AG-9A28-S-09-0026.pdf

PDF 590 KB Posted

Attached to
McCloud Loop Road Paving Federal contract opportunity
Solicitation number
AG-9A28-S-10-0026
Issued by
Department of Agriculture Forest Service R5-Pacific Southwest Region

About this file

AG-9A28-S-10-0026

View the file

Other files for this federal contract opportunity

Other files attached to McCloud Loop Road Paving, newest first.
File Type Posted
VENDOR QUESTIONS AND FOREST SERVICE RESPONSES.docx DOCX document
Amendment No. 2.pdf PDF
Amendment No. 1.pdf PDF
CA903262010_dvb.htm HTM file
CA903122010_dvb.htm HTM file
McCloud Loop Paving Sheet 1.pdf PDF
McCloud Loop Paving Sheet 2pdf.pdf PDF
McCloud Loop Paving Sheet 4.pdf PDF
SF24BidBond.pdf PDF
McCloud Loop Paving Sheet 3pdf.pdf PDF
McCloud Loop Paving Sheet 5.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OMB APPROVAL NO. 2700-0042

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

AG-9A28-S-10-0026

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE

ISSUED

03/12/2010

PAGE OF

PAGES

1 68

IMPORTANT - The ―offer‖ section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

5. REQUISITION/PURCHASE REQUEST

NO.

6. PROJECT NO.

7. ISSUED BY CODE 8. ADDRESS OFFER TO

USDA, Northern Province Acquisitions

Redding Office

3644 Avtech Parkway, Suite 180

Redding, CA 96002

Same as Block 7.

9. FOR INFORMATION

CALL:

A. NAME

PAMELA J. VILHAUER

pvilhauer@fs.fed.us

B. TELEPHONE NO. (Include area code) (NO COLLECT

CALLS)

530-226-2454

SOLICITATION

NOTE: In sealed bid solicitations ―offer‖ and ―offeror‖ mean ―bid‖ and ―bidder.‖

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

MCCLOUD LOOP ROAD PAVING

SHASTA-TRINITY NATIONAL FOREST

SISKIYOU COUNTY, CALIFORNIA

Price Range

The Government's estimate is:

between $500,000 and $1,000,000.

DUNS NO.___________________________________

TAX I.D. NO._________________________________

11. The Contractor shall begin performance within 5 calendar days and complete it within 30 calendar days after receiving award, XX notice to proceed. This performance period is XX mandatory, negotiable. (See .)

12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT

BONDS?

(If “YES,” indicate within how many calendar days after award in Item 12B.)

XX YES NO

12B. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and 0 copies to perform the work required are due at the place specified in Item 8 by 4:30 PM (hour) local time April

12, 2010 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee XX is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Computer Generated

Prescribed by GSA mailto:pvilhauer@fs.fed.us

FAR (48 CFR) 53.236-1(e)

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

15. TELEPHONE NO. (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14)

CODE FACILITY CODE

17. The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

20B. SIGNATURE

20C. OFFER DATE

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT

23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN

IN

(4 copies unless otherwise specified)

ITEM

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT

TO

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( )

26. ADMINISTERED BY CODE 27. PAYMENT WILL BE MADE BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.)

Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON

AUTHORIZED TO SIGN (Type or print)

31A. NAME OF CONTRACTING OFFICER (Type or print)

PAMELA J VILHAUER

30B. SIGNATURE

30C. DATE

31B. UNITED STATES OF AMERICA

BY

31C. AWARD DATE

Computer Generated STANDARD FORM 1442 BACK (REV. 4-85)

SOL NO. AG-9A28-S-10-0026

UNIT: Shasta-Trinity National Forest

PROJ NAME: McCloud Loop Road Paving

PART I – THE SCHEDULE

SECTION B – SUPPLIES OR SERVICES AND PRICES/COSTS

SCHEDULE OF ITEMS

ITEM

NO.

DESCRIPTION

PAY

UNIT

EST.

QTY.

UNIT

PRICE

TOTAL

PRICE

151(01) Mobilization JOB 1 $_________ $___________

230(01) Roadside brushing JOB 1 $_________ $___________

301(01)

Untreated aggregate course, gradation D, Table 703-2, shoulder backing, compaction A TN 300 $_________ $___________

303(01)

Road reconditioning, compaction F, 95% T180

(contractor required testing) MI 1.7 $_________ $___________

403(01)

Hot asphalt concrete pavement, type PG 64-16, grading

B TN 3300 $_________ $___________

634(01)

Permanent pavement markings, 4-inch, white, type H, thermoplastic fog line FT 17952 $_________ $__________

635(01) Temporary traffic control JOB 1 $_________ $__________

Total of all items

NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price

Construction Contracts, shall not be in addition to the contract price. Include bond payments under 15101

Mobilization.

SAMPLING AND TESTING

The contractor will be required to complete all sampling and testing in accordance with the specifications.

Sampling and testing does not have a separate pay item. Any cost associated with sampling and testing should be included in the associated bid item. See table 303-1 on the following page.

T a b le

-1

S m p li n g a n d

T es ti n g a n d

R eq u ir em e n ts

R e p o r ti g im e

B ef o re u si in w o rk

B ef o re u si w

E d o f sh if t

(1

M in im u m p o in ts p er p ro ct r.

p li t m le

Y es w h en re q u es te d

P in t o f

S a m p li

R ad b ed ro ce ss m at er ia l b ef re co rp o ra ti i w

C m p ac at er ia l

S a m p li

F r e q u e n c y er s il ty e f o r ea ch m ix tu re o r ch an g e in m at er ia l p er y st

M e th o d s

S p e c if ic a ti o n s

A A

S H

T O

M

A A

S H

T O

T et h o d D

(1

A A

S H

T O

T th er a p p ro v ro ce d u re s

C a te g ry

C h a ra c te r is ti c

C la ss if ic at io

M is tu re d en si

In -p la ce d en si is tu re c o n te n t

T y p e o f A c ce p ta ce

(S u b se c ti o n

M ea su re d a n d t es fo co n fo rm an ce

(1

.0

M a te ri a l o r

P r o d u c t

E x is ti n g r o ad b

PROJ NAME: McCloud Loop Road Paving

SECTION C – DESCRIPTION/SPECIFICATION/WORK STATEMENT

C.1 SCOPE OF CONTRACT

Furnish all labor, equipment and materials to pulverize, compact, pave and stripe 1.7 miles of road

40N44, Middle Falls Road, from mile post 0.60 (intersection with road 39N28) to mile post 2.30

(intersection with road 39N13Y), McCloud Ranger District, Shasta-Trinity National Forest, Siskiyou

County, California.

C.2 PROJECT LOCATION

From Redding, CA travel north on Interstate 5 approximately 55 miles to Highway 89 east toward

McCloud, CA. Travel approximately 14 miles east, through McCloud, to Middle Falls Road and the project site.

C.3 PROJECT ACCESS

This project road may be closed to traffic during construction. The closure shall be allowed during the week, Monday through Friday, and one weekend closure will be allowed. The Contractor will give the

Government 14 days notice before closing the road.

C.4 ESTIMATED START WORK DATE

Estimated start work date is April 26, 2010. Contract time will be 30 calendar days.

C.5 CONTRACTOR SUBMITTALS

C5.1 Plans- The Contractor shall furnish a traffic control plan, safety plan and a spill plan, along with a detailed plan of operation, for approval by the Government prior to starting work.

C.6 SAFETY PLAN REQUIREMENTS

1. General Statements of Policy

a. Company Policy

b. Health and Safety

c. Safety Inspections

d. Accident Prevention

e. Emergency Procedures

2. Fire Prevention

a. General Statement

b. Fire Restrictions

c. Communications

d. Smoking

e. Cleaning and Decreasing

f. Welding or Torch Work

PROJ NAME: McCloud Loop Road Paving

3. Medical

a. On Site First Aid

b. Medical Facilities

c. Training and Certification

d. Personnel Qualifications

e. Record Keeping

4. Communications (radio-phone)

a. Personnel Training

b. Available Equipment

c. Communications Plan

5. Occupational Health and Safety

a. Job Hazard Analysis

b. Drinking Water

c. Noise Exposure

d. Atmospheric Contaminants

e. Hazardous Chemicals

f. Personal Protective Equipment

g. Excavation and Trenching

h. Working Surfaces

i. Trips and Falls

6. Heavy Equipment and Motor Vehicles

b. Inspection and Maintenance Procedures

c. Personnel Qualifications

d. Operation of Heavy Equipment

e. Operation of Motor Vehicles

7. Small Equipment and Tools

b. Slings and Hoists

c. Hand and Power Tools

d. Grinding Tools

e. Power Saws

f. Pneumatic Tools

g. Air Compressors

h. Compressed Gas Cylinders

i. Man and Scissor Lifts

j. Generators and Welders

k. Whackers and Vibratory Plate

8. Public Protection

a. Traffic Control

b. Signs

c. Barricades

d. Sign Plan

C.7 PROJECT SPECIFICATIONS

All of the specifications from Standard Specifications for Construction of Roads and Bridges on

Federal Highways, FP-03 issued in 2003 are a part of this solicitation and any resultant contract.

Internet web location of FP-03 Specifications is http://www.wfl.fha.dot.gov/design/specs/fp03.htm.

The following project specifications are specifically associated with the work under this contract. The omission of a Forest Specification shall not be a cause for a contract modification.

Preface

101 - Terms, Format, and Definitions

101.01 Meaning of Terms

101.03 Abbreviations

101.04 Definitions

102 - Bid, Award, and Execution of Contract 102 Bid, Award, and Execution of Contract

103 - Scope of Work

Deletions 104 - Control of Work

Deletions

104.06 Use of Roads by Contractor

105 - Control of Material

105.02 Material Sources

105.02(a) Government-provided sources

105.05 Use of Material Found in the Work

106 - Acceptance of Work

106.07 Delete

107 - Legal Relations and Responsibility to the Public

107.05 Responsibility for Damage Claims

107.06 Contractor’s Responsibility for Work

107.09 Legal Relationship of the Parties

107.10 Environmental Protection

107.02 Protection and Restoration of Property and Landscape

108 - Prosecution and Progress

108 Delete 109 - Measurement and Payment

109 Deletions

109.02 Measurement Terms and Definitions

151 - Mobilization

155 - Schedules for Construction Contracts 155 Delete

156 - Public Traffic

156.04 Maintaining Roadways During Work

156.08 Traffic and Safety Supervisor

230 - Roadside Brushing 301 - Untreated Aggregate Courses

301 Title Change

301.05 Compacting

PROJ NAME: McCloud Loop Road Paving

303 - Road Reconditioning

303.05 Compacting

409 - Asphalt Surface Treatment

409.06 Weather

409.06 Date & Time

409.13 Acceptance

Table 409-4 Sampling and Testing Requirements

702- Asphalt Material

PROJ NAME: McCloud Loop Road Paving

Preface

Preface_wo_03_15_2004_m

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National

Forest System Roads.

PROJ NAME: McCloud Loop Road Paving

101 - Terms, Format, and Definitions

101.00_nat_us_07_25_2005

101.01_nat_us_01_22_2009

101.01 Meaning of Terms

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03_nat_us_06_16_2006

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association

Mine Safety and Health Administration

National Institute of Standards and Technology

National Electrical Safety Code

West Coast Lumber Inspection Bureau

Add the following to (b) SI symbols:

mp Milepost ppm Part Per Million

101.04_nat_us_03_29_2007

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the ―purchaser‖.

Culvert--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line

(including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2)

Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following:

Adjustment in Contract Price--―Equitable adjustment,‖ as used in the Federal Acquisition

Regulations, or ―construction cost adjustment,‖ as used in the Timber Sale Contract, as applicable.

Change--―Change‖ means ―change order‖ as used in the Federal Acquisition Regulations, or ―design change‖ as used in the Timber Sale Contract.

Design Quantity--―Design quantity‖ is a Forest Service method of measurement from the FS-96

Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term ―Contract Quantities‖.

Forest Service--The United States of America, acting through the Forest Service, U.S. Department of

Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

http://www.nist.gov/

PROJ NAME: McCloud Loop Road Paving

Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction.

Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

PROJ NAME: McCloud Loop Road Paving

Figure 101-1—Illustration of road structure terms.

PROJ NAME: McCloud Loop Road Paving

102 - Bid, Award, and Execution of Contract

102.00_nat_us_02_16_2005

102 Bid, Award, and Execution of Contract

Delete Section 102 in its entirety.

PROJ NAME: McCloud Loop Road Paving

103 - Scope of Work

103.00_nat_us_02_16_2005

Deletions

Delete all but subsection 103.01 Intent of Contract.

PROJ NAME: McCloud Loop Road Paving

104 - Control of Work

104.00_nat_us_06_16_2006

Deletions

Delete Sections 104.01, 104.02, and 104.04.

104.06_nat_us_02_17_2005

Add the following subsection:

104.06 Use of Roads by Contractor

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road

Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

PROJ NAME: McCloud Loop Road Paving

105 - Control of Material

105.02_nat_us_01_18_2007

105.02 Material Sources.

105.02(a) Government-provided sources.

Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.

105.05_nat_us_05_12_2004

105.05 Use of Material Found in the Work.

Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:

Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.

PROJ NAME: McCloud Loop Road Paving

106 - Acceptance of Work

106.07_nat_us_05_11_2004

106.07 Delete

Delete subsection 106.07.

PROJ NAME: McCloud Loop Road Paving

107 - Legal Relations and Responsibility to the Public

107.05_nat_us_05_11_2004

107.05 Responsibility for Damage Claims.

Delete the entire subsection.

107.06_nat_us_06_16_2006

107.06 Contractor’s Responsibility for Work.

Delete the following from the first paragraph.

―except as provided in Subsection 106.07‖.

107.09_nat_us_06_16_2006

107.09 Legal Relationship of the Parties.

Delete the entire subsection.

107.10_nat_us_06_16_2006

107.10 Environmental Protection.

Add the following:

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

Exact time and location of spill including a description of the area involved.

Containment procedures.

Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with

Federal, state, and local laws and regulations.

107.10_05_us_05_04_2007

107.02 Protection and Restoration of Property and Landscape

Meet the requirements chapters 10, 11, and 12.2 in their entirety of ―Water Quality Management for

National Forest System Lands in California Best Management Practices‖ dated September 2000

PROJ NAME: McCloud Loop Road Paving

108 - Prosecution and Progress

108.00_nat_us_02_16_2005

108 Delete.

Delete Section 108 in its entirety.

PROJ NAME: McCloud Loop Road Paving

109 - Measurement and Payment

109.00_nat_us_02_17_2005

109 Deletions

Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

109.02_nat_us_06_16_2006

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Add the following:

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

Change the following:

―(b) Cubic yard‖ to ―(c) Cubic yard‖.

Add the following definition:

(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

PROJ NAME: McCloud Loop Road Paving

151 - Mobilization

151.00_01_us_10_11_2006

Delete Section 151 in its entirety and replace with the following.

Description

151.01 This work consists of moving personnel, equipment, material, and incidentals to the project and performing all work necessary before beginning work at the project site; obtaining of permits, insurance, and bonds. This work also includes washing and treating construction equipment and vehicles necessary for equipment transport to remove seeds, plants, and plant fragments before the equipment is used on Forest Service lands, according to the requirements within.

Construction Requirements

Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment. Only equipment inspected by the Forest

Service will be allowed to operate within the project area. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in. This requirement does not apply to cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas off the National Forest.

Equipment will be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment, components or the need for specialized inspection tools is not required.

Notify the CO in writing at least 72 hours before moving any construction equipment onto the national forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Forest Service. Inspection will be required after every cleaning.

Use methods of cleaning and locations for cleaning approved by the CO.

For work at a commercial washing facility, use an approved facility.

New infestations of noxious weeds of concern to Forest Service and identified by either Contractor or

Forest Service, in the Project Area or on the haul route, will be promptly reported to the other party.

Contractor and Forest Service will agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found. A current list of noxious weeds of concern to Forest Service is available at each Forest Service office.

Measurement

151.02 Clean equipment prior to moving onto this project. The initial cleaning will not be included in the measurement for payment. Payment for cleaning will only be made if subsequent cleanings are ordered by the CO. Measurement shall be on an ―each‖ basis, meaning one complete cleaning of all equipment required for this contract. Subsequent cleanings necessitated by the Contractor’s actions but not directed by the CO will not be included in the measurement for payment.

Measure mobilization according to Subsection 109.02.

PROJ NAME: McCloud Loop Road Paving

Payment

151.03 The accepted quantity, measured as provided in Subsection 109.02, will be paid at the contract price per unit of measurement for the Section 151 pay item shown in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

Progress payments for mobilization lump sum will be paid as follows:

(a) If applicable, bond premiums will be reimbursed according to FAR Clause 52.232-5 Payments

Under Fixed-Price Construction Contracts, after receipt of the evidence of payment.

(b) When 5 percent of the original contract amount is earned from other bid items, 50 percent of the mobilization item, or 5 percent of the original contract amount, whichever is less, will be paid.

(c) When 10 percent of the original contract amount is earned from other bid items, 100 percent of the mobilization item, or 10 percent of the original contract amount, whichever is less, will be paid.

(d) Any portion of the mobilization item in excess of 10 percent of the original contract amount will be paid after final acceptance.

Include all costs associated with the initial cleaning of equipment in the unit bid price for Mobilization.

Cleaning for subsequent move-ins will not be paid for unless after a suspension ordered by the CO.

PROJ NAME: McCloud Loop Road Paving

155 - Schedules for Construction Contracts

155.00_nat_us_05_11_2004

155 Delete.

Delete Section 155 in its entirety.

PROJ NAME: McCloud Loop Road Paving

156 - Public Traffic

156.00_nat_us_04_17_2007

Delete Section 156 in its entirety and replace with the following:

156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.

Material

156.02 Conform to the MUTCD and the following Sections and Subsections:

Construction sign panels 633

Retro-reflective sheeting 718.01

Temporary concrete barrier 618

Temporary plastic fence 710.11

Temporary traffic control devices 718.22

156.03 General. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic.

Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved. Post construction signs and traffic control devices in conformance with MUTCD. All required signs will be in place and approved prior to beginning work on project.

If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.

156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:

(a) Furnish and install traffic control devices before the start of construction operations.

(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.

(c) Install only those traffic control devices needed for each stage or phase.

(d) Relocate temporary traffic control devices as necessary.

(e) Remove devices that no longer apply to the existing conditions.

(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.

(g) Keep temporary traffic control devices clean.

(h) Remove all temporary traffic control devices upon contract completion or when approved.

(i) When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use

PROJ NAME: McCloud Loop Road Paving type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags.

Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.

156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s). Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.

Prior to closing roads during construction, give written notice to the Contracting Officer at least 10 days in advance.

Table 156-1

Temporary Road Closures

Road

Number

From

Terminus

To

Terminus

Maximum

Consecutive

Days of

Closure

Minimum

Consecutive

Days Open

40N44 39N28 39N13Y 12 2

156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.

Measurement and Payment

156.07 Payment will be made as specified in the Schedule of Items.

156.04_nat_us_02_24_2005

156.04 Maintaining Roadways During Work.

(a) Add the following:

Do not construct detours outside of the clearing limits or use alternate route detours without the approval of the CO.

156.08_nat_us_02_24_2005

156.08 Traffic and Safety Supervisor.

Delete this subsection in its entirety.

PROJ NAME: McCloud Loop Road Paving

230 - Roadside Brushing

230.00_0114_us_08_04_2005

230.01 Work. This work consists of removing all vegetative material including limbs, residual slash, live roadside brush, and small trees within the brushing limits designated on the plans.

Construction

230.02 Brushing. Cut all brush and small trees (6 inches diameter, or less, at the point of cut) inside the brushing limits and outside the roadbed no higher than 4 inches above ground level (6 inches for machine brushing). If rocks or other obstructions are encountered, cut no higher than 6 inches above the obstruction. Limb live trees with a diameter larger than 6 inches to provide a clear height of 14 feet above the road surface.

Cut all brush and trees located on the roadbed as nearly flush to the road surface as possible so stumps will not become a hazard to vehicle tires.

230.03 Windfalls. Limb windfalls lying within or across the brushing limits, cut off at the top of the existing cut slope or 5 feet from the shoulder on the fill slope. Dispose of windfall material as slash.

230.04 Road Junctions. Do not deposit brushing debris on the roadway of adjoining roads.

230.05 Slash Treatment. Scatter slash outside the brushing limits without damaging residual trees.

Slash is defined as any material that has a length greater than 36 inches or a diameter greater than 2 inches at any point. Do not deposit material in streams, streambeds, culvert inlets or outlets, drainage ways, or cattle guards.

230.06 Acceptance. Roadside brushing will be evaluated under Subsection 106.02.

Measurement

230.07 Method. Measure the Section 230 items listed in the bid schedule according to Subsection

109.02 and the following.

Linear measurements will be horizontal along the road centerline.

Quantities will be the number of miles (or stations) and fractions thereof along the road centerline.

Payment

230.08. The accepted quantities will be paid at the contract price per unit of measurement for the section 230 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this section. See Subsection 109.05.

301 - Untreated Aggregate Courses

301.00_nat_us_03_03_2005

301 Title Change.

Change the title to: Section 301 Aggregate Courses

301.05_nat_us_05_17_2005

301.05 Compacting

Delete and replace with the following:

Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road.

Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.

Compact the aggregate using one of the following methods as specified:

Compaction A. Operating spreading and hauling equipment over the full width of the travelway.

Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).

Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in

Subsection 204.11(a)(1).

Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.

Compaction E. Compact to a density of at least 96 percent of the maximum density, as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).

Compaction F. Compact to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 180, method C or D.

Compaction G. Compact to a density of at least 100 percent of the maximum density as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).

For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.

301.10_nat_us_03_03_2005

301.10 Payment

Delete the following:

adjusted according to Subsection 106.05

PROJ NAME: McCloud Loop Road Paving

303 - Road Reconditioning

303.05 Compacting

Delete the line

Compact according to Subsection 204.11.

Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road.

Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.

Compact the aggregate using one of the following methods as specified:

Compaction A. Operating spreading and hauling equipment over the full width of the travelway.

Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).

Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in

Subsection 204.11(a)(1).

Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.

Compaction E. Compact to a density of at least 96 percent of the maximum density, as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).

Compaction F. Compact to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 180, method C or D.

Compaction G. Compact to a density of at least 100 percent of the maximum density as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).

For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.

PROJ NAME: McCloud Loop Road Paving

409 - Asphalt Surface Treatment

409.06_nat_us_05_12_2004

409.06 Weather.

Delete the first paragraph and replace with the following:

Apply surface treatments with aggregate only when ambient air and surface temperatures are above 60

°F and rising in the shade, when the weather is not foggy or rainy, and when rain is not forecast for at least 24 hours after application.

409.06 Date & Time.

Add the following.

Construct fog seal and single-course surface treatments between June 1st and Sept 1st and multiple-course surface treatments between June 1st and Sept 1st.

409.13_nat_us_05_13_2004

409.13 Acceptance.

Delete the 2 nd paragraph and replace with the following:

Aggregate gradation for asphalt surface treatment will be evaluated under Subsection 106.04.

Table 409-4 Sampling and Testing Requirements.

Delete the last cell (4 th

) under Sampling Frequency and replace with the following:

1 per tanker truck and 1 per trailer

Delete the 2 nd and 3 rd cell under Type of Acceptance and replace with the following:

Measured and tested for conformance (106.04)

PROJ NAME: McCloud Loop Road Paving

702 Asphalt Material

702.01 Delete the first sentence add the following:

Performance graded (PG) asphalt binder shall conform to the following Standard Specifications, State of

California:

Performance Graded Asphalt Binder

Specification

Grade

Property AASHTO

Test

Method

PG

58-22a

64-10

64-16

64-28

70-10

Original Binder

Flash Point, Min. °C T48 230 230 230 230 230

Solubility, Min. % b T44 99 99 99 99 99

Viscosity at 135°C, c

Max., Pa·s

T316

3.0

Dynamic Shear, Test Temp. at 10 rad/s, °C

Min. G*/sin(delta), kPa

T315

1.00

RTFO Test e, Mass Loss, Max., %

T240

RTFO Test Aged Binder

Dynamic Shear, Test Temp. at 10 rad/s, °C

Min. G*/sin(delta), kPa

T315

2.20

Ductility at 25°C

Min., cm

T51

PAV f Aging, Temperature, °C

R28

RTFO Test and PAV Aged Binder

Dynamic Shear, Test Temp. at 10 rad/s, °C

Min. G*sin(delta), kPa

T315

22 d

31 d

28 d

22 d

34 d

Creep Stiffness, Test Temperature, °C

Max. S-value, MPa

Min. M-value

T313

-12

0.300

-6

-18

0.300

Notes:

a. For use as asphalt rubber base stock for high mountain and high desert area.

b. The Engineer will waive this specification if the supplier is a Quality Supplier as defined by the Department's "Certification Program for Suppliers of Asphalt."

c. The Engineer will waive this specification if the supplier certifies the asphalt binder can be adequately pumped and mixed at temperatures meeting applicable safety standards.

d. Test the sample at 3°C higher if it fails at the specified test temperature. G*sin(delta) shall remain 5000 kPa maximum.

e. "RTFO Test" means the asphaltic residue obtained using the Rolling Thin Film Oven

Test, AASHTO Test Method T240 or ASTM Designation: D 2872.

f. "PAV" means Pressurized Aging Vessel.

PROJ NAME: McCloud Loop Road Paving

SECTION D--PACKAGING AND MARKING

{For this Solicitation, there are NO clauses in this Section}

PROJ NAME: McCloud Loop Road Paving

SECTION E--INSPECTION AND ACCEPTANCE

FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES

52.246-12 Inspection of Construction (AUG 1996) http://www.arnet.gov/far/

PROJ NAME: McCloud Loop Road Paving

SECTION F--DELIVERIES OR PERFORMANCE

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/

52.242-14 Suspension of Work (APR 1984)

FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 30 days. The time stated for completion shall include final cleanup of the premises.

AGAR 452.236-75 Maximum Workweek – Construction Schedule (NOV 1996)

Within seven calendar days after receipt of a written request from the Contracting Officer, the

Contractor must submit the following information in writing for approval:

(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and

(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposes to carry out the work.

The maximum workweek that will be approved is seven days.

PROJ NAME: McCloud Loop Road Paving

SECTION G--CONTRACT ADMINISTRATION DATA

PROJ NAME: McCloud Loop Road Paving

SECTION H--SPECIAL CONTRACT REQUIREMENTS

PROJ NAME: McCloud Loop Road Paving

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

www.arnet.gov/far/ www.usda.gov/procurement/policy/agar.html

52.202-1 Definitions (JUL 2004)

52.203-3 Gratuities (APR 1984)

52.203-5 Covenant Against Contingent Fees (APR 1984)

52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006)

52.203-7 Anti-Kickback Procedures (JUL 1995)

52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (JAN 1997)

52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997)

52.203-12 Limitation on Payments to Influence Certain Federal Transactions (SEP 2007)

52.204-4 Printed or Copied Double-Sided on Recycled Paper (AUG 2000)

52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (SEP 2006)

52.211-18 Variation in Estimated Quantity (APR 1984)

52.215-2 Audit and Records -- Negotiation (JUN 1999)

52.219-8 Utilization of Small Business Concerns (MAY 2004)

52.222-3 Convict Labor (JUN 2003)

52.222-4 Contract Work Hours and Safety Standards Act -- Overtime Compensation (JUL 2005)

52.222-6 Davis-Bacon Act (JUL 2005)

52.222-7 Withholding of Funds (FEB 1988)

52.222-8 Payrolls and Basic Records (FEB 1988)

52.222-9 Apprentices and Trainees (JUL 2005)

52.222-10 Compliance with Copeland Act Requirements (FEB 1988)

52.222-11 Subcontracts (Labor Standards) (JUL 2005)

52.222-12 Contract Termination - Debarment (FEB 1988)

52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988)

52.222-14 Disputes Concerning Labor Standards (FEB 1988)

52.222-15 Certification of Eligibility (FEB 1988)

52.222-21 Prohibition of Segregated Facilities (FEB 1999)

52.222-26 Equal Opportunity (MAR 2007)

52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999)

52.222-35 Equal Opportunity for Special Disabled Veterans, Veterans of the Vietnam Era, and other Eligible Veterans (SEP 2006)

52.222-36 Affirmative Action for Workers with Disabilities (JUN 1998) http://www.usda.gov/procurement/policy/agar.html

PROJ NAME: McCloud Loop Road Paving

52.222-37 Employment Reports on Special Disabled Veterans, Veterans of the Vietnam Era, and other Eligible Veterans (SEP 2006)

52.222-50 Combating Trafficking in Persons (SEP 2007)

52.223-6 Drug-Free Workplace (MAY 2001)

52.223-14 Toxic Chemical Release Reporting (AUG 2003)

52.225-13 Restrictions on Certain Foreign Purchases (FEB 2006)

52.228-2 Additional Bond Security (OCT 1997)

52.228-11 Pledges of Assets (FEB 1992)

52.228-12 Prospective Subcontractor Requests for Bonds (OCT 1995)

52.228-14 Irrevocable Letter of Credit (DEC 1999)

52.228-15 Performance and Payment Bonds – Construction (NOV 2006)

52.229-3 Federal, State, and Local Taxes (APR 2003)

52.232-5 Payments Under Fixed-Price Construction Contracts (SEP 2002)

52.232-17 Interest (JUN 1996)

52.232-23 Assignment of Claims (JAN 1986)

52.232-27 Prompt Payment for Construction Contracts (SEP 2005)

52.232-33 Payment by Electronic Funds Transfer – Central Contractor Registration (OCT 2003)

52.233-1 Disputes (JULY 2002)

52.233-3 Protest After Award (AUG 1996)

52.233-4 Applicable Law for Breach of Contract Claim (OCT 2004)

52.236-2 Differing Site Conditions (APR 1984)

52.236-3 Site Investigation and Conditions Affecting the Work (APR 1984)

52.236-5 Material and Workmanship (APR 1984)

52.236-6 Superintendence by The Contractor (APR 1984)

52.236-7 Permits and Responsibilities (NOV 1991)

52.236-8 Other Contracts (APR 1984)

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

(APR 1984)

52.236-10 Operations and Storage Areas (APR 1984)

52.236-11 Use and Possession Prior to Completion (APR 1984)

52.236-12 Cleaning Up (APR 1984)

52.236-13 Accident Prevention (NOV 1991)

Alternate I

52.236-15 Schedules for Construction Contracts (APR 1984)

52.236-16 Quantity Surveys (APR 1984)

52.236-17 Layout of Work (APR 1984)

52.236-21 Specifications and Drawings for Construction (FEB 1997)

Alternate I

52.236-26 Preconstruction Conference (FEB 1995)

52.242-13 Bankruptcy (JUL 1995)

52.243-4 Changes (AUG 1987)

52.244-6 Subcontracts for Commercial Items (MAR 2007)

52.246-21 Warranty of Construction (MAR 1994)

52.248-3 Value Engineering – Construction (SEP 2006)

52.249-2 Termination for Convenience of the Government (Fixed-Price) (MAY 2004)--Alternate

I (SEP 1996)

52.249-10 Default (Fixed-Price Construction) (APR 1984)

52.253-1 Computer Generated Forms (JAN 1991)

AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES

452.232-70 Reimbursement for Bond Premiums – Fixed-Price Construction Contracts (NOV 1996)

452.236-71 Prohibition Against the Use of Lead-Paint (NOV 1996)

452.236-72 Use of Premises (NOV 1996)

452.236-73 Archeological or Historic Sites (FEB 1988)

452.236-74 Control of Erosion, Sedimentation and Pollution (NOV 1996)

452.236-76 Samples and Certificates (FEB 1988)

452.236-77 Emergency Response (NOV 1996)

52.204-7 Central Contractor Registration (JUL 2006)

(a) Definitions. As used in this clause—

“Central Contractor Registration (CCR) database” means the primary Government repository for

Contractor information required for the conduct of business with the Government.

“Data Universal Numbering System (DUNS) number” means the 9-digit number assigned by Dun and

Bradstreet, Inc. (D&B) to identify unique business entities.

“Data Universal Numbering System+4 (DUNS+4) number” means the DUNS number means the number assigned by D&B plus a 4-character suffix that may be assigned by a business concern. (D&B has no affiliation with this 4-character suffix.) This 4-character suffix may be assigned at the discretion of the business concern to establish additional CCR records for identifying alternative Electronic

Funds Transfer (EFT) accounts (see the FAR at Subpart 32.11) for the same parent concern.

“Registered in the CCR database” means that—

(1) The Contractor has entered all mandatory information, including the DUNS number or the DUNS+4 number, into the CCR database; and

(2) The Government has validated all mandatory data fields, to include validation of the

Taxpayer Identification Number (TIN) with the Internal Revenue Service (IRS), and has marked the record ―Active‖. The Contractor will be required to provide consent for TIN validation to the Government as a part of the CCR registration process.

(b)

(1) By submission of an offer, the offeror acknowledges the requirement that a prospective awardee shall be registered in the CCR database prior to award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.

(2) The offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation ―DUNS‖ or ―DUNS+4‖ followed by the DUNS or DUNS+4 number that identifies the offeror’s name and address exactly as stated in the offer. The

PROJ NAME: McCloud Loop Road Paving

DUNS number will be used by the Contracting Officer to verify that the offeror is registered in the CCR database.

(c) If the offeror does not have a DUNS number, it should contact Dun and Bradstreet directly to obtain one.

(1) An offeror may obtain a DUNS number—

(i) If located within the United States, by calling Dun and Bradstreet at 1-866-

705-5711 or via the Internet at http://www.dnb.com; or

(ii) If located outside the United States, by contacting the local Dun and

Bradstreet office.

(2) The offeror should be prepared to provide the following information:

(i) Company legal business name.

(ii) Tradestyle, doing business, or other name by which your entity is commonly recognized.

(iii) Company physical street address, city, state and Zip Code.

(iv) Company mailing address, city, state and Zip Code (if separate from physical).

(v) Company telephone number.

(vi) Date the company was started.

(vii) Number of employees at your location.

(viii) Chief executive officer/key manager.

(ix) Line of business (industry).

(x) Company Headquarters name and address (reporting relationship within your entity).

(d) If the Offeror does not become registered in the CCR database in the time prescribed by the

Contracting Officer, the Contracting Officer will proceed to award to the next otherwise successful registered Offeror.

(e) Processing time, which normally takes 48 hours, should be taken into consideration when registering. Offerors who are not registered should consider applying for registration immediately upon receipt of this solicitation.

http://farsite.hill.af.mil/reghtml/regs/far2afmcfars/fardfars/far/04.htm#TopOfPage

PROJ NAME: McCloud Loop Road Paving

(f) The Contractor is responsible for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government’s reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.

(g)

(1)

(i) If a Contractor has legally changed its business name, ―doing business as‖ name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in Subpart

42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day’s written notification of its intention to:

(A) Change the name in the CCR database;

(B) Comply with the requirements of Subpart 42.12 of the FAR;

(C) Agree in writing to the timeline and procedures specified by the responsible Contracting Officer. The Contractor must provide with the notification sufficient documentation to support the legally changed name.

(ii) If the Contractor fails to comply with the requirements of paragraph (g)(1)(i) of this clause, or fails to perform the agreement at paragraph (g)(1)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the

Contractor indicated in the contract will be considered to be incorrect information within the meaning of the ―Suspension of Payment‖ paragraph of the electronic funds transfer (EFT) clause of this contract.

(2) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see FAR Subpart 32.8, Assignment of…