Solicitation.pdf

PDF 315 KB Posted

Attached to
Gallatin Low Water Boat Ramp
Solicitation number
AG-9AC7-S-11-0002
Issued by

About this file

Solicitation

View the file

Other files

File Type Posted
Amendment Two.pdf PDF
Drawings.pdf PDF
Specs.pdf PDF
Fire Plan.pdf PDF
Return Package.pdf PDF
DAVIS BACON Gallatin Low Water Boat Ramp - 2-02-11.pdf PDF
sf-30.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OMB APPROVAL NO. 2700-0042

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

AG-9AC7-S-11-0002

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED

3/25/2011

PAGE OF PAGES

IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST NO.

6. PROJECT NO.

7. ISSUED BY CODE 8. ADDRESS OFFER TO

Northern California Acquisition Service Area Lassen National Forest 2550 Riverside Drive Susanville, CA 96130

9. FOR INFORMATION

CALL:

A. NAME

Leslie Solberg

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

(530) 252-6657

SOLICITATION

NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

Low Water Boat Ramp, Lassen National Forest

Price Range: Between $100,000 and $250,000.

HUBZONE Set-Aside

NAICS Code: 237990, Size Standard: $33.5 million

TAX ID NO.__________________________

DUNS NO.___________________________

Email:_______________________________

11. The Contractor shall begin performance within 10 calendar days and complete it within 60 calendar days after receiving award, notice to proceed. This performance period is mandatory, negotiable. (See .)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12B.)

YES NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and 1 copy to perform the work required are due at the place specified in Item 8 by 4:30pm local time on Monday, April 25, 2011. If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Computer Generated Prescribed by GSA FAR (48 CFR) 53.236-1(e)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER

(Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

COR

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract.

The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED

TO SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

30B. SIGNATURE

30C. DATE

31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)

Solicitation Number: AG-9AC7-S-11-0002 PAGE 3 of 34 Project Name: Gallatin Low Water Boat Ramp

TABLE OF CONTENTS

PART I

SECTION A - SOLICITATION, OFFER, AND AWARD

TABLE OF CONTENTS

SECTION B – SCHEDULE OF ITEMS

SECTION C – DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK... 5

SECTION E – INSPECTION AND ACCEPTANCE

SECTION F – DELIVERIES OR PERFORMANCE

SECTION G - CONTRACT ADMINISTRATION DATA

PART II

SECTION I – CONTRACT CLAUSES

PART III

SECTION J – LIST OF ATTACHMENTS

PART IV

SECTION K – REPRESENTATIONS AND INSTRUCTIONS

SECTION L – INSTRUCTIONS, CONDITIONS, AND NOTICES

INSTRUCTIONS FOR SUBMISSION OF OFFERS

SECTION M – EVALUATION FACTORS FOR AWARD

RESPONSE TO EVALUATION FACTORS

SEPARATE:

SPECIFICATIONS (SEE LIST OF SPECIFICATIONS)

DRAWINGS (SEE LIST OF ATTACHMENTS, PAGE 18)

FIRE PLAN

DAVIS BACON WAGE DETERMINATION

Solicitation Number: AG-9AC7-S-11-0002 PAGE 4 of 34

PART I—THE SCHEDULE

SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS SCHEDULE OF ITEMS

Name of Offeror or Contractor

ITEM NO. DESCRIPTION METHOD OF

MEASURE

QUANTITY PAY UNIT UNIT PRICE TOTAL

Base Bid items 1-14 1 Mobilization LSQ 1 LS

2 Construction Survey and Staking: New Construction

DQ .07 Mile $__________

3 Clearing and Grubbing DQ .07 Mile $__________

4 Site Grading (Excavation and Embankment)

DQ 312.5 CY $__________

5 Grading DQ 765 SY $__________

6 Install 8” V-groove Precast Concrete Panel

DQ 1600 SF $__________

7 Precast Concrete Grade Beam DQ 2 EA $__________

8 Misc. stainless steel anchor and end panel connectors and related hardware

LSQ 1 LS

9 Aggregate Base DQ 210 CY $__________

10 Riprap and Filter Fabric DQ 70 CY $__________

11 Turbidity Curtain DQ 370 LF $__________

12 Cast-in Place Concrete Apron DQ 9 CY $__________

13 Cast-In-Place Concrete Anchor DQ 2 CY $__________ $__________

BASE BID SUBTOTAL (1-13)

Option 1 Furnish and install Double Pipe Gate

DQ 1 EA

TOTAL BID

Solicitation Number: AG-9AC7-S-11-0002 PAGE 5 of 34

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 DESCRIPTION OF WORK

A. This project consists of constructing a Low Water Boat Ramp for the United States Department of Agriculture (USDA) Forest Service (FS) as shown on the contract documents.

B. The Work consists of the following:

1. The Work includes clearing, earthwork, and construction of a native material access road, installation of 80 feet of V-groove concrete panels and riprap, and an option to install a medium weight road closure gate.

2. Furnish, install and maintain barriers and construction signs to protect existing facilities and the public from construction operations. Ensure public safety by using fence, barricade or otherwise block off immediate work area to prevent unauthorized entry.

C.2 PROJECT LOCATION

A. All work is located at the Gallatin Marina on the Lassen National Forest (NF). The project is located approximately 20 miles northwest of Susanville, California on the south side of Eagle Lake on the Eagle Lake Ranger District of the Lassen NF. The project area is accessed via National Forest System Road (NFSR) 31N02 and located in T31N, R11E, Sec. 7 of Lassen County.

AGAR 452.211-73 ATTACHMENTS TO STATEMENT OF WORK/SPECIFICATIONS

(FEB 1988)

The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.

SECTION D--PACKAGING AND MARKING

For this Solicitation, there are NO clauses in this Section.

SECTION E--INSPECTION AND ACCEPTANCE

FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

Clause Number Title Date 52.246-12 Inspection of Construction AUG 1996 http://www.arnet.gov/far/� http://www.usda.gov/procurement/policy/agar.html�

Solicitation Number: AG-9AC7-S-11-0002 PAGE 6 of 34

FINAL CLEANUP

Before final acceptance, all areas occupied by the Contractor in connection with the work shall be cleaned of all Contractor's rubbish, excess materials, temporary structures, and equipment, and all parts of the work area shall be left in a neat and presentable condition.

SECTION F--DELIVERIES OR PERFORMANCE

FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.242-14 Suspension of Work APR 1984

FAR 52.211-10 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK

(APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 60 calendar days.

The time stated for completion shall include final cleanup of the premises. Work is estimated to begin on July 5, 2011.

AGAR 452.236-75 MAXIMUM WORKWEEK-CONSTRUCTION (NOV 1996)

Within five calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in writing for approval:

(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and

(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposed to carry out the work.

The maximum workweek that will be approved is: During the period from May 30 (Memorial Day) to September 2 (Labor Day), Monday through Friday, 8:00 a.m. to 6:00 p.m.

SECTION G--CONTRACT ADMINISTRATION DATA

DESIGNATION OF CONTRACTING OFFICER'S REPRESENTATIVE

The Contracting Officer designates the Contracting Officer's Representative(s) (COR). The COR is responsible for administering the performance of work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless

Solicitation Number: AG-9AC7-S-11-0002 PAGE 7 of 34 formalized by proper contractual documents executed by the Contracting Officer prior to completion of the contract.

The Contracting Officer should be informed as soon as possible of any actions or inactions by the Contractor or the Government which will change the required delivery or completion times stated in the contract, and the contract will be modified accordingly. (This does not apply to individual task assignments which were issued by the COR provided they do not affect the delivery schedule or performance period stated in the contract.)

On all matters that pertain to the contract terms, the Contractor must communicate with the Contracting Officer. Whenever, in the opinion of the Contractor, the COR requests effort outside the scope of the contract, the Contractor should so advise the COR. If the COR persists and there still exists a disagreement as to proper contractual coverage, the Contracting Officer should be notified immediately, preferably in writing if time permits. Proceeding with work without proper contractual coverage could result in nonpayment or necessitate submittal of a contract claim.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

FAR 52.236-14 AVAILABILITY AND USE OF UTILITY SERVICES (APR 1984)

(a) The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. Unless otherwise provided in the contract, the amount of each utility service consumed shall be charged to or paid for by the Contractor at prevailing rates charged to the Government or, where the utility is produced by the Government, at reasonable rates determined by the Contracting Officer. The Contractor shall carefully conserve any utilities furnished without charge.

(b) The Contractor, at its expense and in a workmanlike manner satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of each utility used for the purpose of determining charges. Before final acceptance of the work by the Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia.

PRODUCT SUBSTITUTION

Any modification of other items, designs, materials, products or equipment (including Government-furnished property), made necessary because of a substitution, will be the responsibility of the Contractor without adjustment in contract price or time. The Contracting Officer's approval of any substitute will not affect the Contractor's responsibility for such modification. Any and all substitutions will be requested by the Contractor after award of the contract has been made. No approvals will be made prior to award.

A. When submitted within 30 days after contract award, the Contracting Officer will consider formal requests for substitution of products, equipment and methods, in place of those specified.

Requests submitted after 30 days will be considered only in case of product unavailability or other conditions beyond the control of Contractor. Requests shall provide the information and be in the format as specified in paragraph B below.

Solicitation Number: AG-9AC7-S-11-0002 PAGE 8 of 34

B. Submit separate request for each substitution. Support each request with:

1. Complete data substantiating compliance of proposed substitution with requirements stated in contract documents:

a. Product identification, including manufacturer's name and address.

b. Manufacturer's literature; identify:

1) Product description

2) Reference standards

3) Performance and test data

c. Samples, as applicable

d. Name and address of similar projects on which product has been used, and date of each installation.

e. Comparative data of item to be deleted by proposed substitution. Include drawings to same (or larger) scale as pertinent portion of contract documents and marked to show how differences will be accommodated.

f. Show complete system/assembly as revised to accommodate proposed alternate for difference in performance, size, configuration, connections, service, accessibility, or any other significant characteristics.

g. Show complete layout of system except that which is identical to contract documents unless unchanged portion must be shown to indicate clearances, etc.

h. Include complete detail drawings of supports for all substitute equipment and complete load calculations for adequacy of support prepared and signed by a registered structural engineer.

1. Itemized comparison of the proposed substitution with product specified; list significant variations.

2. Data relating to changes in construction schedule.

3. Any effect of substitution on separate contracts.

4. List of changes required in other work or products.

5. Accurate cost data comparing proposed substitution with product specified.

6. Proposed amount of change to the contract.

7. Designation of required license fees or royalties.

8. Designation of availability of maintenance services, sources of replacement materials.

C. Substitutions will NOT be considered for acceptance when:

1. They are merely indicated or implied on shop drawings or product data submittals without a formal request from Contractor.

2. They are requested directly by a subcontractor or supplier.

3. Acceptance will require substantial revision of contract documents.

4. Substitution has not been requested in accordance with this and related clauses.

D. Substitute products shall not be ordered or installed without written acceptance of the

Contracting Officer.

Solicitation Number: AG-9AC7-S-11-0002 PAGE 9 of 34

E. Contracting Officer will determine acceptability of proposed substitutions.

F. Number of Substitution Submittals: Only one proposed alternative will be considered for each item. Provide specified item if substitution proposal is rejected.

CONTRACTOR'S REPRESENTATION & RESPONSIBILITY

A. In making formal request for substitution the Contractor represents he/she:

1. Have investigated proposed product and determined that it is equal to or superior in all respects to that originally specified.

2. Will provide same warranties and bond for substitute as for originally specified product.

3. Will coordinate installation of accepted substitution into the work, and will make such changes as may be required for the work to be complete in all respects.

4. Will waive claims for additional costs caused by substitution, which may subsequently become apparent.

5. Cost data is complete and includes related costs under the contract, but not:

a. Costs under separate contracts.

b. Contracting Officer costs for redesign or revision of contract documents.

B. The Contractor assumes full responsibility that the substitution and/or alternate items or procedures proposed will meet the job requirements.

C. The Contractor is solely responsible for the cost of redesign and modifications to this and other parts of the work caused by the substitutions or alternates furnished.

SUBMITTALS

The following shall be submitted on this project:

Title Referenced by Specification No.

Time of Government Approval After Submittal

Submittals 013300 14 days Project Closeout 017000 14 days Structural Concrete 033000 14 days Aggregate Base Course 310516 14 days Demolition and Removal 312300 14 days Rock Slope Protection 313700 14 days

SHOP DRAWINGS

The following shop drawings shall be submitted on this project:

Title Referenced by Specification No.

Time of Government Approval After Submittal

Project Closeout (As-Built Drawings) 017000 30 days

Solicitation Number: AG-9AC7-S-11-0002 PAGE 10 of 34

MATERIAL CERTIFICATIONS AND TESTING REPORTS

The following material certifications and/or testing reports shall be submitted on this project:

Title Referenced by Specification No.

Submittals 013300 Site Grading (Excavation and Embankment) 312000 Aggregate Base Course 310516 Structural Concrete 033000

AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996)

A post award conference with the successful offeror is required. It will be scheduled and held within 10 days after the date of contract award. The conference will be held at

Lassen NF Supervisors Office.

PUBLIC OFFICIALS NOT PERSONALLY LIABLE

There shall be no personal liability upon the Contracting Officer or officer in charge, their agents or employees, for any act performed in the discharge of any duty imposed or the exercise of any power or authority conferred upon them by, or within the scope of the contract, it being understood that in all such matters they act solely as agents and representatives of the Government.

LANDSCAPE PRESERVATION

The Contractor shall give attention to the effect of contract operation upon the landscape, shall take care to maintain natural surroundings undamaged, and shall conduct the work at all times in compliance with the following requirements.

a. Prevention of the Landscape Defacement. The Contractor shall not remove, deface, injure, or destroy trees, shrubs, lawns, or other natural features or any other improvements in the work area unless specifically authorized by the Contracting Officer. Unless otherwise provided herein, the Contractor shall confine contract operations to within the areas designated in contract documents.

b. Protection of Streams, Lakes, and Reservoirs. The Contractor shall take sufficient precautions to prevent pollution of streams, lakes, small ponds, and reservoirs with fuels, oils, bitumens, calcium chloride, silt, or other harmful materials. Mechanical equipment shall not be operated in live streams without written approval of the Contracting Officer.

CONTRACTOR'S USE OF EXISTING ROADS

The Contractor is authorized to use roads in the immediate construction project area for performance of work under this contract. The authorization is limited to roads necessary for direct access between the construction area and storage sites, disposal areas, and other work areas designated in the contract.

The roads authorized for use will be subject to the following general conditions:

(1) State laws governing traffic rules and equipment requirements on State and County Highways.

Solicitation Number: AG-9AC7-S-11-0002 PAGE 11 of 34

(2) Federal Regulations contained in 36 CFR 261.12. These regulations prohibit use in excess of State Codes for weight and size, damaging a road while using it, and blocking a road open to use by others.

The Contractor shall be responsible for and perform road maintenance commensurate with his use of Forest Service roads in the construction area.

ROAD MAINTENANCE REQUIREMENTS

In order to fulfill the obligation to protect existing facilities, material source, and disposal site access roads from seasonal weather damage, to safeguard soil and water quality, and to repair damage commensurate with his use, the Contractor shall perform road maintenance work on these roads in accordance with the following:

1. While performing ordinary road maintenance work, the Contractor shall avoid permanent fouling of gravel or bituminous surfaces through covering them with earth or debris from side ditches, slides, or other sources. The Contractor shall avoid blading surface material off the surface of roads.

2. While performing all phases of construction, the Contractor shall minimize damage to ditches, slopes and road surfaces. Where damage does occur, the Contractor shall restore the road to its prior condition within a reasonable period of time.

3. The Contractor shall remove all excess materials and debris from asphalt roadways and trails immediately after backfilling has been completed. This may require brooming and hosing down with water.

4. On completion and acceptance of work requirements, including acceptance of road maintenance by the Forest Service, Contractor road maintenance responsibility shall terminate.

TRAFFIC CONTROL

The Contractor shall provide, erect and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.

The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagman and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.

The Contractor shall furnish, erect, maintain, and remove when notified any project identification signs shown on the drawings

Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.

Solicitation Number: AG-9AC7-S-11-0002 PAGE 12 of 34

AGAR 452.237-74 KEY PERSONNEL (FEB 1988)

(a) The Contractor shall assign to this contract the following key personnel:

Project Manager, Site Superintendent and Quality Control Manager

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutions, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualififcations to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

SAFETY

Before starting work, the contractor shall provide a Safety Plan to the Contracting Officer which includes but is not limited to the following inherently hazardous conditions:

• Operation of equipment

• Operation of power tools

• Exposure to dust, heat and other environmental conditions

• Uneven walking surfaces

• Heavy lifting

Solicitation Number: AG-9AC7-S-11-0002 PAGE 13 of 34

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

FAR 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text.

Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

Clause No Title Date

52.202-1 DEFINITIONS JUL 2004

52.203-3 GRATUITIES APR 1984

52.203-5 COVENANT AGAINST CONTINGENT FEES APR 1984

52.203-6 RESTRICTIONS ON SUBCONTRACTOR SALES TO THE GOVERNMENT SEPT 2006

52.203-7 ANTI-KICKBACK PROCEDURES OCT 2010

52.203-8 CANCELLATION, RESCISSION, AND RECOVERY OF FUNDS FOR ILLEGAL OR IMPROPER ACTIVITY JAN 1997

52.203-10 PRICE OR FEE ADJUSTMENT FOR ILLEGAL OR IMPROPER ACTIVITY JAN 1997

52.203-12 LIMITATION ON PAYMENTS TO INFLUENCE CERTAIN FEDERAL TRANSACTIONS OCT 2010

52.204-4 PRINTED OR COPIED DOUBLE- SIDED ON RECYCLED PAPER AUG 2000

52.204-7 CENTRAL CONTRACTOR REGISTRATION APR 2008

52.209-6 PROTECTING THE GOVERNMENT'S INTEREST WHEN SUBCONTRACTING WITH CONTRACTORS DEBARRED, SUSPENDED, OR PROPOSED FOR DEBARMENT

DEC 2010

52.211-18 VARIATION IN ESTIMATED QUANTITY JUL 2005

52.215-2 AUDIT AND RECORDS -- NEGOTIATION OCT 2010

52.219-3 NOTICE OF TOTAL HUBZONE SET-ASIDE OR SOLE SOURCE AWARD JAN 2011

52.219-8 Utilization of Small Business Concerns JAN 2011

52.219-27 NOTICE OF TOTAL SERVICE-DISABLED VETERAN-OWNED SMALL BUSINESS SET-ASIDE MAY 2004

52.222-3 CONVICT LABOR JUN 2003

52.222-4 CONTRACT WORK HOURS AND SAFETY STANDARDS ACT -- OVERTIME COMPENSATION JUL 2005

52.222-6 DAVIS-BACON ACT JUL 2005

52.222-7 WITHHOLDING OF FUNDS FEB 1988

52.222-8 PAYROLLS AND BASIC RECORDS JUN 2010

52.222-9 APPRENTICES AND TRAINEES JUL 2005

52.222-10 COMPLIANCE WITH COPELAND ACT REQUIREMENTS FEB 1988

52.222-11 SUBCONTRACTS (LABOR STANDARDS) JUL 2005

52.222-12 CONTRACT TERMINATION - DEBARMENT FEB 1988

52.222-13 COMPLIANCE WITH DAVIS-BACON AND RELATED ACT REGULATIONS FEB 1988

52.222-14 DISPUTES CONCERNING LABOR STANDARDS FEB 1988

52.222-15 CERTIFICATION OF ELIGIBILITY FEB 1988

52.222-21 PROHIBITION OF SEGREGATED FACILITIES FEB 1999

52.222-26 EQUAL OPPORTUNITY MAR 2007

52.222-27 AFFIRMATIVE ACTION COMPLIANCE REQUIREMENTS FOR CONSTRUCTION FEB 1999

52.222-35 EQUAL OPPORTUNITY FOR SPECIAL DISABLED VETERANS, VETERANS OF THE VIETNAM ERA, AND

OTHER ELIGIBLE VETERANS

SEPT 2010

52.222-36 AFFIRMATIVE ACTION FOR WORKERS WITH DISABILITIES JUN 1998

52.222-37 EMPLOYMENT REPORTS VETERANS SEPT 2010

52.222-54 EMPLOYMENT ELIGIBILITY VERIFICATION JAN 2009

52.223-5 POLLUTION PREVENTION AND RIGHT-TO-KNOW INFORMATION AUG 2003

52.223-6 DRUG-FREE WORKPLACE MAY 2001

52.223-14 TOXIC CHEMICAL RELEASE REPORTING AUG 2003

52.225-13 RESTRICTIONS ON CERTAIN FOREIGN PURCHASES JUN 2008

52.227-1 AUTHORIZATION AND CONSENT DEC 2007

52.227-2 NOTICE AND ASSISTANCE REGARDING PATENT AND COPYRIGHT INFRINGEMENT DEC 2007

52.227-4 PATENT INDEMNITY -- CONSTRUCTION CONTRACTS DEC 2007

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

Clause No Title Date

52.228-2 ADDITIONAL BOND SECURITY OCT 1997

52.228-11 PLEDGES OF ASSETS SEP 2009

52.228-12 PROSPECTIVE SUBCONTRACTOR REQUESTS FOR BONDS OCT 1995

52.228-14 IRREVOCABLE LETTER OF CREDIT DEC 1999

52.228-15 PERFORMANCE AND PAYMENT BONDS – CONSTRUCTION OCT 2010

Solicitation Number: AG-9AC7-S-11-0002 PAGE 14 of 34

52.229-3 FEDERAL, STATE, AND LOCAL TAXES APR 2003

52.232-5 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION CONTRACTS SEP 2002

52.232-9 LIMITATION ON WITHHOLDING OF PAYMENTS APR 1984

52.232-17 INTEREST OCT 2010

52.232-18 AVAILABILITY OF FUNDS APR 1984

52.232-23 ASSIGNMENT OF CLAIMS JAN 1986

52.232-27 PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS OCT 2008

52.232-33 PAYMENT BY ELECTRONIC FUNDS TRANSFER - CENTRAL CONTRACTOR REGISTER OCT 2003

52.233-1 DISPUTES – ALTERNATE I (DEC 1991) JULY 2002

52.233-3 PROTEST AFTER AWARD AUG 1996

52.236-2 DIFFERING SITE CONDITIONS APR 1984

52.236-3 SITE INVESTIGATION AND CONDITIONS AFFECTING THE WORK APR 1984

52.236-5 MATERIAL AND WORKMANSHIP APR 1984

52.236-6 SUPERINTENDENCE BY THE CONTRACTOR APR 1984

52.236-7 PERMITS AND RESPONSIBILITIES NOV 1991

52.236-8 OTHER CONTRACTS APR 1984

52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS APR 1984

52.236-10 OPERATIONS AND STORAGE AREAS APR 1984

52.236-11 USE AND POSSESSION PRIOR TO COMPLETION APR 1984

52.236-12 CLEANING UP APR 1984

52.236-13 ACCIDENT PREVENTION – Alternate I (NOV 1991) NOV 1991

52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS APR 1984

52.236-16 QUANTITY SURVEYS – Alternate I (APR 1984) APR 1984

52.236-17 LAYOUT OF WORK APR 1984

52.236-21 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION FEB 1997

52.236-26 PRECONSTRUCTION CONFERENCE FEB 1995

52.242-13 BANKRUPTCY JUL 1995

52.243-4 CHANGES JUN 2007

52.244-6 SUBCONTRACTS FOR COMMERCIAL ITEMS DEC 2010

52.245-1 GOVERNMENT PROPERTY AUG 2010

52.245-2 GOVERNMENT PROPERTY INSTALLATION OPERATION SERVICES AUG 2010

52.246-21 WARRANTY OF CONSTRUCTION – Alternate I (APR 1984) MAR 1994

52.248-3 VALUE ENGINEERING – CONSTRUCTION OCT 2010

52.249-1 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT (FIXED FEE) (SHORT FROM) APRIL1984 52.249-2 TERMINATION FOR CONVENIENCE OF THE GOVERNMENT – Alternate I (SEP 1996) MAY 2004

52.249-10 DEFAULT (FIXED-PRICE CONSTRUCTION) APR 1984

52.253-1 COMPUTER GENERATED FORMS JAN 1991

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70 REIMBURSEMENT FOR BOND PREMIUMS – FIXED-PRICE CONSTRUCTION CONTRACTS NOV 1996

452.236-72 USE OF PREMISES NOV 1996

452.236-73 ARCHEOLOGICAL OR HISTORIC SITES FEB 1988

452.236-74 CONTROL OF EROSION, SEDIMENTATION AND POLLUTION NOV 1996

452.236-76 SAMPLES AND CERTIFICATES FEB 1988

452.236-77 Emergency Response “NOTE:*

The Contractor shall comply with and/or complete the attached forms:

Fire Protection Requirements

(1) Fire Protection and Suppression Requirements.

(NOTE: See Fire Plan Requirements referenced in the attachments.)

NOV 1996

CERTIFICATION OF COMPLIANCE

Contractor shall certify compliance with specific fire precautionary measures included in the attached Fire Protection and Suppression Forms. The certification shall be made prior to commencement of work and shall be updated if at any time during performance the conditions change.

The Government may conduct verification inspections to ensure Contractor's compliance.

Solicitation Number: AG-9AC7-S-11-0002 PAGE 15 of 34

FAR 52.225-9 BUY AMERICAN ACT—CONSTRUCTION MATERIALS (SEP 2010)

(a) Definitions. As used in this clause— “Commercially available off-the-shelf (COTS) item”—

(1) Means any item of supply (including construction material) that is—

(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);

(ii) Sold in substantial quantities in the commercial marketplace; and

(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and

(2) Does not include bulk cargo, as defined in section 3 of the Shipping Act of 1984 (

46 U.S.C. App. 1702), such as agricultural products and petroleum products.

“Component” means an article, material, or supply incorporated directly into a construction material.

“Construction material” means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies.

However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.

“Cost of components” means—

(3) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or

(4) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.

“Domestic construction material” means—

(1) An unmanufactured construction material mined or produced in the United States;

(2) A construction material manufactured in the United States, if—

(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic;

or

(ii) The construction material is a COTS item.

“Foreign construction material” means a construction material other than a domestic construction material.

“United States” means the 50 States, the District of Columbia, and outlying areas.

(b) Domestic preference.

(1) This clause implements the Buy American Act (41 U.S.C. 10a - 10d) by providing a preference for domestic construction material. In accordance with 41 U.S.C. 431, the component test of the Buy American Act is waived for construction material that is a COTS item (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.

(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows: None

(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that— https://www.acquisition.gov/far/current/html/Subpart%202_1.html#wp1145508� http://uscode.house.gov/� http://uscode.house.gov/� http://uscode.house.gov/� https://www.acquisition.gov/far/current/html/Subpart%2012_5.html#wp1077123�

Solicitation Number: AG-9AC7-S-11-0002 PAGE 16 of 34

(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;

(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or

(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.

(c) Request for determination of inapplicability of the Buy American Act.

(1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including—

(A) A description of the foreign and domestic construction materials;

(B) Unit of measure;

(C) Quantity;

(D) Price;

(E) Time of delivery or availability;

(F) Location of the construction project;

(G) Name and address of the proposed supplier; and

(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.

(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.

(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).

(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.

(2) If the Government determines after contract award that an exception to the Buy American Act applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.

(3) Unless the Government determines that an exception to the Buy American Act applies, use of foreign construction material is noncompliant with the Buy American Act.

(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:

FOREIGN AND DOMESTIC CONSTRUCTION MATERIALS PRICE COMPARISON

Construction Material Description Unit of Measure Quantity Price (Dollars)* Item 1:

Foreign construction material _______ _______ _______ Domestic construction material _______ _______ _______

Item 2: _______ _______ _______ Foreign construction material _______ _______ _______ Domestic construction material [List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.] [Include other applicable supporting information.] [* Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).]

Solicitation Number: AG-9AC7-S-11-0002 PAGE 17 of 34

FAR 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –

(1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or 3 million, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

AGAR 452.228-70 ALTERNATIVE FORMS OF SECURITY (NOV 1996)

If furnished as security, money orders, drafts, cashier's checks, or certified checks shall be drawn payable to: USDA Forest Service.

FAR 52.232-18 AVAILABILITY OF FUNDS (APR 1984)

Funds are not presently available for this contract. The Government’s obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.

ORDER OF PRECEDENCE--CONSTRUCTION

Any inconsistency in this solicitation or contract shall be resolved by giving precedence in the following order:

(1) The Schedule (excluding the specifications); i.e. Sections A, B, D, E, F, G, and H

(2) Representations and Other Instructions; i.e. Sections K, L, and M

(3) Contract Clauses; i.e. Section I

(4) Other Documents, Exhibits, and Attachments; i.e. Section J

(5) Special Project Specifications

(6) Standard Specifications; i.e. Section C (including FAR clauses)

(7) (a) Drawings, figured dimensions over scaled dimensions.

(b) Drawings, large scale contract drawings over small scale contract drawings.

(c) Schedules on contract drawings over any conflicting notations on contract drawings.

(8) Shop Drawings

Solicitation Number: AG-9AC7-S-11-0002 PAGE 18 of 34

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

The following attachments are made a part of this solicitation and any resultant contract.

Title Pages

1. Specification List 1

2. Specifications 58

3. Project Drawings (Attached) or (Separate) 6

Page No Description 1 Title Sheet 1 2 Site Plan 1 3 Access Road and Ramp Plan and Profile 1 4 Precast Panel Details 1 5 Anchor and Pile Details 1 6 Gate Details 1

4. DOL Wage Decision No. CA20080009 12/03/2010 Summary 2

5. Fire Protection and Suppression 8

NOTE: IN COMPLIANCE WITH THE PAPER REDUCTION ACT, SECTIONS K, L, AND M, WHICH

APPLY ONLY TO THE SOLICITATION PHASE, ARE NOT DUPLICATED AFTER CONTRACT

AWARD. HOWEVER, SECTION K WILL BE INCORPORATED BY REFERENCE INTO THE

RESULTING CONTRACT.

Solicitation Number: AG-9AC7-S-11-0002 PAGE 19 of 34

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND OTHER

STATEMENTS OF OFFERORS OR RESPONDENTS

FAR 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE

(FEB 1998)

This solicitation incorporates one or more provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a provision may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

FAR 52.204-6 DATA UNIVERSAL NUMBERING SYSTEM (DUNS) NUMBER

(APR 2008)

(a) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation “DUNS” or “DUNS+4” followed by the DUNS number or “DUNS+4” that identifies the offeror’s name and address exactly as stated in the offer. The DUNS number is a nine-digit number assigned by Dun and Bradstreet, Inc. The DUNS+4 is the DUNS number plus a 4-character suffix that may be assigned at the discretion of the offeror to establish additional CCR records for identifying alternative Electronic Funds Transfer (EFT) accounts (see Subpart 32.11) for the same concern.

(b) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.

(1) An offeror may obtain a DUNS number—

(i) Via the Internet at http://fedgov.dnb.com/webform or if the offeror does not have internet access, it may call Dun and Bradstreet at 1-866-705-5711 if located within the United States; or

(ii) If located outside the United States, by contacting the local Dun and Bradstreet office.

The offeror should indicate that it is an offeror for a U.S. Government contract when contacting the local Dun and Bradstreet office.

(2) The offeror should be prepared to provide the following information:

(i) Company legal business name.

(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.

(iii) Company physical street address, city, state and ZIP Code.

(iv) Company mailing address, city, state and ZIP Code (if separate from physical).

(v) Company telephone number.

(vi) Date the company was started.

(vii) Number of employees at your location.

(viii) Chief executive officer/key manager.

(ix) Line of business (industry).

(x) Company Headquarters name and address (reporting relationship within your entity).

DUNS Number: ____________________________

Pursuant to AGAR 419.508, the contracting officer shall insert the following provision 452.219- 70 (January 2005), in solicitations that are set aside for small businesses, but for which FAR

4.1202 has directed that FAR 52.219-1 not be included in the solicitation.

http://www.arnet.gov/far/� http://www.usda.gov/procurement/policy/agar.html� http://acquisition.gov/far/current/html/Subpart%2032_11.html#wp1043964� http://acquisition.gov/far/current/html/%20http:/fedgov.dnb.com/webform�

Solicitation Number: AG-9AC7-S-11-0002 PAGE 20 of 34

FAR 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2011)

(a)(1) The North American Industry Classification System (NAICS) code for this acquisition is 237990.

(2) The small business size standard is 33.5 mil.

(3) The small business size standard for a concern which submits an offer in its own name, other than on a construction or service contract, but which proposes to furnish a product which it did not itself manufacture, is 500 employees.

(b)(1) If the clause at 52.204-7, Central Contractor Registration, is included in this solicitation, paragraph (d) of this provision applies.

(2) If the clause at 52.204-7 is not included in this solicitation, and the offeror is currently registered in CCR, and has completed the ORCA electronically, the offeror may choose to use paragraph (d) of this provision instead of completing the corresponding individual representations and certifications in the solicitation. The offeror shall indicate which option applies by checking one of the following boxes:

[ ] (i) Paragraph (d) applies.

[ ] (ii) Paragraph (d) does not apply and the offeror has completed the individual representations and certifications in the solicitation.

(c)(1) The following representations or certifications in ORCA are applicable to this solicitation as indicated:

(i) 52.203-2, Certificate of Independent Price Determination. This provision applies to solicitations when a firm-fixed-price contract or fixed-price contract with economic price adjustment is contemplated, unless—

(A) The acquisition is to be made under the simplified acquisition procedures in Part 13;

(B) The solicitation is a request for technical proposals under two-step sealed bidding procedures; or

(C) The solicitation is for utility services for which rates are set by law or regulation.

(ii) 52.203-11, Certification and Disclosure Regarding Payments to Influence Certain

Federal Transactions. This provision applies to solicitations expected to exceed $150,000.

(iii) 52.204-3, Taxpayer Identification. This provision applies to solicitations that do not include the clause at 52.204-7, Central Contractor Registration.

(iv) 52.204-5, Women-Owned Business (Other Than Small Business). This provision applies to solicitations that—

(A) Are not set aside for small business concerns;

(B) Exceed the simplified acquisition threshold; and

(C) Are for contracts that will be performed in the United States or its outlying areas.

(v) 52.209-5, Certification Regarding Responsibility Matters. This provision applies to solicitations where the contract value is expected to exceed the simplified acquisition threshold.

(vi) 52.214-14, Place of Performance—Sealed Bidding.

This is the start of the file's text. The full file is on GovTribe.