RECOVERY - Stabilization of the Mexican Canyon Trestle
Solicitation number
AG-9702-S-10-0349
Issued by

About this file

Amendment 0002 page 2 of 2

View the file

Other files

File Type Posted
AMEND 0003 PG 1.pdf PDF
AMEND 0002 PG 1.pdf PDF
38_AG-9702-S-10-0349.doc DOC document
38_AMEND 0001.pdf PDF
Attachment 5 - Phase II MCT Drawings.pdf PDF
38_AG-9702-S-10-0349.doc DOC document
Attachment 4 - Bent 11 to 22.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTINUATION SHEET PAGE 2 OF 2

AG-9702-S-10-0349 Amendment 0002____________________________________________________

Furnished Material (GFM) and this is noted in the Osmose report pages included in the solicitation.

Question 1:Will the report in 557.05 need to be stamped by a register engineer?
Answer 1:Sections 557.03 Inspection, 557.04, 557.04 Analysis, and 557.05 Reports were completed under Phase 1 of the project and are not a requirement of this project.
Question 2:Will the existing slash piles along the road be removed prior to reclaiming the road or if not, how would the slash piles be handled?
Answer 2:It is the intent of the Forest Service to have the slash removed before contract award.
Question 3:How will the road be reclaimed and did we anticipate a requirement to haul out any of the material?
Answer 3:The intent is to have the material excavated during the construction of the road and crane pads pulled back up and contoured to match the grade existing prior to construction. All of the material in place today is native and there is not a need to haul material out. Any material hauled in to construct access to the south side during Phase II will need to be removed from the site once construction is complete.
Question 4:Could the crane pads be constructed on the south side of the drainage similar to the crane pads used during Phase I?
Answer 4:Yes, the hope is to minimize the number of trees required to be removed to allow construction of the crane pads.

The original solicitation dated April 28, 2010 is replaced by the revised solicitation dated May 10, 2010.

The revisions are in Section M, Evaluation factors for Award.

Based on these changes, the solicitation is extended to June 3, 2010, at 2:00 p.m., Pacific Time. Please submit your offers according to the instructions for proposal submission in Section L, Instruction, Conditions, and Notices to Offerors.