy/agar.htm

FEDERAL ACQUISITION REGULATIONS (FAR)

52.202-1 Definitions. (NOV 2013) 52.203-3 Gratuities. (APR 1984) 52.203-5 Covenant against Contingent Fees. (MAY 2014) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (OCT 2010) 52.204-4 Printed or Copied Double-Sided on Postconsumer Fiber Content Paper. (May 2011) 52.209-6 Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (OCT 2015) 52.215-2 Audit and Records - Negotiation (OCT 2010) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2011) 52.219-14 Limitations on Subcontracting. (NOV 2017) 52.219-28 Post-Award Small Business Program Representations (JUL 2013) 52.222-3 Convict Labor (JUN 2003) 52.222-4 Contract Work Hours and Safety Standards Act - Overtime Compensation (MAY 2014) 52.222-5 Davis-Bacon Act--Secondary Site of the Work. (MAY 2014) 52.222-6 Davis-Bacon Act. (MAY 2014) 52.222-7 Withholding of Funds (MAY 2014) 52.222-8 Payrolls and Basic Records (MAY 2014) 52.222-9 Apprentices and Trainees (JUL 2005) 52.222-10 Compliance with Copeland Act Requirements (FEB 1988) 52.222-11 Subcontracts (Labor Standards) (MAY 2014) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Davis-Bacon and Related Act Regulations (MAY 2014) 52.222-14 Disputes Concerning Labor Standards (FEB 1988) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-21 Prohibition of Segregated Facilities (APR 2015) 52.222-26 Equal Opportunity (SEP 2016) 52.222-27 Affirmative Action Compliance Requirements for Construction (APR 2015) 52.222-35 Equal Opportunity for Veterans (OCT 2015) 52.222-36 Equal Opportunity Action for Workers with Disabilities (JUL 2014) 52.222-37 Employment Reports on Veterans (FEB 2016) 52.222-50 Combating Trafficking in Persons (MAR 2015) 52.222-55 Minimum Wages under Executive Order 13658 (DEC 2015) 52.223-6 Drug-Free Workplace. (MAY 2001) 52.225-13 Restrictions on Certain Foreign Purchases (JUN 2008) http://www.acquisition.gov/far https://www.dm.usda.gov/procurement/policy/agar.htm

NCSC Ops Roofing Project, Northern California Service Center - 13 -

52.227-1 Authorization and Consent. (DEC 2007) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (DEC 2007) 52.227-4 Patent Indemnity--Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-11 Pledges of Assets. (JAN 2012) 52.228-12 Prospective Subcontractor Requests for Bonds (MAY 2014) 52.228-14 Irrevocable Letter of Credit. (NOV 2014) 52.228-15 Performance and Payment Bonds - Construction. (OCT 2010) 52.229-3 Federal, State, and Local Taxes. (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts. (MAY 2014) 52.232-17 Interest. (MAY 2014) 52.232-18 Availability of Funds (APR 1984) 52.232-23 Assignment of Claims. (MAY 2014) 52.232-27 Prompt Payment For Construction Contracts. (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer - Central Contractor Registration. (JUL 2013) 52.233-1 Disputes. (MAY 2014) 52.233-3 Protest after Award. (AUG 1996) 52.233-4 Applicable Law for Breach of Contract Claim. (OCT 2004) 52.236-2 Differing Site Conditions. (APR 1984) 52.236-3 Site Investigation and Conditions Affecting the Work. (APR 1984) 52.236-5 Material and Workmanship. (APR 1984) 52.236-6 Superintendence by the Contractor. (APR 1984) 52.236-7 Permits and Responsibilities. (NOV 1991) 52.236-8 Other Contracts. (APR 1984) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements. (APR

1984) 52.236-10 Operations and Storage Areas. (APR 1984) 52.236-11 Use and Possession Prior to Completion. (APR 1984) 52.236-12 Cleaning Up. (APR 1984) 52.236-13 Accident Prevention. (NOV 1991) 52.236-15 Schedules for Construction Contracts. (APR 1984) 52.236-21 Specifications and Drawings for Construction (FEB 1997) 52.242-13 Bankruptcy. (JUL 1995) 52.243-4 Changes. (JUN 2007) 52.246-21 Warranty of Construction. (MAR 1994) 52.248-3 Value Engineering - Construction. (OCT 2015) 52.249-2 Termination for Convenience of the Government (Fixed-Price). (APR 2012) 52.249-10 Default (Fixed-Price Construction). (APR 1984) 52.253-1 Computer Generated Forms. (JAN 1991)

AGRICULTURE ACQUISITION REGULATION

452.232-70 Reimbursement for Bond Premiums - Fixed-Price Construction Contracts. (NOV 1996) 452.236-72 Use of Premises. (NOV 1996) 452.236-73 Archaeological or Historic Sites. (FEB 1988) 452.236-74 Control of Erosion, Sedimentation, and Pollution. (NOV 1996) 452.236-76 Samples and Certificates. (FEB 1988)

NCSC Ops Roofing Project, Northern California Service Center - 14 -

I.2 Affirmative Procurement of Biobased Products under Service and Construction Contracts, FAR 52.223-2 (SEP 2013)

(a) In the performance of this contract, the contractor shall make maximum use of biobased products that are United States Department of Agriculture (USDA)-designated items unless—

(1) The product cannot be acquired—

(i) Competitively within a time frame providing for compliance with the contract performance schedule;

(ii) Meeting contract performance requirements; or

(iii) At a reasonable price.

(2) The product is to be used in an application covered by a USDA categorical exemption (see 7 CFR 3201.3(e)). For example, all USDA-designated items are exempt from the preferred procurement requirement for the following:

(i) Spacecraft system and launch support equipment.

(ii) Military equipment, i.e., a product or system designed or procured for combat or combat-related missions.

(b) Information about this requirement and these products is available at http://www.biopreferred.gov.

(c) In the performance of this contract, the Contractor shall—

(1) Report to http://www.sam.gov, with a copy to the Contracting Officer, on the product types and dollar value of any USDA-designated biobased products purchased by the Contractor during the previous Government fiscal year, between October 1 and September 30; and

(2) Submit this report no later than—

(i) October 31 of each year during contract performance; and

(ii) At the end of contract performance.

I.3 Buy American—Construction Materials. FAR 52.225-9 (MAY 2014)

(a) Definitions. As used in this clause— “Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material.

“Construction material” means an article, material, or supply brought to the construction site by the

Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means—

(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means— http://www.biopreferred.gov/ http://www.sam.gov/ http://www.acquisition.gov/far/current/html/Subpart%202_1.html#wp1145508 http://uscode.house.gov/

NCSC Ops Roofing Project, Northern California Service Center - 15 -

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or

(ii) The construction material is a COTS item.

“Foreign construction material” means a construction material other than a domestic construction material.

“United States” means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: NONE

[Contracting Officer to list applicable excepted materials or indicate “none”]

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that—

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American statute is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American statute to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American statute.

(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis http://uscode.house.gov/ http://uscode.house.gov/ http://www.acquisition.gov/far/current/html/Subpart%2012_5.html#wp1077123

NCSC Ops Roofing Project, Northern California Service Center - 16 -for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

FOREIGN AND DOMESTIC CONSTRUCTION MATERIALS PRICE COMPARISON

Construction Material Description Unit of Measure Quantity Price (Dollars)* Item 1:

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______

Item 2: _______ _______ _______ Foreign construction material _______ _______ _______ Domestic construction material [List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.] [* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]

I.4 Bid Guarantee, FAR 52.228-1 (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds -

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3 Million, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

NCSC Ops Roofing Project, Northern California Service Center - 17 -

PART III – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

SECTION J - List of Documents, Exhibits, and Other Attachments

J.1 Attachments to Statements of Work/Specifications, AGAR 452.211-73 (FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

Attachment No. Description Number of Pages

1 Project Specifications 13

2 Plans 4

4 Davis Bacon WD, mod 11, dated 06/02/2017 43

5 SF-24, Bid Bond Form 2

NCSC Ops Roofing Project, Northern California Service Center - 18 -

PART IV – REPRESENTATIONS AND INSTRUCTIONS

SECTION K - Representations, Certifications, and Other Statements of Offerors

K.1 Biobased Product Certification, FAR 52.223-1 (MAY 2012) As required by the Farm Security and Rural Investment Act of 2002 and the Energy Policy Act of 2005

(7 U.S.C. 8102(c)(3)), the offeror certifies, by signing this offer, that biobased products (within categories of products listed by the United States Department of Agriculture in 7 CFR part 3201, subpart B) to be used or delivered in the performance of the contract, other than biobased products that are not purchased by the offeror as a direct result of this contract, will comply with the applicable specifications or other contractual requirements

K.2 Annual Representations and Certifications, FAR 52.204-8 (JAN 2017) (a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 238160.

(2) The small business size standard is $15.0 Million.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the provision at 52.204-7, System for Award Management, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the provision at 52.204-7 is not included in this solicitation, and the offeror is currently registered in the System for Award Management (SAM), and has completed the Representations and Certifications section of SAM electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:

□ (i) Paragraph (d) applies.

□ (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in SAM are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.203-18, Prohibition on Contracting with Entities that Require Certain Internal Confidentiality Agreements or Statements-Representation. This provision applies to all solicitations.

(iv) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the provision at 52.204-7, System for Award Management.

(v) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

http://uscode.house.gov/ https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1137850 https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1137850 https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1137583 https://www.acquisition.gov/sites/default/files/current/far/html/FARTOCP13.html#wp271421 https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1137684 https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1150648 https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1137777 https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1137850 https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1149919

NCSC Ops Roofing Project, Northern California Service Center - 19 -

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(vi) 52.209-2, Prohibition on Contracting with Inverted Domestic Corporations—Representation.

(vii) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(viii) 52.209-11, Representation by Corporations Regarding Delinquent Tax Liability or a Felony

Conviction under any Federal Law. This provision applies to all solicitations.

(ix) 52.214-14, Place of Performance—Sealed Bidding. This provision applies to invitations for bids except those in which the place of performance is specified by the Government.

(x) 52.215-6, Place of Performance. This provision applies to solicitations unless the place of performance is specified by the Government.

(xi) 52.219-1, Small Business Program Representations (Basic & Alternate I). This provision applies to solicitations when the contract will be performed in the United States or its outlying areas.

(A) The basic provision applies when the solicitations are issued by other than DoD, NASA, and the Coast Guard.

(B) The provision with its Alternate I applies to solicitations issued by DoD, NASA, or the Coast

Guard.

(xii) 52.219-2, Equal Low Bids. This provision applies to solicitations when contracting by sealed bidding and the contract will be performed in the United States or its outlying areas.

(xiii) 52.222-22, Previous Contracts and Compliance Reports. This provision applies to solicitations that include the clause at 52.222-26, Equal Opportunity.

(xiv) 52.222-25, Affirmative Action Compliance.This provision applies to solicitations, other than those for construction, when the solicitation includes the clause at 52.222-26, Equal Opportunity.

(xv) 52.222-38, Compliance with Veterans’ Employment Reporting Requirements. This provision applies to solicitations when it is anticipated the contract award will exceed the simplified acquisition threshold and the contract is not for acquisition of commercial items.

(xvi) 52.222-57, Representation Regarding Compliance with Labor Laws (Executive Order 13673).

This provision applies to solicitations expected to exceed $50 million which are issued from October 25, 2016 through April 24, 2017, and solicitations expected to exceed $500,000, which are issued after April 24, 2017.

Note to paragraph (c)(1)(xvi): By a court order issued on October 24, 2016, 52.222-57 is enjoined indefinitely as of the date of the order. The enjoined paragraph will become effective immediately if the court terminates the injunction. At that time, GSA, DoD and NASA will publish a document in the Federal Register advising the public of the termination of the injunction.

(xvii) 52.223-1, Biobased Product Certification. This provision applies to solicitations that require the delivery or specify the use of USDA–designated items; or include the clause at 52.223-2, Affirmative Procurement of Biobased Products Under Service and Construction Contracts.

(xviii) 52.223-4, Recovered Material Certification. This provision applies to solicitations that are for, or specify the use of, EPA–designated items.

(xix) 52.223-22, Public Disclosure of Greenhouse Gas Emissions and Reduction Goals– Representation. This provision applies to solicitation that include the clause at 52.204-7.

(xx) 52.225-2, Buy American Certificate. This provision applies to solicitations containing the clause at 52.225-1.

(xxi) 52.225-4, Buy American—Free Trade Agreements—Israeli Trade Act Certificate. (Basic, Alternates I, II, and III.) This provision applies to solicitations containing the clause at 52.225-3.

(A) If the acquisition value is less than $25,000, the basic provision applies.

https://www.acquisition.gov/sites/default/files/current/far/html/52_207_211.html#wp1144766 https://www.acquisition.gov/sites/default/files/current/far/html/52_207_211.html#wp1144909 https://www.acquisition.gov/sites/default/files/current/far/html/52_207_211.html#wp1146404 https://www.acquisition.gov/sites/default/files/current/far/html/52_214.html#wp1129381 https://www.acquisition.gov/sites/default/files/current/far/html/52_215.html#wp1144523 https://www.acquisition.gov/sites/default/files/current/far/html/52_217_221.html#wp1135900 https://www.acquisition.gov/sites/default/files/current/far/html/52_217_221.html#wp1135943 https://www.acquisition.gov/sites/default/files/current/far/html/52_222.html#wp1147663 https://www.acquisition.gov/sites/default/files/current/far/html/52_222.html#wp1147711 https://www.acquisition.gov/sites/default/files/current/far/html/52_222.html#wp1147704 https://www.acquisition.gov/sites/default/files/current/far/html/52_222.html#wp1147711 https://www.acquisition.gov/sites/default/files/current/far/html/52_222.html#wp1148142 https://www.acquisition.gov/sites/default/files/current/far/html/52_222.html#wp1168958 https://www.acquisition.gov/sites/default/files/current/far/html/52_223_226.html#wp1168785 https://www.acquisition.gov/sites/default/files/current/far/html/52_223_226.html#wp1168786 https://www.acquisition.gov/sites/default/files/current/far/html/52_223_226.html#wp1168826 https://www.acquisition.gov/sites/default/files/current/far/html/52_223_226.html#wp1197892 https://www.acquisition.gov/sites/default/files/current/far/html/52_200_206.html#wp1137850 https://www.acquisition.gov/sites/default/files/current/far/html/52_223_226.html#wp1169013 https://www.acquisition.gov/sites/default/files/current/far/html/52_223_226.html#wp1192900 https://www.acquisition.gov/sites/default/files/current/far/html/52_223_226.html#wp1169071 https://www.acquisition.gov/sites/default/files/current/far/html/52_223_226.html#wp1169038

NCSC Ops Roofing Project, Northern California Service Center - 20 -

(B) If the acquisition value is $25,000 or more but is less than $50,000, the provision with its Alternate I applies.

(C) If the acquisition value is $50,000 or more but is less than $77,533, the provision with its Alternate II applies.

(D) If the acquisition value is $77,533 or more but is less than $100,000, the provision with its Alternate III applies.

(xxii) 52.225-6, Trade Agreements Certificate. This provision applies to solicitations containing the clause at 52.225-5.

(xxiii) 52.225-20, Prohibition on Conducting Restricted Business Operations in Sudan— Certification. This provision applies to all solicitations.

(xxiv) 52.225-25, Prohibition on Contracting with Entities Engaging in Certain Activities or Transactions Relating to Iran-Representation and Certifications. This provision applies to all solicitations.

(xxv) 52.226-2, Historically Black College or University and Minority Institution Representation.

This provision applies to solicitations for research, studies, supplies, or services of the type normally acquired from higher educational institutions.

(2) The following representations or certifications are applicable as indicated by the Contracting Officer:

[Contracting Officer check as appropriate.] __ (i) 52.204-17, Ownership or Control of Offeror.

__ (ii) 52.204-20, Predecessor of Offeror.

__ (iii) 52.222-18, Certification Regarding Knowledge of Child Labor for Listed End Products.

__ (iv) 52.222-48, Exemption from Application of the Service Contract Labor Standards to

Contracts for Maintenance, Calibration, or Repair of Certain Equipment- Certification.

__ (v) 52.222-52, Exemption from Application of the Service Contract Labor…