SHAH KAWASAKI ARCHITECTS

BRISTLECONE VISITOR CENTER

INYO NATIONAL FOREST

SECTION 01 11 00

SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. Project consists of construction of the Bristlecone Visitor Center, Inyo National Forest, outside of Bishop, California 93514, as indicated in Contract Documents.

1. Items noted "NIC" (Not in Contract) will be furnished and installed by Owner or under separate contract.

a. Hazardous Materials Removal: Known hazardous materials will be removed under separate contract (NIC); inform Owner immediately where materials suspected of being hazardous are encountered.

B. Division 1: Where provisions of General Conditions relate to Project administration or work-related requirements of the Contract, those paragraphs are expanded in Division 1 - General Requirements.

1. General Conditions, Supplementary Conditions and Division 1 - General Requirements contain information necessary for completion of every part of Project.

2. Where items of Work are done under subcontracts, each item shall be subject to these conditions.

C. LEED Requirements: Owner has established general environmental goals for design and for construction of Project based on LEED Green Building criteria; construction team is required to participate to realize Owner’s environmental goals.

3. LEED Green Building Rating: Goal is to achieve Gold Silver Rating., but no less than Certified is required.

1.2 REQUIREMENTS INCLUDED

A. This section includes administrative provisions:

1. Work sequence.

2. Contractor use of premises.

3. Field engineering.

4. Regulatory requirements and reference standards.

5. Owner furnished, Contractor installed products.

6. Special definitions.

1.3 WORK SEQUENCE

A. Coordinate construction schedule and operations with Owner and Architect.

1.4 CONTRACTOR USE OF PREMISES

A. Limit use of premises for Work and construction operations and to allow for work by other contractors.

B. Coordinate use of premises and access to site under direction of Owner and Architect.

1.5 FIELD ENGINEERING

A. Provide field engineering services; establish lines and levels by use of recognized engineering survey practices.

B. Locate and protect control and reference points.

1.6 REGULATORY REQUIREMENTS AND REFERENCE STANDARDS

A. Regulatory Requirements:

1. Architect has contacted governing authorities and reviewed design requirements of local, state and federal agencies for applicability to Project.

2. Contractor shall be responsible for contacting governing authorities directly for necessary information and decisions bearing upon performance of Work.

B. Reference Standards:

1. For Products specified by association or trade standards, comply with requirements of referenced standard, except when more rigid requirements are specified or are required by applicable codes.

2. Applicable date of each standard is that in effect as of date on proposal or date on Contract where no proposal is available, except when a specific date is specified.

1.7 OWNER FURNISHED, CONTRACTOR INSTALLED PRODUCTS

A. Select products are to be furnished and paid for by Owner and installed by Contractor:

1. Refer to Drawings.

B. Owner's Responsibilities:

1. Arrange for and deliver shop drawings, product data, and samples to Contractor.

2. Arrange and pay for product delivery to site.

3. Inspect products jointly with Contractor on delivery.

4. Submit claims for transportation damage.

5. Arrange for replacement of damaged, defective, or missing items.

6. Arrange for manufacturer's warranties, inspections, and service.

C. Contractor's Responsibilities:

1. Review shop drawings, product data, and samples.

2. Receive and unload products at site.

3. Inspect jointly with Owner for completeness and damage.

4. Handle, store, and install products.

5. Finish products as required after installation.

6. Repair or replace items damaged by Work of this Contract.

1.8 SPECIAL DEFINITIONS

A. Equal, or Approved Equal: Equal and approved equal shall require requests for substitutions for products or manufacturers not specified.

1. Requests for substitutions shall be in accordance with requirements of Section 01 62 00 - Substitutions.

B. Furnish: Furnish means supply and deliver to Project, unless otherwise defined in greater detail.

C. Install: Install is used to describe operations at Project, from inspecting and unloading, to completion in place, ready for intended use.

D. Provide: Provide means furnish and install, complete and ready for intended use, unless otherwise defined in greater detail.

E. Reviewed: Reviewed, directed, selected, required, ordered, designated, accepted, acceptable, and satisfactory shall require written action by Architect.

END OF SECTION

Amendment No. 4 Revised 8/30/10 01 11 00 - 3 Summary of Work

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .