i

FOREST SERVICE

SUPPLEMENTAL SPECIFICATIONS

FOR

WALNUT CANYON CREEK

BRIDGE REPAIRS

ROAD NO. 651 - M.P. 0.1

U.S.D.A Forest Service, Region 3 Coconino National Forest Flagstaff Ranger District

Coconino County, Arizona

Prepared by:

GREAT WEST ENGINEERING

2501 Belt View Drive

Helena, MT 59601 ii

WALNUT CANYON CREEK BRIDGE REPAIRS

Road No. 651 - M.P. 0.1

FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS

TABLE OF CONTENTS

PREFACE

101 – TERMS, FORMAT, AND DEFINITIONS

102 – BID, AWARD, AND EXECUTION OF CONTRACT

103 – SCOPE OF WORK

104 – CONTROL OF WORK

105 – CONTROL OF MATERIAL

106 – ACCEPTANCE OF WORK

107 – LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

108 – PROSECUTION AND PROGRESS

109 – MEASUREMENT AND PAYMENT

151 – MOBILIZATION

153 – CONTRACTOR QUALITY CONTROL

155 – SCHEDULES FOR CONSTRUCTION CONTRACTS

156 – PUBLIC TRAFFIC

157 – SOIL EROSION CONTROL

203 – REMOVAL OF STRUCTURES AND OBSTRUCTIONS

208 – STRUCTURE EXCAVATION AND BACKFILL

574 – BRIDGE REPAIR

622 – RENTAL EQUIPMENT

PREFACE

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.

101 – TERMS, FORMAT, AND DEFINITIONS

101.01 Meaning of Terms.

Add the following:

Delete all references in FP-03 to Transportation Acquisition Regulations (TAR).

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau

Add the following to (b) SI Symbols:

mp Milepost ppm Part Per Million

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.

Culvert--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

http://www.nist.gov/

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.

Forest Service--The United States of America, acting through the Forest Service, U.S.

Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

R ig ht of

W ay

R oa ds id e R oa ds id e

C le ar in g W id th

R oa dw ay

C le ar in g Li m it

X Y

G ro un d

Li ne

Tr av el ed

W ay C L

B er m S ur fa ce C ou rs e B as e

C ou rs e

Fi ll

S lo pe

B ac k S lo pe

D ra in ag e D itc h

G ro un d

Li ne

S ub gr ad e

R oa d B ed

S ha pe s an d di m en si on s w ill va ry to fi t l oc al c on di tio ns

S ee d ra w in gs fo r t yp ic al s ec tio ns

X a nd Y d en ot e cl ea rin g ou ts id e of ro ad w ay

N ot e:

Right - of - Way Line

Right - of - Way Line

Clearing Limit

Shoulder

Shoulder

102 – BID, AWARD, AND EXECUTION OF CONTRACT

102 Bid, Award, and Execution of Contract Delete Section 102 in its entirety.

103 – SCOPE OF WORK

Deletions Delete all but subsection 103.01 Intent of Contract.

The projects consist of the upgrades and repairs to the Walnut Canyon Creek Bridge.

Improvements consist of, but are not limited to, removal and disposal of asphalt & timber components, new glued-laminated treated timber curbs, new glued-laminated treated timber stringers, object markers, running planks, gate removal and placement, and other miscellaneous items.

The project is located in the Flagstaff Ranger District of the Coconino National Forest, Coconino County, Township 19 North, Range 9 East, Section 16. Refer to the location map on the title sheet of the plans.

104 – CONTROL OF WORK

Delete sections 104.01, 104.02, and 104.04.

Add the following subsection:

104.06 Use of Roads by Contractor

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 – CONTROL OF MATERIAL

105.02 Material Sources.

Add the following before the first paragraph.

Sources have been designated for this project as follows:

Materials Stockpile Site – Government Furnished –The Contractor will be allowed to stockpile material, crushed aggregate, and bridge components, adjacent to the existing roadway. Materials must be stockpiled in such a manner as to allow for safe passage of the general public along the road access and to avoid damage to any trees at the bridge site. Provide the CO 72 hours advance notification prior to stockpiling any materials at the construction site.

Under (b) Contractor-located sources add the following:

Prior to any pit development or use of materials, the pit site shall be approved by the CO that the pit site is free of noxious weed as listed on the "All States Noxious Weeds List”.

106 – ACCEPTANCE OF WORK

106.07 Delete

Delete subsection 106.07.

107 – LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

107.05 Responsibility for Damage Claims.

Delete the entire subsection.

107.06 Contractor’s Responsibility for Work.

Delete the following.

“except as provided in Subsection 106.07”

107.09 Legal Relationship of the Parties.

Delete the entire subsection:

107.10 Environmental Protection.

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

• Exact time and location of spill including a description of the area involved.

• Containment procedures.

• Summary of any communications contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

108 – PROSECUTION AND PROGRESS

108 Delete Delete Section 108 in its entirety.

109 – MEASUREMENT AND PAYMENT

109 Deletions Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Add the following:

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

Change the following:

“(b) Cubic yard” to “(c) Cubic yard”.

Add the following definitions:

(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

(q) Actual Quantities (AQ). These quantities are determined from measurements of completed work.

151 – MOBILIZATION

151.01 Description

Add the following requirements:

Noxious Weed Control Requirements:

All construction equipment to be used at the job site shall be cleaned and certified free of noxious weeds and their seeds prior to entrance on to forest lands, whether they are owned, leased or borrowed by the Contractor or any subcontractors. “Construction equipment” does not include personal vehicles or support equipment that remains on the main travel route.

Cleaning shall occur off forest land.

Construction equipment shall be visually inspected by the COR and each one certified in writing to be reasonably clean and weed free. Inspections will take place at a forest administrative site with the Contractor providing at least 24 hours notice. The location of the administrative site is to be agreed upon in advance between the COR and the Contractor or Subcontractor. Equipment is expected to proceed directly to the job site following the inspection and to not leave the designated weed management district wherein the job site exists.

Certification shall remain valid for each identified piece of equipment for the duration of the specified project and only as long as the equipment remains at the job site or within the designated weed management district. Equipment leaving the designated weed management district will need to be recertified as weed free before being allowed to return to the job site.

151.03 Payment

Include all costs associated with the cleaning of equipment in the unit price for Mobilization.

153 – CONTRACTOR QUALITY CONTROL

Add the following.

153.07. Project Submittals

At a minimum the contractor shall provide project submittals as shown on the below Submittal Log. Submittal requirements are listed in the Standard Specifications, Supplemental Specifications, and Plans.

Submittal Log

Log No.

Incidental to

Pay Item(s) Description of Submittal

Type of Submittal

Requirement found in

Specification No.

/Drawings

Additional Specification References

1 151 Weed Free Material Source Certification

Material Certification FSSS 105.02(b)

2 151 Contractor Quality Control Plan Plan 153.02 552.09

3 151 Traffic Control Plan Plan FSSS 156.03

4 557 Timber Structures Shop Drawing 104.03 557, Drawings

5 557 Timber Structures: Materials Material Certification 557.19 106, 716, Drawings

6 574 Erection Plan Plan FSSS 574.03 Drawings

7 574 Aggregate Gradation Material Certification 308 703.06, Drawings

8 574 Asphalt Mix Design 403.03 106

9 574 Asphalt Testing Test Results 403.17 106

10 622 Equipment Rental Equipment Approval FSSS 622.02

11 633 Signs & Signposts Material Certification 633 Drawings

155 – SCHEDULES FOR CONSTRUCTION CONTRACTS

155 Delete Delete Section 155 in its entirety.

156 – PUBLIC TRAFFIC

156.03 Accommodating Traffic During Work.

Delete the following from the last paragraph:

According to Subsection 106.07(b)

Delete the first paragraph and replace with the following:

Accommodate traffic according to the requirements set forth below, MUTCD, and Section 635.

Submit a traffic control plan for acceptance at least 30 days before intended use.

Add the following project specific requirements:

The Contractor will be allowed to close Road No. 651 to through traffic for up to 3 continuous weeks.

It is the responsibility of the Contractor to schedule delivery of materials, equipment, and all necessary supplies to the site, to ensure that the bridge repairs can be substantially completed within the specified contract time. The Contractor shall give the CO at least two weeks advanced written notice prior to any road closure. The Contractor shall be responsible for providing, installing, maintaining, and removal of warning signs and Type 3 barricades required for the road closure period. Contractor shall remove and reset the gate prior to any road closures.

156.08 Traffic and Safety Supervisor.

Delete this subsection in its entirety.

156.10 Measurement and payment.

Delete this subsection in its entirety and replace with the following:

Do not measure Public Traffic for payment. Compensation for this item shall be incidental to Mobilization.

157 – SOIL EROSION CONTROL

Arizona Department of Environmental Quality (ADEQ) Requirements This project will disturb less than one acre; however, the Contractor shall submit a notice of intent (NOI) and shall prepare a Storm Water Pollution Prevention Plan (SWPPP) in accordance with the requirements of the ADEQ. The SWPPP shall be submitted to the CO prior to starting construction. It may be submitted in conjunction with or as a supplement to the Erosion Control Plan described above.

Add the following to the third paragraph:

Upon completion of construction at the site, remove all temporary erosion control devices, dewatering materials and equipment from Government property.

203 – REMOVAL OF STRUCTURES AND OBSTRUCTIONS

203.04 Removing Material.

Removal of existing asphalt. Remove existing asphalt AS SHOWN ON THE PLANS in such a way as to avoid any damage to the timber deck. Timber decking which is damaged must be replaced at the Contractor’s expense. Asphalt milling equipment will be allowed.

203.05 Disposing of Material.

Modify this subsection as follows:

(a) Remove from project. Add the following:

All materials designated for removal become property of the Contractor and are to be disposed of by removing off of Forest Service Lands in accordance with all local, state, and federal requirements.

(b) Burn. Delete this section.

(c) Bury. Delete this section.

208 – STRUCTURE EXCAVATION AND BACKFILL

208.01 Description

Add the following:

This work shall include necessary excavation for stringer and backwall installation.

208.04 General.

Add the following:

Use all suitable material in the construction of the roadway embankment and for structural backfill. Field drain and dry excessively wet material that is otherwise suitable for embankment before placement. Place and shape unsuitable or excess material at designated sites shown on the drawings or as directed by the CO.

208.08 Dewatering.

Delete the subsection and add the following:

Submit a dewatering plan according to Section 157.03.

Construct diversion prior to performing any excavation and according to Sections 157.08 and

157.09. Construct diversions using water tight, non-eroding methods. Employ settling basins or other methods so that muddy water is not returned to stream. Install, operate, and remove diversions in a manner that minimizes erosion and sedimentation.

208.11 Compacting.

Delete this section and add the following:

Compaction shall be attained with a minimum of (3) passes of approved mechanical compaction equipment or until there is no visible deflection under load. Ensure that backfill density exceeds the density of the surrounding embankment. Adjust the moisture content of the backfill material to a moisture content suitable for compaction.

208.12 Acceptance.

Delete reference to Table 208-1:

Delete Table 208-1:

574 – BRIDGE REPAIR

Description

574.01 Work. This work includes bridge repairs as indicated on the PLANS which includes but is not limited to: preparation and submission of erection plan, structure excavation and backfill, removal and installation of bridge deck materials and cleaning, removal of existing asphalt, placing and compaction of crushed aggregate, placing and compaction of hot mix asphalt, installation of backing planks, and all hardware as SHOWN ON THE PLANS.

574.02 Requirements. The Contractor shall furnish material that conforms to the plans and the specifications in the following section and subsections:

Removal of Structures and Obstructions Structure Excavation and Backfill……

Minor Crushed Aggregate Hot Asphalt Concrete Pavement

Treated Timber Materials…

574.03 Erection Plan. Contractor must develop and submit an erection plan to the CO for approval a minimum of two weeks prior to planned construction.

574.03 Disposal. All bridge demolition materials and construction refuse shall be disposed of according to FSSS 203.

Measurement

574.03 Method. Use the method of measurement that is DESIGNATED IN THE SCHEDULE

OF ITEMS.

Payment

574.04 Basis. The accepted quantities will be paid for at the contract price for each PAY ITEM

DESIGNATED IN THE SCHEDULE OF ITEMS.

Payment will be made under:

Pay Item Pay Unit

57401 Minor Bridge Repair……………………………………… Refer to Bid Schedule

622 – RENTAL EQUIPMENT

622.02 Rental Equipment.

Delete the first two sentences of the first paragraph and add the following:

Hydraulic Excavator. Provide a track mounted hydraulic excavator, 15 years or newer. Bucket must be equipped with a hydraulic "thumb". Contractor shall supply an excavator of a size capable of performing the excavation needs for the project, or other work that may be directed under this section. Contractor is required to get approval of the size of the Hydraulic Excavator from the Contracting Officer prior to any work taking place.

STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON

FEDERAL HIGHWAY PROJECTS (FP-03 U.S. CUSTOMARY UNITS) (2003)

The Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-03 U.S. Customary Units), 2003 are included by reference. The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract.

The 700-page book entitled “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects (FP-03 U.S. Customary Units), is available from:

Headquarters Washington DC David K. Green Construction Standards Engineer Internet: David.Green@fhwa.dot.gov Mail: Federal Highway Administration

HFPD-3

400 Seventh Street, SW Washington D.C. 20590 http://www.wfl.fha.dot.gov/design/specs/fp03.htm

Applicable sections include (1) Sections designated in the following list and (2) Sections referenced therein.

Section No.

Title

101 Terms, Format, and Definitions 102 Bid, Award, and Execution of Contract 103 Scope of Work 104 Control of Work 105 Control of Material 106 Acceptance of Work 107 Legal Relations and Responsibility to the

Public 108 Prosecution and Progress 109 Measurement and Payment 151 Mobilization 153 Contractor Quality Control 154 Contractor Sampling and Testing 155 Schedules for Construction Contracts 156 Public Traffic 157 Soil Erosion Control mailto:David.Green@fhwa.dot.gov

171 Weed and Disease Prevention 204 Excavation and Embankment 303 Road Reconditioning 308 Minor Crushed Aggregate 403 Hot Asphalt Concrete Pavement 635 Temporary Traffic Control 703 Aggregate 718 Traffic Signing and Marking Material

Optional Asphalt Rehabilitation Specifications

FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS

TO FP-03

U.S. CUSTOMARY UNITS

101 - Terms, Format, and Definitions 101.00_nat_us_07_25_2005

101.01_nat_us_01_22_2009

101.01 Meaning of Terms

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03_nat_us_06_16_2006

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau

Add the following to (b) SI symbols:

mp Milepost ppm Part Per Million

101.04_nat_us_03_29_2007

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.

Culvert--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

http://www.nist.gov/

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.

Forest Service--The United States of America, acting through the Forest Service, U.S.

Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

102 - Bid, Award, and Execution of Contract 102.00_nat_us_02_16_2005

102 Bid, Award, and Execution of Contract

Delete Section 102 in its entirety.

103 - Scope of Work 103.00_nat_us_02_16_2005

Delete all but subsection 103.01 Intent of Contract.

104 - Control of Work 104.00_nat_us_06_16_2006

Delete Sections 104.01, 104.02, and 104.04.

104.06_nat_us_02_17_2005

Add the following subsection:

104.06 Use of Roads by Contractor

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 - Control of Material 105.02_nat_us_01_18_2007

105.02 Material Sources.

105.02(a) Government-provided sources.

Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.

105.05_nat_us_05_12_2004

105.05 Use of Material Found in the Work.

Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:

Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.

106 - Acceptance of Work 106.07_nat_us_05_11_2004

106.07 Delete

Delete subsection 106.07.

107 - Legal Relations and Responsibility to the Public 107.05_nat_us_05_11_2004

107.05 Responsibility for Damage Claims.

107.06_nat_us_06_16_2006

107.06 Contractor’s Responsibility for Work.

Delete the following from the first paragraph.

“except as provided in Subsection 106.07”.

107.09_nat_us_06_16_2006

107.09 Legal Relationship of the Parties.

107.10_nat_us_06_16_2006

107.10 Environmental Protection.

Add the following:

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

• Exact time and location of spill including a description of the area involved.

• Containment procedures.

• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

108 - Prosecution and Progress 108.00_nat_us_02_16_2005

108 Delete.

Delete Section 108 in its entirety.

109 - Measurement and Payment 109.00_nat_us_02_17_2005

109 Deletions Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

109.02_nat_us_06_16_2006

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Add the following:

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

Change the following:

“(b) Cubic yard” to “(c) Cubic yard”.

Add the following definition:

(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

109.03_nat_us_03_29_2005

109.03 Weighing Procedures and Devices.

(c) Project weighing system.

Add the following:

For aggregates weighed for payment, adjust scale weights of material to deduct the daily average moisture content in excess of 2 percentage points over optimum moisture as determined by AASHTO T 99 or the designated compaction method. If moisture determination is necessary, determine the daily average moisture content in accordance with AASHTO T 255, from not less than three representative samples of aggregate taken at random intervals each day that aggregate is being weighed.

151 - Mobilization 151.03_nat_us_08_05_2005

151.03 Payment

Delete the entire subsection and add the following:

153 - Contractor Quality Control 153.02_nat_us_02_17_2005

153.02 Contractor Quality Control Plan.

Add the following:

Submit written proposals for approval of alternate AASHTO or State approved test methods.

Alternate methods may be allowed based on documented equivalence to the specified method.

153.04_nat_us_10_24_2007

153.04 Records.

Delete all but the first sentence

154 - Contractor Sampling and Testing 154.01_nat_us_05_24_2005

154.01 Description

Delete the last sentence of the first paragraph.

155 - Schedules for Construction Contracts 155.00_nat_us_05_11_2004

155 Delete.

Delete Section 155 in its entirety.

156 - Public Traffic 156.00_nat_us_04_17_2007

Delete Section 156 in its entirety and replace with the following:

156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.

Material

156.02 Conform to the MUTCD and the following Sections and Subsections:

Construction sign panels 633 Retro-reflective sheeting 718.01 Temporary concrete barrier 618 Temporary plastic fence 710.11 Temporary traffic control devices 718.22

156.03 General. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Delays may not exceed _30 minutes at any one time followed by an open period of no less than _30_ minutes.

Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved. Post construction signs and traffic control devices in conformance with MUTCD. All required signs will be in place and approved prior to beginning work on project.

If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.

156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:

(a) Furnish and install traffic control devices before the start of construction operations.

(b) All detours outside of clearing limits will be approved in writing by the Contracting

Officer as part of the traffic control plan.

(c) Install only those traffic control devices needed for each stage or phase.

(d) Relocate temporary traffic control devices as necessary.

(e) Remove devices that no longer apply to the existing conditions.

(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.

(g) Keep temporary traffic control devices clean.

(h) Remove all temporary traffic control devices upon contract completion or when approved.

(i) When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.

156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s).

Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.

Prior to closing roads during construction, give written notice to the Contracting Officer at least 10 days in advance.

Table 156-1 Temporary Road Closures

Road

Number From

Terminus To

Terminus Maximum

Consecutive Days of Closure

Minimum Consecutive Days Open

N/A N/A N/A N/A

156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.

Measurement and Payment

156.07 Do not measure Public Traffic for payment. Compensation is made as an indirect payment.

156.03_nat_us_02_24_2005

157 - Soil Erosion Control 157.03_nat_us_02_24_2005

157.03 General

Delete the entire subsection and replace with the following:

Prior to the start of construction, submit a written plan that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction.

Do not begin work until the necessary controls for that particular phase of work have been implemented. Do not modify the type, size, or location of any control. An alternate erosion control plan with all necessary permits may be submitted 30 days before intended use.

Incorporate all permanent erosion control features into the project at the earliest practicable time, as outlined in the approved plan.

When erosion control measures are not functioning as intended, immediately take corrective action.

171 - Weed and Disease Prevention 171.00_nat_us_03_30_2005

171.01 This work consists of washing and treating construction equipment to remove seeds, plants, and plant fragments from the equipment before the equipment is used on National Forest System lands.

171.02 Conform to the following Subsection:

Water 725.01

Construction Requirements

171.03 General . Notify the CO in writing at least 15 days before moving any construction equipment onto National Forest System lands. Construction equipment does not include cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas outside of National Forest System lands.

Perform all work at a location designated on the plans or other locations approved in writing.

Provide the CO with an opportunity to monitor the washing and inspection.

171.04 Equipment. Use a high pressure washing system.

For work on National Forest System lands, use a washing system that traps all wash water and either stores it for removal from National Forest System lands or recycles the water for continued use. If the equipment recycles the water, provide adequate filters for seed removal. Dispose of the filter material and removed seeds in an approved manner. Do not mix soaps, detergents, or other chemicals with the wash water.

For work at a commercial washing facility, use an approved facility.

171.05 Washing. Wash the sides, tops, and undercarriages of all construction equipment.

Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment.

171.06 Inspection. Inspect the washed construction equipment, including the undercarriage, to ensure that the washing removed the dirt, debris, and seeds from the construction equipment.

Rewash the construction equipment as necessary or as directed.

171.07 Acceptance. Weed prevention will be evaluated under Subsection 106.02.

171.08 Do not measure weed prevention for payment.

171.09 Include all costs associated with the Section 171-Weed Prevention in the unit price for Section 151-Mobilization.

204 - Excavation and Embankment 204.00_nat_us_03_26_2009

Replace Section 204 in its entirety with the following:

204.01 This work consists of excavating material and constructing embankments. This includes furnishing, hauling, stockpiling, placing, disposing, sloping, shaping, compacting, and finishing earthen and rocky material.

204.02 Definitions.

(a) Excavation. Excavation consists of the following:

(1) Roadway excavation. All material excavated from within the right-of-way or easement areas, except subexcavation covered in (2) below and structure excavation covered in Sections 208 and 209. Roadway excavation includes all material encountered regardless of its nature or characteristics.

(2) Subexcavation. Material excavated from below subgrade elevation in cut sections or from below the original groundline in embankment sections. Subexcavation does not include the work required by Subsections 204.05, 204.06(b), and 204.06(c).

(3) Borrow excavation. Material used for embankment construction that is obtained from outside the roadway prism. Borrow excavation includes unclassified borrow, select borrow, and select topping.

(b) Embankment construction. Embankment construction consists of placing and compacting roadway or borrow excavation. This work includes:

(1) Preparing foundation for embankment;

(2) Constructing roadway embankments;

(3) Benching for side-hill embankments;

(4) Constructing dikes, ramps, mounds, and berms; and

(5) Backfilling subexcavated areas, holes, pits, and other depressions.

(c) Conserved topsoil. Excavated material conserved from the roadway excavation and embankment foundation areas that is suitable for growth of grass, cover crops, or native vegetation.

(d) Waste. Excess and unsuitable roadway excavation and subexcavation that cannot be used.

204.03 Conform to the following Subsections:

Backfill material 704.03 Select borrow 704.07 Select topping 704.08 Topping 704.05 Unclassified borrow 704.06 Water 725.01

Construction Requirements

204.04 Preparation for Roadway Excavation and Embankment Construction. Clear the area of vegetation and obstructions according to Sections 201 and 203.

204.05 Reserved.

204.06 Roadway Excavation. Excavate as follows:

(a) General. Do not disturb material and vegetation outside the construction limits.

Incorporate only suitable material into embankments. Replace any shortage of suitable material caused by premature disposal of roadway excavation. Dispose of unsuitable or excess excavation material according to Subsection 204.14.

At the end of each day's operations, shape to drain and compact the work area to a uniform cross-section. Eliminate all ruts and low spots that could hold water.

Retrieve material deposited outside of the clearing limits as directed by the CO. Place unsuitable material in designated areas.

(b) Rock cuts. Blast rock according to Section 205. Excavate rock cuts to 6 inches below subgrade within the roadbed limits. Backfill to subgrade with topping or with other suitable material. Compact the material according to Subsection 204.11

(c) Earth cuts. Scarify earth cuts to 6 inches below subgrade within the roadbed limits.

Compact the scarified material according to Subsection 204.11.

(d) Pioneer Roads. Road pioneering, slash disposal, and grubbing of stumps may proceed concurrently with excavation. Conduct excavation and placement operations so material to be treated under Section 201 will not be incorporated into the roadway unless specified in the slash treatment method. Maintain drainage during pioneering operations.

Remove snow and ice in advance of the work and deposit beyond the roadway limits in a manner that will not waste material or generate sediment. Do not incorporate snow and ice into embankments. Place snow or ice in a manner to prevent resource damage.

204.07 Subexcavation. Excavate material to the limits designated by the CO. Take cross-sections according to Section 152. Prevent unsuitable material from becoming mixed with the backfill. Dispose of unsuitable material according to Subsection 204.14. Backfill the subexcavation with topping, or other suitable material. Compact the material according to Subsection 204.11.

204.08 Borrow Excavation. Use all suitable roadway excavation in embankment construction.

Do not use borrow excavation when it results in excess roadway excavation. Deduct excess borrow excavation from the appropriate borrow excavation quantity.

Obtain borrow source acceptance according to Subsection 105.02. Develop and restore borrow sources according to Subsection 105.03. Do not excavate beyond the established limits. When applicable, shape the borrow source to permit accurate measurements when excavation is complete.

204.09 Preparing Foundation for Embankment Construction. Prepare foundation for embankment construction as follows:

(a) Embankment less than 4 feet high over natural ground. When designated, remove topsoil and break up the ground surface to a minimum depth of 6 inches by plowing or scarifying. Compact the ground surface according to Subsection 204.11.

(b) Embankments over an existing asphalt, concrete, or gravel road surface. Scarify gravel roads to a minimum depth of 6 inches. Scarify or pulverize asphalt and concrete roads to 6 inches below the pavement. Reduce all particles to a maximum size of 6 inches and produce a uniform material. Compact the surface according to Subsection 204.11.

(c) Embankment across ground not capable of supporting equipment. Dump successive loads of embankment material in a uniformly distributed layer to construct the lower portion of the embankment. Limit the layer thickness to the minimum depth necessary to support the equipment.

(d) Embankment on an existing slope steeper than 1V:3H. Cut horizontal benches in the existing slope to a sufficient width to accommodate placement and compaction operations and equipment. Bench the slope as the embankment is placed and compacted in layers. Begin each bench at the intersection of the original ground and the vertical cut of the previous bench.

204.10 Embankment Construction. Incorporate only suitable roadway excavation material into the embankment. When the supply of suitable roadway excavation is exhausted, furnish unclassified borrow to complete the embankment. Obtain written approval before beginning construction of embankments over 6 feet high at subgrade centerline. Construct embankments as follows:

(a) General. At the end of each day's operations, shape to drain and compact the embankment surface to a uniform cross-section. Eliminate all ruts and low spots that could hold water.

During all stages of construction, route and distribute hauling and leveling equipment over the width and length of each layer of material.

Compact embankment side slopes flatter than 1V:1.75H with a tamping type roller or by walking with a dozer. For slopes 1V:1.75H or steeper, compact the slopes as construction of the embankment progresses.

Where placing embankment on one side of abutments, wing walls, piers, or culvert headwalls, compact the material using methods that prevent excessive pressure against the structure.

Where placing embankment material on both sides of a concrete wall or box structure, conduct operations so compacted embankment material is at the same elevation on both sides of the structure.

Where structural pilings are placed in embankment locations, limit the maximum particle size to 4 inches.

(b) Embankment within the roadway prism. Place embankment material in horizontal layers not exceeding 12 inches in compacted thickness. Incorporate oversize boulders or rock fragments into the 12-inch layers by reducing them in size or placing them individually as required by (c) below. Compact each layer according to Subsection 204.11 before placing the next layer.

Material composed predominately of boulders or rock fragments too large for 12-inch layers may be placed in layers up to 24 inches thick. Incorporate oversize boulders or rock fragments into the 24-inch layer by reducing them in size or placing them individually according to (c) below. Place sufficient earth and smaller rocks to fill the voids. Compact each layer according to Subsection 204.11 before placing the next layer.

(c) Individual rock fragments and boulders. Place individual rock fragments and boulders greater than 24 inches in diameter as follows:

(1) Reduce rock to less than 48 inches in the largest dimension.

(2) Distribute rock within the embankment to prevent nesting.

(3) Place layers of embankment material around each rock to a depth not greater than that permitted by (b) above. Fill all the voids between rocks.

(4) Compact each layer according to Subsection 204.11 before placing the next layer.

(d) Embankment outside of roadway prism. Where placing embankment outside the staked roadway prism, place material in horizontal layers not exceeding 24 inches in compacted thickness. Compact each layer according to Subsection 204.11.

204.11 Compaction. Compact the embankment using one of the following methods as specified:

(a) Compaction A. Use AASHTO T 27 to determine the amount of material retained on a Number 4 sieve. If there is more than 80 percent retained on the No. 4 sieve use procedure (1).

If there is 50 to 80 percent retained on the No. 4 sieve use procedure (2). If there is less than 50 percent retained on the No. 4 sieve use procedure (3).

(1) Adjust the moisture content to a level suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Use compression-type rollers at speeds less than 6feet per second and vibratory rollers at speeds less than 3 feet per second.

Compact each layer of material full width with one of the following and until there is no visible evidence of further consolidation.

(a) Four roller passes of a vibratory roller having a minimum dynamic force of 40,000 pounds impact per vibration and a minimum frequency of 1000 vibrations per minute.

(b) Eight roller passes of a 20-ton compression-type roller.

(c) Eight roller passes of a vibratory roller having a minimum dynamic force of 30,000 pounds impact per vibration and a minimum frequency of 1000 vibrations per minute.

Increase the compactive effort for layers deeper than 12 inches as follows:

• For each additional 6 inches or fraction thereof, increase the number of roller passes in (a) above by four passes.

• For each additional 6 inches or fraction thereof, increase the number of roller passes in (b) and (c) above, by eight passes.

(2) Use AASHTO T 99 to determine the optimum moisture content of the portion of the material passing a No. 4 sieve. Multiply this number by the percentage of material passing a No. 4 sieve, and add 2 percent to determine the optimum moisture content of the material.

Adjust the moisture content of material classified A-1 through A-5 to a moisture content suitable for compaction. Adjust the moisture content of material classified A-6 and A-7 to within 2 percent of the optimum moisture content.

Use compression-type rollers at speeds less than 6 feet per second and vibratory rollers at speeds less than 3 feet per second. Compact each layer of material full width according to

(1) above.

(3) Classify the material according to AASHTO M 145. For material classified A-1 or A- 2-4, determine the maximum density according to AASHTO T 180, method D. For other material classifications, determine the optimum moisture content and maximum density according to AASHTO T 99, method C.

Adjust the moisture content of material classified A-1 through A-5 to a moisture content suitable for compaction. Adjust the moisture content of material classified A-6 and A-7 to within 2 percent of the optimum moisture content.

Use compression-type or vibratory rollers. Compact each layer of material full width to at least 95 percent of the maximum density. Determine the in-place density and moisture content according to AASHTO T 310 or other approved test procedures. When required, use AASHTO T 224 to correct for coarse particles.

(b) Compaction B. Place material by end dumping to the minimum depth needed for operation of spreading equipment. Adjust the moisture content of the material to obtain a mass that will not visibly deflect under the load of the hauling and spreading equipment. Operate compaction equipment over the full width of each layer until there is no visible evidence of further consolidation or, if when a sheepsfoot roller is used, the roller “walks out” of the layer.

Make at least three complete passes.

(c) Compaction C. Place material by end dumping to the minimum depth needed for operation of spreading equipment. Level and smooth each embankment layer before placing the next layers. Operate hauling and spreading equipment uniformly over the full width of each layer. Construct a solid embankment with adequate compaction by working smaller rock and fines in with the larger rocks to fill the voids, and by operating hauling and spreading equipment uniformly over the full width of each layer as the embankment is constructed.

204.12 Ditches. Slope, grade, and shape ditches. Remove all projecting roots, stumps, rock, or similar matter. Maintain all ditches in an open condition and free from leaves, sticks, and other debris.

Form furrow ditches by plowing or using other acceptable methods to produce a continuous furrow. Place all excavated material on the downhill side so the bottom of the ditch is approximately 18 inches below the crest of the loose material. Clean the ditch using a hand shovel, ditcher, or other suitable method. Shape to provide drainage without overflow.

204.13 Sloping, Shaping, and Finishing. Complete slopes, ditches, culverts, riprap, and other underground minor structures before placing aggregate courses. Slope, shape, and finish as follows:

(a) Sloping. Leave all earth slopes with uniform roughened surfaces, except as described in (b) below, with no noticeable break as viewed from the road. Except in solid rock, round tops and bottoms of all slopes including the slopes of drainage ditches. Round material overlaying solid rock to the extent practical. Scale all rock slopes. Slope rounding is not required on tolerance class D though M roads.

If a slide or slipout occurs on a cut or embankment slope, remove or replace the material, and repair or restore all damage to the work. Bench or key the slope to stabilize the slide. Reshape the cut or embankment slope to an acceptable condition.

(b) Stepped slopes. Where required by the contract, construct steps on slopes of 1⅓V:1H to 1V:2H. Construct the steps approximately 18 inches high.