Attachment1_ SPS_sps.pdf
PDF 238 KB Posted
- Attached to
- DAKOTA PRAIRIE GRASSLANDS -Burning Coal Vein Campground Aggregate Removal and Replacement
- Solicitation number
- AG-87BJ-S-10-0019
About this file
Attachment 1 -SPS
View the file
Other files
| File | Type | Posted |
|---|---|---|
| COVER_SHEET.pdf | ||
| AG_87BJ_S_10_0019_CONST_RFQ.pdf | ||
| Attachment2_BCV Drawings.pdf | ||
| Attachment3_General Decision Number.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1 AG-87BJ-S-10-0019
Medora Ranger District, Dakota Prairie Grasslands
Burning Coal Vein Campground Aggregate Removal and Replacement
INDEX
Attachment 1
SPECIAL PROJECT SPECIFICATIONS
SPS 101 Terms, Format & Definitions 3/05 DPG
SPS 102-108 General Requirements 3/05 DPG
SPS 109 Measurement and Payment 3/05 DPG
SPS 153 Contractor Quality Control & Quantity Measurement 4/06 DPG
SPS 156 Public Traffic 1/08 DPG
SPS 204 Excavation and Embankment 4/06 DPG
SPS 301 Untreated Aggregate Courses 1/08 DPG
SPS 301(A&B)Aggregate Hauling 1/09 DPG
SPECIAL PROJECT SPECIFICATION
Section 101 – Terms, Format and Definitions
101.03
Abbreviations
Available Avail
Coating Coat
Construction Const
Contracting Officer Representative COR
Government Gov’t.
Includes Culvert Excavation Incl Culv Exc
Individual Removal of Trees Ind Removal/Trees
Large Lg
Left Lt
Logs Log
Medium Med
Millimeter Mil
One Thousand Gallons Mile M.Gals.MI. or MGM
Options Opt
Placement Method P.M.
Right Rt
Slash Treatment S.T.
Small Sm
Steel Stl
Structure Str
Timber Tbr
Treatment Treat
Typical Typ
03 SPS 101 - 1 DPG (3/05)
Section 101 – Terms, Format, and Definitions
101.04
Definitions
Add the following:
”Noxious Weeds or Weeds. Any exotic plant species established or that may be introduced in the
State which may render land unfit for agriculture, forestry, livestock, wildlife or other beneficial uses and which is designated by the State’s Department of Agriculture, or by the County’s weed management district, or by other appropriate agencies having jurisdiction.
Weed Management District. A weed management district is any area of land identified for the purpose of weed management or control. Such an identified land area may be, but is not limited to one of the following: a project or job site, a County, two or more Counties or a National Grassland.”
Section 102 – Bid, Award and Execution of Contract
Delete entire section
Section 103 – Scope of Work
Delete Subections 103.02 – 103.05
Section 104 – Control of Work
Delete Subsections 104.03 and 104.04
03 SPS 101, 102, 103, 104 - 2 DPG (3/05)
Section 106 – Acceptance of Work
106.05
Statistical Evaluation of Work and Determination of Pay Factor (Value of Work)
Delete this subsection
106.07
Partial and Final Acceptance
Section 107 – Legal Relations and Responsibility to the Public
107.04
Railroad Protection
107.05
Responsibility for Damage Claims
Section 108 – Prosecution and Progress
Delete entire section
03 SPS 106, 107, 108 -1 DPG (3/05)
Section 109 - Measurement and Payment
109.02
Measurement Terms and Definitions
Under “(b) Cubic yard”
(1) Cubic Yard in place, “ add the following:
”(d) Aggregate Base or Surfacing, Compacted in Place. The measurement computed using measurements of material in the compacted state on the project.
109.06
Pricing of Adjustments
109.07
Eliminated Work
109.08
Progress Payments
109.09
Final Payment
03 SPS 109 – 1 DPG (3/05)
Section 153 – Contractor Quality Control & Quantity Measurement
CONSTRUCTION
153.02
Contractor Quality Under “ Contractor Quality Control Plan”, add the following:
Control Plan
(3) Production Phase
(d) Random sampling and/or measurement plan prepared in accordance with requirements in Table 153.”
A log of all samples that are taken by the Contractor shall be maintained for the duration of the contract, and provided to the Contracting Officers Representative
(COR) upon request.
TABLE 153
SAMPLING, TESTING AND MEASUREMENT REQUIREMENTS
Key to symbols used in table:
CT: Sampling and testing by contractor’s personnel identified by name on the approved contractor’s Q/C plan. Interim approval of personnel submitted will be based on specified training or experience requirements.
Final approvalwill be based on observation of work performance on the project.
FS: Sampling, testing, measuring and/or data furnished by the Forest Service.
Note: The minimum frequency shown in this table is for contractor Quality Control sampling and testing. The contractor can run additional samples over the minimum number specified in the table. These additional samples can be taken in any manner, at any time desired by the contractor. Quality assurance sampling and testing by the Forest Service may be done at any time or location.
SUBSECTION REFERENCE
REQ’D SAMPLING, TESTING RESPONSIBILITY FOR MINIMUM FREQUENCY
AND MEASUREMENTS SAMPLING/TESTING
204.17 Construction Tolerances
Measurement of Construction Tolerances CT/CT For Roads, Parking Lot and
Width and Grade Camping Spurs:
5 random samples
03 SPS 153-1 DPG (4/06)
Section 156 - Public Traffic
156.02
Delete reference to Section 635
156.03
Accomodating Traffic During Work
Replace with the following:
Traffic control for this project is subsidiary to items that require it. Traffic control shall be as a minimum a ROAD WORK AHEAD sign at the intersection of Forest Highway #3 and National Forest Service Road #772 and at the entrance into the campground.
The approach road can be closed during the week from 7 AM to 7 PM.
The Contractor shall notify the assigned Contracting Officers Representative
(COR) or the Medora District Ranger, at (701) 227-7800, a minimum of 72 hours before beginning work on the project.
156.07
Nighttime Operations
156.08
Traffic and Safety Supervisor
156.10
Measurement and Payment
All costs of this work shall be considered subsidiary to other items in this contract and the Contractor will not be paid an additional amount for this work.
03 SPS 156 – 1 DPG (1/08)
Section 204 - Excavation and Embankment
204.10
Embankment Construction.
(a) General.
Delete the third paragraph and add the following:
Compact embankment layers for roads and parking lot with hauling equipment as construction progresses by Compaction Method D.
204.11
Compaction.
Delete the first paragraph and replace it with the following:
For compaction method D, no sieve test is required.
Add the following compaction method:
(D) Layer Placement Method - (Hauling and Spreading Equipment). Place material by end dumping to the minimum depth needed for operation of spreading equipment. Level and smooth each embankment layer before placing the next layers. Operate hauling and spreading equipment uniformly over the full width of each layer. Construct a solid embankment with adequate compaction by working smaller rock and fines in with the larger rocks to fill the voids and by operating hauling and spreading equipment uniformly over the full width of each layer as the embankment is constructed.
03 SPS 204-1 DPG (4/04)
204.13 Sloping, Shaping, and Finishing.
Delete section (d) and add the following:
(d) Finishing. For surfaced roads, parking lots, camping spurs and picnic table/fire ring pads, remove all rock larger than six (6) inches from the top six (6) inches of the subgrade. For all roads, parking lots and camping spurs finish the roadbed to be smooth and uniform, and shaped to conform to the typical sections. Remove unsuitable material from the roadbed and replace it with suitable material. Finish roadbeds to the construction tolerance class E.
Ensure that the subgrade for the roads is visibly moist during shaping and dressing. Bring low sections, holes, cracks, or depressions to grade with suitable material. Maintain proper ditch drainage.
204.14 Disposal of Unsuitable or Excess Material.
Delete the text of the first paragraph:
Table 204-1 Sampling and Testing Requirements.
Add the following note to the table:
(2) Using compaction Method (D), AASHTO M 145, T 99, T 180, and T 310 are not required for earth embankment test methods.
204-2—Construction Tolerances:
Tolerance Class E allowable maximum deviations are:
- Roadbed width - maximum deviation shall be +1.0 foot
- Subgrade elevation - maximum deviation shall be +0.5 feet
- Centerline Alignment - maximum deviation shall be + or – 1.0 foot
- Slopes, Excavation & Embankment (% slope) – maximum deviation shall be + or – 5%
03 SPS 204-2 DPG (4/06)
Section 301 - Untreated Aggregate Courses
301 Title Change.
Change the title to: Section 301. Aggregate Courses
301.01 Description
The Government Furnished aggregate material is in a stockpile located about thirty-five
(35) miles west of the project in Section 8 T136N R104W. The designated haul route shall not be changed except by written permission. The Contractor shall maintain haul routes to pre hauling condition or better. The haul routes shall be inspected by the
Forest Service and the Contractor prior to hauling aggregate material. The Contractor is responsible for loading, hauling, placing and compacting the aggregate required for the campground, access road and overlook road. The quantity of Aggregate Courses in the
Summary of Quantities is compacted in place on the roads, parking lots, camping spurs, trails, walkways and picnic table/fire ring pads. Loose quantity hauled, placed and compacted shall include additional material necessary to overcome the compaction effort.
The Contractor shall maintain a record of number of truck loads and amounts of aggregate hauled and supply the record to the Contracting Officers Representative
(COR).
301.03 General.
Add the following:
Request written approval by the Contracting Officers Representative (COR) of the roadbed, camping spurs, parking lots, trails, walkways and picnic table/fire ring pads a minimum of forty-eight (48) hours before placing aggregate.
301.04 Mixing and Spreading.
Delete the first sentence of the first paragraph and add the following:
Spread the aggregate in a uniform layer, with no segregation of size, and to a loose depth that will provide the required compacted thickness.
Route and distribute leveling equipment over the width and length of each layer.
03 SPS 301-1 DPG (1/08)
301.05 Compacting.
Delete the first and third paragraphs and add the following:
Compact the aggregate on the roads and parking lots using the following method:
Compaction A. Layer Placement (Hauling & Spreading Equipment)
Place aggregate by end dumping to the minimum depth needed for operation of the spreading equipment. Adjust the moisture content of the aggregate to obtain a mass that will not visibly deflect under the load of the hauling and spreading equipment. Compact the aggregate on the roads and parking lot by operating spreading and hauling equipment over the full width of each layer of the aggregate.
For the compaction method, blade the surfaces of each layer during the compaction operations to remove irregularities and produce a smooth surface.
301.06 Surface Tolerance.
Delete the first paragraph and add the following:
Thickness and Width requirements:
The maximum variation from the compacted specified thickness is one (1) inch. The compacted thickness shall not be below the specified thickness and the average thickness of four (4) random measurements for the road segment, camping spurs, parking lots or picnic table/fire ring pads is within + 1 inch of the specified thickness.
The maximum variation from the specified width will not exceed +12 inches at any point.
301.08 Acceptance.
Delete subsections (a) and (b)
301.09 Measurement.
The quantity of 301 in the Schedule of Items is compacted in place on the roadways, camping spurs, parking lots, trails, walkways and picnic table/fire ring pads. Loose quantity loaded, hauled, placed and compacted shall include such additional material necessary to overcome the compaction factor. Contractor shall take precautions in loading of aggregate from stockpiles to prevent segregation of material.
03 SPS 301-2 DPG (1/08)
Table 301-1: Delete Table 301-1 in FP-03 and replace with the following:
Table 301-1—Acceptance Sampling and Testing Requirements to be done by Contractor.
Material or
Product
Type of
Acceptance
(Subsection)
Characteristic Category Test Methods
Specifications
Sampling
Frequency
Point of
Sampling
Split
Sample
Aggregate
Width
Measured and tested conformance
(Subsection
106.04)
Width - - 4 random locations on the road, spurs, parking lot and pads.
Roadbed after processing
Aggregate
Thickness
Measured and tested conformance
(Subsection
106.04)
Thickness - - 4 random locations on the road, spurs, parking lot and pads.
Roadbed after processing
03 SPS 301-3 DPG (1/08)
SECTION 301 (A) & (B) - AGGREGATE HAULING
301.A & B Description
This item is for the loading and hauling of aggregate from a stockpile located in Section 35
T137N R101W about 5 miles from the disposal pit and from a stockpile located in Section
35 T139N R102W about 16 miles from the disposal pit.
The Contractor shall maintain a record of number of truck loads and amounts of aggregate hauled and supply the records to the Contracting Officers Representative
(COR).
301.A General
Site one (1) is approximately five (5) miles northeast of the disposal pit in Section 10
T136N R102W and is located in the SW ¼ SW ¼ of Section 35 T137N R101W just off the south side of the Forest Service Route #769. The Contractor shall load, haul and dump about two hundred sixty (260) cubic yards from this site.
301.B General
Site two (2) is approximately sixteen (16) miles north of the disposal pit and is located in the NE ¼ NE ¼ of Section 35 T139N R102W just off the north side of Forest Highway 3
(FH-3). The Contractor shall load, haul and dump about three hundred sixty (360) cubic yards from this site.
The Contractor shall remove all the aggregate from the two (2) sites and repair any disturbance to the areas.
03 SPS 301 (A & B)-1 DPG (1/09)