SF-30 Amendment of Solicitation_Mod2.doc

DOC document 67 KB Posted

Attached to
Panguitch Administrative Site Waterline-Dixie NF Federal contract opportunity
Solicitation number
AG-84N8-S-10-0103
Issued by
Department of Agriculture Forest Service R4-Intermountain Region

About this file

SF30_Mod 2 to incorporates Site Visit Meeting notes

View the file

Other files for this federal contract opportunity

Other files attached to Panguitch Administrative Site Waterline-Dixie NF, newest first.
File Type Posted
2_Panguitch Waterline Drawings.pdf PDF
1_RFQ AG84N8S100103 Panguitch Admin Site Waterline.doc DOC document
3_Panguitch Waterline Specifications 6_24_2010.docx DOCX document
RFQ AG84N8S100103 Panguitch Admin Site Waterline.doc DOC document
Panguitch Waterline Drawings.pdf PDF
SF-30 Amendment of Solicitation_Mod1.doc DOC document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE
PAGE OF PAGES
84N8
1
2
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
4. REQUISITION/PURCHASE REQ. NO.
5. PROJECT NO. (If applicable)
2
08/05/2010
6. ISSUED BY
CODE
7. ADMINISTERED BY (If other than Item 6)
CODE

USDA- Forest Service R4 - Utah Acquisition Support Center 2222 West 2300 South Salt Lake City, UT 84119-2020

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code)
(X)
9A. AMENDMENT OF SOLICITATION NO.
X
AG-84N8-S-10-0103

9B. DATED (SEE ITEM 11)

07/26/2010

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE
FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

XThe above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, X is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(X)
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN

THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

X
D. OTHER (Specify type of modification and authority)

Attach Site Visit/Pre-Bid meetings notes

E. IMPORTANT: X Contractor _ is not, is required to sign this document and return __copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.

1. This amendment is to incorporate the Site Visit notes from August 3, 2010 (page 2-3 to this document)

2. This amendmend is also to attached a revised solicitation (3_Panguitch Waterline Specifications 6-24-2010).

Solcitation response date is NOT extended and all other terms and conditions are to remain the same.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Elouise Fowler, Contracting Officer

15B. CONTRACTOR/OFFEROR
15C. DATE SIGNED
16B. UNITED STATES OF AMERICA
16C. DATE SIGNED

08/05/2010

(Signature of person authorized to sign)

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

30-105
STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

PRE-BID TRIP MEETING NOTES

PANGUITCH ADMINISTRATIVE SITE WATERLINE

RFQ# AG-84N8-S-10-0103

CONTRACTOR ATTENDEES:

Tim Strong

Red Rock Earthmovers, Inc

Wayne Olsen

PCI

Fred Barlow

Perco Rock

Neal Barton

Bartons Lot Care

Robert Dennett

Dennett Construction, Inc.

Kevin New

Ron New & Sons

Berklee Holm

Long Horn West (Came after the group had adjourned)

GOVERNMENT ATTENDEES:

Lu Fowler FS Contracting Officer (CO)

Phone # 435-865-3763

Paul Dastrup FS Contracting Officers Representative (COR)

Phone # 435-676-9352 or 435-676-3025 cell

Robert Miller

FS Contract Inspector

Phone # 435-676-9356

The pre-bid meeting was held on August 3, 2010 at 9:00 a.m. We met at the Powell Ranger District Office for a brief meeting then went to the project site and walked through the project. The pre-bid meeting notes are part of an amendment to the above referenced solicitation.

The following is a list of questions and answers:

1. Question. Will the Forest Service pay impact fees relating to the new water meter? Answer. Yes, the Forest Service has already arranged with Panguitch City for installation of the new water meter and has paid the required fees.

2. Question. Will bacteriological tests be required and who is responsible? Answer. Yes, See section 221100 3.6. Bacteriological tests are required and the contractor is responsible for taking samples and paying for the test.

3. Question. Is compaction testing required? Answer. Yes. See Table 014100. Change this specification to require testing only in the road crossing. Trench outside the road crossing still requires compaction as specified in section 312000, but does not require testing.

4. Question. Who pays for the compaction testing? Answer. Contractor

5. Question. Can the line to the trailer pads be moved to avoid crossing the lawn? Answer. The payment for waterline is for actual quantities installed. If lines are moved slightly, payment will be for actual lengths.

6. Comment. This contract is subject to Davis Bacon wage rates. The rates are included in the solicitation.

7. Question. Are bonds required? Answer. A bid bond is not required, but performance and payments bonds are required.

8. Question. What is the requirement for disposal of excess material from the trenching? Answer. Section 024100 requires hauling to a disposal area. The disposal area shall be arranged by the contractor at a site off of National Forest Lands.

9. Question. If Blue Stakes will not mark the electric line from the meter to the trailer pads who is responsible for marking? Answer. Contractor should try and make special arrangements with Blue Stakes or directly with the power company to have the lines marked.

10. Question. What size is the secondary waterline? Answer. The size is not known.

The original solicitation has several typos and is missing several specifications. This will be corrected in Amendment #2.