Pre-Bid Questions and Answers
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 0423 amend 0004.PDF | ||
| d2 maps and drawings.PDF | ||
| List of Attachments for Amendment 0003.pdf | ||
| Bogs_existing_alignment_2.jpg | JPG image | |
| SOI_D2_Water_100609.pdf | ||
| 0423 amend 003.PDF | ||
| Bogs_existing_alignment_1.jpg | JPG image | |
| Bogs_existing_alignment_3.jpg | JPG image | |
| 0423.PDF | ||
| bog_springs_map_and_directions.pdf | ||
| D2_Water_Specs_100323.pdf | ||
| D2_SF30_Amend 0001.pdf | ||
| D2_Water_Maps_100322.pdf | ||
| SOI_D2_Water_100322.pdf | ||
| D2_Water_Drawings_100323.pdf | ||
| D2_Water_SOW_100323.pdf | ||
| D2_DOL WAGE DECISION AZ20080001.pdf | ||
| D2_DOL WAGE DECISION AZ20080005.pdf | ||
| General_Fire_Plan.pdf | ||
| D2_FIRE PLAN.pdf | ||
| D2_DOL WAGE DECISION AZ20080001.pdf | ||
| D2_SOI.pdf | ||
| D2_MAPS and DRAWINGS.pdf | ||
| D2_SOW.pdf | ||
| D2_DOL WAGE DECISION AZ20080005.pdf | ||
| SF 24 Bid Bond.pdf | ||
| D2_SOLICITATION PAGES 1 - 3.pdf | ||
| D2_SOLICITATION PAGES 4 - 47.pdf | ||
| D2_SPECS.pdf |
Show all 29
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
D2 WATER SYSTEMS UPGRADES – IAS REQ#379483
PRE‐BID MEETING – MAY 27, 2010 – 10 AM – BOG SPRINGS CAMPGROUND
NOTES
ITEM # TOPIC
1 BIDDING PROCESS
This is the pre‐bid meeting for the D2 Water Systems Recovery Act project. The information presented here today will be taken directly from the documents supplied on the fbo.gov website. Any information that is new or different will be posted after this meeting at that same website. Specific questions about how the bids will be evaluated and awarded should be directed to the Contract Specialist listed on the website – Tanjia Harris‐Davis. All bids are due June 14, 2010, in electronic form, by 2 pm Pacific time. (Please note that the bid due date has been revised to June 21, 2010.)
Field visit today will include review of three of the projects in the package: Bog Springs, Kent Springs, and Pena Blanca water systems.
2 HIGHLIGHTS FROM SPECIFICATIONS
GENERAL
Contractor is to furnish all materials, equipment, transportation, labor, and supervision necessary to complete the work.
All work on each water system must comply with ADEQ standards as a public water system.
Garbage service and electricity are not available for use at any of the sites at this time; water from the Bog Springs tanks can be used for construction water as available, up to a maximum of 20,000 gallon; water from Pena Blanca Lake can be used for construction at the Pena Blanca site.
Staying in campgrounds other than as a member of the public (paying fees, 14‐day stay limit) is not allowed; use of the restroom facilities during the duration of the contract will be possible.
It is the Contractor’s responsibility to familiarize themselves with the existing conditions and notify the Government of any discrepancies shown in the bid documents.
The Contractor shall provide safety fencing around the work area to protect the public, employees, and concessionaires.
A schedule for all work must be submitted and approved by the Government prior to commencement of construction.
SCHEDULE RESTRICTIONS: Bog and Kent Springs projects are located in Protected Activity Centers for Mexican Spotted Owls. No construction is allowed from March 1 through August 31. Additionally, Kent Springs is a cabin rental – the work for this site is scheduled for October 11 through 22.
HIGHLIGHTS FROM SPECIFICATIONS
GENERAL (continued)
A pre‐work meeting will be held at each site for clarification of the projects.
All work shall be completed within 120 days from NTP.
Protection of natural resources is required and NEPA documentation must be followed. Contractor is to clearly stake limits of construction for Government approval and maintain those stakes.
Upon completion of the project, all demolished improvements become the property of the Contractor, and must be disposed of off Forest Service land.
Safety and security of the Contractor’s equipment and materials at the construction site is not guaranteed. The Contractor is responsible for providing the necessary security for equipment, materials, and work until final acceptance by the Government.
No live trees are to be cut without Government permission.
Best Management Practices, including the use of wattle and silt fence, will need to be followed.
Submittals are required, including shop drawings, manufacturer’s literature, and samples, and must be approved by the Government prior to their use on the project.
Quality control, including water line pressure testing, is required and outlined in detail in the specifications. Compaction and concrete tests are required for well building and road crossings.
As‐built drawings will be required – they do not need to be sealed by a Registered Land Surveyor.
Salvage of usable existing equipment is required.
UTILITIES
All utility lines are required to be installed with marking tape AND tracer wire.
Locations of new utilities will need to be staked by the Contractor and approved by Government.
There are some very specific inspection points called out in Section 2510, including approval of trenching, pipe placement, etc – please note and review this section before preparing your bid.
Utility line locations will be as per the drawings or as staked in the field.
Minimum cover for water lines – 2 feet, unless otherwise noted.
Thrust blocks will be required as necessary and as indicated in the supplied details.
Suitable fill material from required excavations shall be exhausted before using import fill material, except in the case of the water operations shed and road crossings.
3 BOG SPRINGS CAMPGROUND
Site used for recreation – system services this campground and recreation sites further north, to Proctor Parking area and beyond.
Served by Bog Springs – existing system includes sediment tank, two 20,000‐gallon tanks, chlorination equipment, and approximately 1.4 miles of distribution main.
Whole system is potable.
Project includes:
Repair of the leak at one of the existing 20,000‐gallon tanks and replacement of the chlorination equipment.
Installation of fencing around the sediment tank, including access gates.
Removal and replacement of nearly 1.4 miles of PVC and GSP main with new 2” HDPE. This alignment travels cross‐country.
Removal and replacement of approximately 500 feet of existing PVC that leads to the Madera Picnic Area with 1” HDPE.
Replacement of all appurtenances currently directly on the main (valves, air release valves, pressure‐reducing valves, etc.) – no system “branches” will be replaced.
Please note the special pressure‐reducing valve configuration needed maintain pressure control of the line. Substantial pressure is received at lower recreation areas.
4 KENT SPRING CABIN
Site is part of the cabin‐rental program, and is actively rented.
Served by Kent Spring.
System will be replaced starting at current tank location and ending at service entrance to house.
Project includes:
Removal and replacement of the existing water tank with a new 1,000‐gallon potable water tank. Tank site has been relocated to a site under the house deck.
Removal and replacement of approximately 400 feet of GSP main between the existing tank location and the house. New main is to be 2” HDPE.
Removal of the existing shed structure. New enclosure to be placed under deck.
Installation of a new pressure tank, pump, meter, chlorinator, and other equipment in the new enclosure.
Fencing of the tank to prevent unauthorized access.
Connection of the new system to the house system.
5 PENA BLANCA LAKE
Recent work on lake has been completed, and new work including a boat ramp and restroom is anticipated.
Long‐term plans for this are extensive.
Served by an on‐site well – well pump is not operable.
Tanks will be replaced as a part of a separate Recovery Act project.
Project includes:
Refurbishment of the well with a new pump.
Construction of a new water operations shed to house the new chlorinator, meter, and other requested equipment.
Fencing of the new tank as well as the water operations shed and well; access gates are included.
Replacement of 300’ of GSP/PVC main between the tanks and the well with new 2” HDPE.
Re‐establishment of power to the well site. Power will be obtained from an overhead electric line located 1/8th of a mile away. Design includes a pad‐ mounted transformer, and underground lines. Please note ground/digging conditions.
Installation of a new water pedestal.
6 QUESTIONS AND ANSWERS
a CAN THE CONTRACTOR STAY IN THE KENT SPRINGS CABIN DURING WORK? Yes, provided they follow the same rules as all renters of the cabin.
b DOES THE EXISTING BOG SPRINGS LINE STAY IN SERVICE DURING CONSTRUCTION? No.
c DOES THE EXISTING LINE NEED TO BE REMOVED OR ABANDONED IN PLACE? Removed and replaced.
d HOW DEEP ARE THE EXISTING LINES? Approximately 2 feet deep.
e WHAT IS THE REQUIRED TANK REPAIR? This item is not longer needed f DOES A GEOLOGIST NEED TO LOG THE WELL DRILLING? No.
g WHERE IS THE WELL AT BOG SPRINGS? There is no well – it is fed by a spring approximately 1 mile away.
h IS THE AIR RELEASE VALVE AT THE FENCE NEAR THE BOG TANKS BEING REPLACED? Yes.
6 QUESTIONS AND ANSWERS (continued) i WHAT HAPPENS WHEN THE LINES GO UNDER PAVEMENT? We will either place the pipe in the shoulder of the road or use the existing pipe as a sleeve.
j ARE THE CARSONITE SITES BEING REPLACED? No.
k THERE IS A LOT OF ROCK AT KENT SPRINGS – IS THE BURY DEPTH STILL 2 FEET? No, in instances where there is substantial rock interference at this project site, the trench depth will be modified to accommodate 8” of cover. The entire trench will need to be filled with AB when this option is exercised.
l CAN 1.5”HDPE BE USED AT KENT SPRINGS? Yes, In addition to the base bid, please provide an alternate bid that details this proposed change.
m WHY IS THERE 400 LF OF PIPE IN THE KENT SPRINGS CONTRACT? This is an overestimate that allows more freedom in tank placement should it not fit in the proposed location.
n CAN WE HAND‐MIX THE CONCRETE SLABS? Yes o WHERE DOES THE WATER LINE ENTER THE HOUSE? Our understanding is that it enters the house by the existing spigot.
p WHERE DOES THE ELECTRIC LINE RUN FOR KENT SPRINGS? It will be run from the panel, through the attic, to the water enclosure.
q WHERE DOES THE ELECTRIC LINE RUN FOR PENA BLANCA? Please refer to the supplied plans.
r HOW OLD IS THE WELL AT PENA BLANCA? Old – exact age is unknown s WILL THE ELECTRIC LINE RUN IN CONTAMINATED SOIL? No, the trenchline avoids areas of dredged material. It does run along an area where bedrock is known to exist.
t WHERE IS THE TRANSFORMER LOCATED? Per the supplied plan, at the pole.
u WHAT IS THE DEPTH OF THE PENA BLANCA WELL? Our records show close to 400 feet.
6 QUESTIONS AND ANSWERS (continued) v DO WE REPLACE THE RISED IN THE WELL? Yes, please follow what is outlined in the specifications.
w WILL THE POWER COMPANY PROVIDE POWER TO THE TRANSFORMER? Typically this is the case. Coordination with Unisource is the responsibility of the Contractor.
x CAN WE GET A SKETCH OF THE ELETRICAL AT PENA BLANCA – IS A METER NEEDED?
The information supplied on fbo.gov is all we have at the moment. A meter will be required – it’s base will be located at the service entrance at the water operations shed.
y IS THE 1” CONDUIT BETWEEN THE WELL AND TANK SUFFICIENT FOR THE WIRE? We believe it is. If there is a concern, please feel free to submit a bid option for 1.5” conduit.
z IS THE 2HP PUMP LARGE ENOUGH FOR THE SYSTEM? Yes, pump curves show that it is adequately sized.
aa CAN THE DROP PIPE FOR THE WELL BE GALVANIZED INSTEAD OF STAINLESS STEEL? We will accept PVC as an option to this requirement – please provide a bid option to the base bid package that details this choice.
bb ARE CONCRETE VALVE BOXES REQUIRED FOR THIS PROJECT? Yes, as shown on the supplied details. Please include costs for valve boxes in the appropriate appurtenance line items.