MesaCampgroundToiletRetrofitRFQ.doc
DOC document 367 KB Posted
- Attached to
- Mesa Campground Toilet Retrofit
- Solicitation number
- AG-8399-S-12-0019
About this file
SOLICITATION
View the file
Other files
| File | Type | Posted |
|---|---|---|
| sf-301.doc | DOC document | |
| Title Sheet Mesa Toilet Retro-Model.pdf | ||
| MesaFinalSF 1442.pdf | ||
| Mesa 1 Toilet Retrofit-Model.pdf | ||
| Concrete Demo-DEMOLITION.pdf | ||
| Concrete Layout-CONCRETE.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CONSTRUCTION
SOL. NO.: AG-8399-S-12-0019
UNIT: Gila N.F.
PROJ. NAME: Mesa Campground Toilet Retrofit
CONSTRUCTION
SOL. NO.: AG-8399-S-12-0019
UNIT: Gila N.F.
PROJ. NAME: Mesa Campground Toilet Retrofit
(Page Left Intentionally Blank) (Page Left Intentionally Blank)
PART I—THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES/COSTS
SCHEDULE OF ITEMS
1.0. The Federal Government has a requirement for the Mesa Campground Toilet Retrofits of the Gila National Forest located in the Southwestern Region, Region 3. The Government anticipates award of a Request For Proposal (RFP) contract that contains Firm-Fixed Pricing for the each Task/Line Item proposed. Contractor shall provide all expertise, labor, supervision, services, equipment, tools, supplies (not provided by the government), permits, licenses, transportation, and incidentals necessary to perform all the repair work required on the Mesa Campground Toilet Facilities for which the desired outcome is in strict accordance with the standards attached. The awarded contract shall constitute the entire agreement including all terms and conditions applicable to the contract.
| Item No. |
| Description |
| Quantity |
| Unit of Measure |
| Price |
| 01001 |
| Toilet Retrofit Upper Toilet |
| 1 |
| Lump Sum |
| $__________ |
| 01002 |
| Toilet Retrofit Lower Toilet |
| 1 |
| Lump Sum |
| $__________ |
| Total |
| $__________ |
Prices shall include all applicable taxes, including Federal and New Mexico Gross Receipts Tax
See Section M for evaluation criteria. Offeror’s must submit Experience Questionnaire in response to Section M.
Please Note: There will be a Pre-Bid Site Visit on July 31, 2012 starting at 10:00 a.m. at the Wilderness Ranger District Office, Mimbres, New Mexico. Contact Harley Allsup at (575) 388-8261 if you will be attending the site visit.
Submit your offers to the physical address on Page 1, block 7 of Standard Form 1442.
NOTE: FACSIMILE OR EMAIL OFFERS WILL NOT BE CONSIDERED FOR AWARD.
SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK
DESCRIPTION OF WORK
The Project consists of retrofitting the inside and outside of two similar existing flush type toilet facilities. Major work items include, are not limited to, removal/disposal of items listed and installation of items listed. REMOVAL/DISPOSAL of existing fixtures, existing stall partitions, existing windows, existing plumbing, existing wood back walls, existing ceiling, existing concrete sidewalk/slabs, and existing doors and frames as indicated on drawings. INSTALLING new fixtures at new locations and heights, new stall partitions, new windows, new plumbing, gypsum board on walls and ceilings, new 3’ x 7’ doors and frames, toilet accessories, painting, epoxy grit floor, new concrete, grading and backfilling for concrete, and any needed concrete repairs on walls.
PREBID SHOWING & PROJECT LOCATION
Please contact Harley Allsup (575) 388-8261 Monday through Friday (8:00 a.m. to 4:00 p.m.) to acknowledge desire for attending the prebid tour and any other questions.
Mesa Campground is located in the Wilderness Ranger District of the Gila National Forest, near Silver City, N.M. From Silver City, head East on US 180, for approximately 8 miles. Turn Northeast on Highway 152, for approximately 14 miles. Turn North on Highway 35, for approximately 23 miles. Mesa Campground entrance will be on left hand side.
Phases and Reviews None required.
Codes and Standards Work shall include, but not be limited to the following codes and standards where applicable:
1. American Society for Testing and Materials (ASTM)
2. Occupational Health and Safety Administration (OSHA) standards
3. Environmental Protection Agency (EPA)
4. New Mexico Environment Department (NMED)
5. Americans with Disabilities Act (ADA)
6. Applicable State and local codes.
WARNING SIGNS
The CONTRACTOR shall provide, erect, and maintain all necessary barricades and/or warning signs, suitable for the construction area and shall take all necessary precautions for the protection of the work and safety of the public.
No direct payment will be made for work required by this section, but the costs thereof will be considered to be included in bid prices of the contract. Contractor shall provide the Government a construction control plan during the pre-work meeting.
MATERIAL SUBMITTALS
As per specifications
SCHEDULE AND PAYMENT
A written schedule of work shall be required of the CONTRACTOR. The schedule will be discussed at the pre-work conference. Changes due to unforeseen weather conditions or situations will be allowed under the condition that the CONTRACTING OFFICER’S REPRESENTATIVE (COR) is given a prior notice of the deviation, and approved by the CONTRACTING OFFICER.
Work shall begin within 10 days of Notice to Proceed and completed within 90 days of Notice to Proceed.
Payment shall be considered full compensation for all office/field services, materials required to complete the job, and all miscellaneous work that is required to complete the project.
INSPECTION AND ACCEPTANCE
Work not completed to the standards outlined in the specifications shall be rejected and redone at the CONTRACTOR's expense.
The contractor is responsible for performing inspection services pursuant to the inspection clause and for providing and maintaining inspection records. The government, through its COR, will be monitoring the contractor’s performance on a continuous basis. The method the government will use is random inspection of the contractor’s inspection results. The government COR will perform periodic independent inspections after the contractor has performed their inspection if questions develop regarding the results of the contractor’s inspections. Results of the independent inspections that differ from the results noted by the contractor on their inspections, the costs thereof for the re-inspection costs will be assessed against the contractor. The contractor shall be required to rework the effort until the performance standard is achieved and the added costs of re-inspection charged to the contractor.
PROJECT MAGNITUDE
The Government's estimate is:
Between $100,000 and $250,000.
SECTION 1 – PROJECT REQUIREMENTS
TOILET RETROFIT - 01000
PART 1 - GENERAL
1.1 - Scope
The Project consists of retrofitting the inside and outside of two similar existing flush type toilet facilities. Major work items include, are not limited to, removal/disposal of items listed and installation of items listed. REMOVAL/DISPOSAL of existing fixtures, existing stall partitions, existing windows, existing plumbing, existing concrete sidewalk/slabs, and existing doors and frames as indicated on drawings. INSTALLING new fixtures at new locations and heights, new stall partitions, new windows, new plumbing, gypsum board on ceilings, new 3’ x 7’ doors and frames, toilet accessories, painting, epoxy grit floor, new concrete, and any needed concrete repairs on walls.
1.2 - Included Specifications
A. DEMOLITION
B. CAST-IN-PLACE CONCRETE
C. CARPENTRY
D. CAULKING AND SEALANTS
E. FINISH HARDWARE
F. GYPSUM BOARD ASSEMBLIES
G. COMMERCIAL EPOXY GRIT FLOOR
H. PAINTING
I. TOILET AND BATH ACCESSORIES
J. GENERAL PIPING SYSTEMS
K. ELECTRICAL
PART 2 - PRODUCTS
2.1 See Part 2 for each specification to see required products.
PART 3 - EXECUTION
3.1 - Installation
All items will be installed in accordance with specifications, and manufactures recommendations, and in accordance with the plans. All work will be in accordance with the Uniform Federal Accessibility Standards (UFAS) April 1, 1988.
PART 4 - MEASUREMENT AND PAYMENT
4.1 - Measurement
Will be for work completed and accepted.
4.2 - Payment
Payment will be at contract unit price for work accepted.
PAY ITEM
PAY UNIT
01000
Toilet Retrofit
Total Lump Sum
Upper Toilet
Lump Sum 1
Lower Toilet
Lump Sum 2
Toilet Retrofit includes two similar facilities, the Upper Toilet and the Lower Toilet. Total Lump Sum is equal to Lump Sum 1 plus Lump Sum 2.
SECTION 2 - SITEWORK
DEMOLITION - 02120
PART 1 - GENERAL
This section includes general requirements for all demolition work SHOWN ON THE DRAWINGS or included in other specifications. This shall include the removal and disposal of all material not specifically designated to remain in Government property.
PART 2 - PRODUCTS - NOT APPLICABLE
PART 3 - EXECUTION
3.1 – Construction Material
All material shall be properly disposed of in proper bins, dumpsters, etc. All such dumpsters shall have covers which remain in closed position except when being filled/used.
3.2 - General
Toilet site shall be kept cleared of all debris and shall be cleaned prior to end of work each day.
The contractor may use any means to remove the structure or items SHOWN ON THE DRAWINGS to be removed, as long as the safety of workers and preservation of items to remain is intact.
3.3 – Disposal
All materials removed from job and not designated to be reused shall be properly disposed of at a sanitary landfill.
3.4 – Salvage
Unless notified otherwise, the contractor may, at his option, salvage any materials not designated for reuse or to remain on Government property. Permission must be obtained from the COR or authorized representative before removing any salvage material from job.
3.5 – Cleanup
All demolished materials, dust, and debris shall be removed. Rooms to be re-finished shall be cleared of all other miscellaneous debris before re-construction is to proceed.
PART 4 - MEASUREMENT AND PAYMENT
4.1 - Measurement The work specified herein will not be measured for payment.
4.2 - Payment This work is incidental to other items in this contract and direct separate item payment will not be made.
END OF SPECIFICATION 02120
SECTION 3 – concrete
CAST-IN-PLACE CONCRETE – 03030
PART 1 – GENERAL
1.1 – Quality Assurance
1. Standards: Concrete work shall conform to the latest edition of the following standards and to the Contract Drawings and Specifications.
2. Uniform Building Code, as adopted and modified by the local governing authority.
3. American Concrete Institute "Manual of Concrete Practice", and publication ACI 318 "Building Code Requirements for Reinforced Concrete."
4. American Society for Testing and Materials, Standards as referenced herein.
5. Allowable Tolerances: Flatwork true to plane with maximum deviation of 3/16" in 10 feet, measured in any direction.
PART 2 – PRODUCTS
2.1 – Materials
A. Cement: Portland Cement, Type II, ASTM C150.
1. Color: Concrete shall be uncolored.
B. Aggregate
1. Standard weight aggregates conforming to requirements of ASTM C33.
2. Uniformly graded, clean and durable material free of organic matter or other deleterious substances.
3. The maximum size used in a particular location shall be consistent with the form and dimensions of the section being placed and with the method of compaction. The aggregate sizes shall be such as will produce dense, uniform concrete, free of rock pockets, honey combs and other irregularities unacceptable to an Architectural finished surface.
C. Water: Potable, free of harmful acids, alkalis, oils and organic substances.
D. Admixtures: No air entraining agents shall be used. No admixtures shall be used unless specifically requested by the General Contractor and approved by the Government. When used, the Contractor shall provide evidence from an independent testing laboratory which assures that the admixture will have no deleterious effect upon reinforced concrete; and which indicates chemical compounds, effects upon strength, durability, and resistance to weathering and wear, and curing time.
E. Expansion Joint Filler: 3/8” Bituminous Felt Expansion Joints to be used.
F. Control Joint: As per plan.
2.2 – Mixes
A. Ready Mix Concrete: Transit mixed concrete shall conform to the requirements of Standard Specifications for Ready-Mix Concrete, ASTM C94, Alternative 2.
B. Proportions: Proportions of cement, aggregates and water shall be such as to produce a concrete that will work into all corners and angles of forms, and around reinforcement and inserts; and that will not segregate. Proportions shall be as required within limits specified and shall produce concrete of strength and durability required. Excess free surface water is not permitted.
C. Strength: All concrete to be minimum 3000 psi at 28 days, or as otherwise specified on the plans.
D. Temperature: Concrete when deposited shall have a temperature above 50°F and below 95°F. Design shall provide for duration and type of conveyance and handling.
PART 3 – EXECUTION
3.1 – Subgrade Preparation
Subgrades shall be shaped, dressed, moistened and compacted, as required. Test the subgrade for crown, elevation, and density in advance of placing pavement. Remove and replace soft or unsuitable material with approved material. Bring low sections, holes, or depressions to the required grades with approved material, shape the entire sub-grade to line, grade and cross, and thoroughly compact as specified.
3.2 – Preparation For Concrete Placement A. Place embedded items, and expansion strips as indicated; maintain items securely in place. The Contractor shall give reasonable and adequate advance notice of concrete placement to all subcontractors and concerned parties who must place items to be embedded in or pass through the concrete to be poured, e.g. pipes, anchor bolts, sleeves, reglets, casings, etc., as shown on the drawings or otherwise required. Notify Government immediately of any conflict with structural elements.
B. Water shall be removed from place of deposit before concrete is placed unless otherwise permitted by the Government. All laitance and other unsound material shall be removed from hardened concrete before additional concrete is placed.
C. Screeds shall be rigidly secured in place. When the formwork is cambered, screeds shall be set to a like camber to maintain the proper concrete thickness.
D. Upon completion of preparatory operations, but prior to placement of concrete, Government shall be notified for observation. No concrete shall be placed without notification. The Government may regard preparatory work unacceptable if he has not had reasonable opportunity for such observation.
3.3 – Formwork
A. Formwork shall be structurally sound and rigid and shall conform in section and dimension to the Drawings. Forms are subject to the approval of the Government. Oil forms each time they are used.
B. Shoring and forms shall be cleaned of all loose dirt and other foreign matter. Dampen dry soil and forms just prior to pouring. Avoid excessive watering.
3.4 – Reinforcement
A.
Welded Steel Wire Fabric: ASTM A185 plain type; in flat sheets; unfinished.
3.5 – Accessory Materials
A.
Tie Wire: Minimum 16 gauge annealed type.
B.
Special Chairs, Bolsters, Bar Supports, Spacers Adjacent to Weather Exposed Concrete Surfaces: Plastic coated steel type; size and shape as required.
3.6 – Joints
Joints not indicated on the drawings shall be so made and located as to least impair the strength of the structure, while reducing the effects of shrinkage. The location of joints not indicated on the drawings are subject to the approval of the Government.
Install pre-molded expansion joints where indicated on the drawings. Expansion joint strips shall be installed to the full depth of the joint. Where caulked expansion joints are indicated on the drawings, set the top of expansion joint strips down from the finished top surface of slabs to the depth required to receive the caulking.
3.7 – Placing Concrete
A. Concrete shall be deposited as nearly as practicable in its final position to avoid segregation due to re-handling or flowing. The placing of concrete shall be carried on at such a rate that concrete is at all times plastic and flows readily into the place. No concrete that has been contaminated by foreign material shall be used, nor shall re-tempered concrete be used unless approved by the Government.
B. Once placing has started, it shall be carried on as a continuous operation until placement of the panel or section is completed. When construction joints are necessary, they shall be made as specified herein.
C. No concrete shall be dropped freely into place from a greater height than four feet. Tremies shall be used for placing concrete where the drop is in excess of such height.
D. All concrete shall be thoroughly consolidated by suitable means during placement. It shall be thoroughly worked around reinforcement and embedded fixtures and into the corners of the forms. Vibration shall be transmitted directly to the concrete; in no case shall it be transmitted through the forms. The vibration shall be sufficiently intense to cause the concrete to settle readily into place and to visibly affect the concrete over a radius of at least 18". Vibrators shall not, however, be used to transport concrete or force concrete to flow horizontally. Vibration shall be supplemented by manual forking or spading adjacent to the forms on exposed faces in order to secure smooth, dense surfaces. If, for any reason, the surfaces or interiors have voids or are in any way defective, such concrete shall be repaired as directed by the Government, and no defective work shall be patched or repaired without the prior inspection and approval of the Government.
E. Slump
1. Concrete samples shall be measured for slump in accordance with ASTM C143. The slump of the concrete shall be the minimum that is practicable.
2. In any case, the slump shall not exceed 4-1/2" without the expressed approval of the Government.
3.8 – Hot Weather Requirements
Concrete pours during hot weather should be scheduled for early morning hours to the maximum extent possible in order to permit finishing operations to be completed by noon.
3.9 – Cold Weather Requirements
A. Adequate equipment shall be provided for heating concrete materials and protecting concrete during freezing or near-freezing weather. No frozen materials or materials containing snow or ice shall be used.
B. All reinforcement, forms, fillers, and ground with which the concrete is to come in contact shall be free from snow or ice. Whenever the temperature of the surrounding air is below 40°F or higher after placement. Adequate means shall be provided for maintaining this temperature for 4 days. When high-early-strength concrete is used, a temperature of at least 45°F shall be maintained for 3 days. In either case, any additional time necessary to ensure proper curing of the concrete shall be provided as directed by the Government. The housing, covering, or other protection used in connection with curing shall remain in place and intact at least 24 hours after the artificial heating is discontinued. No dependence shall be placed on salt or other chemicals for the prevention of freezing.
3.10 – Removal Of Forms
Forms shall be removed in such a manner as to ensure the complete safety of the structure.
3.11 – Cement Mortar
Cement mortar for the repair of imperfect concrete work, the filling of holes left by form bolts and ties, and the filling of voids around piping through concrete shall consist of cement and sand mixed in the same proportion as used for the concrete being repaired, with only sufficient water to give the required consistency, but in no case shall the water-cement ratio be more than that specified for Class "A" concrete. Mortar that has not been placed within 30 minutes of mixing shall be discarded.
3.12 – Curing
Concrete shall be protected against loss of moisture, rapid drying, or temperature changes, mechanical injury or injury from rain or flowing water for a period of at least seven days in accordance with requirements of ACI 308 and ACI 305, as specified herein. Curing shall commence as soon as free water has disappeared from the surfaces after finishing.
3.13 – Finishing The Contractor shall apply a medium broom finish to all exterior concrete surfaces. The methods and procedures for this finish shall be approved by the Government prior to execution.
3.14 – Defective Materials And Concrete
Concrete work shall be considered defective if not formed in accordance with the requirements of the drawings and specifications. Concrete may be judged to be unacceptable if it is not true to intended line, grade or plane, or contains sand streaks, objectionable joints, excessive pitting or dusting, voids or rock pockets detrimental to structure or finish, or which shows other irregularities, marking or deficiency including improper strength.
Defective concrete work shall be removed and replaced with new concrete acceptable to the Government, unless suitable correction of defects may be otherwise accomplished as authorized by the Government, and without additional cost to the Government.
3.15 – Protection Of Completed Work
During the curing period, protect the concrete from damaging mechanical disturbances, water flow, loading, shock, impact and vibration.
3.16 – Cleaning
After the concrete work is complete, carefully remove all excess concrete and all protective materials, broom the surfaces and remove all mortar and other foreign materials. All concrete inserts, anchor bolts, etc., shall be cleaned of all concrete after forms are removed.
PART 4 - MEASUREMENT AND PAYMENT
4.1 - Measurement The work specified herein will not be measured for payment.
4.2 - Payment This work is incidental to other items in this contract and direct separate item payment will not be made.
END OF specification 03030
SECTION 6 - WOOD
CARPENTRY - 06100
PART 1 - GENERAL
1.1 - SCOPE
Work Included: Perform all work necessary and required for the construction of the project as indicated. Such work includes, but is not necessarily limited to, the furnishing and installing of all carpentry work SHOWN ON THE DRAWINGS and specified herein.
1.2 - Related Work Specified Elsewhere
07900 - Caulking and Sealants
1.3 - Codes and Standards
The "Uniform Building Code", latest Edition, is hereby made a direct part of this specification and shall be considered the minimum standard. All carpentry work included in this contract shall conform with the applicable requirements therein except where modified to a higher standard.
1.4 - Miscellaneous Items
Carpentry work and miscellaneous items and their related components which are to be furnished and/or installed under this Section are not necessarily individually described. Rough carpentry work and miscellaneous items not mentioned or described shall be furnished and/or installed in accordance with the intent of drawings and specifications and as required to complete the work.
PART 2 - PRODUCTS
2.1 - Materials
Framing Lumber: Grading of lumber shall comply with the "Standard Grading and Dressing Rules", latest edition, of the West Coast Lumber Inspection Bureau. Grade shall be stamped on lumber at the mill.
(a) Wood grounds, nailers and blocking. Blocking shall be framed into all wall assemblies where attachments shall be hung from the wall – guardrails, handrails, fixtures, etc.
(b) Plates and nailing strips in contact with concrete shall be redwood or pressure treated Grade 2 & BTR D.F.
(c) Framing with dimension lumber.
1. Light Framing: Stud, No. 3 or Standard grade.
2. Species: Any species of grade.
(d) Miscellaneous Lumber, Blocking and Nailers:
1. Moisture Content: 19 percent
2. Grade: Standard grade light framing.
(e) Hardware: Furnish all items of hardware, required to complete the work. Bolts, nuts, and washers shall be hot-dipped galvanized, conforming to ASTM-A153.
(1) Nails: Common wire.
(2) Bolts: Standard mild steel, square or hexagonal head machine bolts with matching nuts and cut washers as indicated.
(3) Screws: Standard #10-16x1" Phillips drive wafer head screws.
PART 3 - EXECUTION
3.1 - Installation
Installation of carpentry and millwork shall conform to the applicable requirements of the A.W.I. "Architectural Woodwork Institute".
Secure all trim with finishing nails, hot-dip galvanized or aluminum. Do not penetrate bottom of plywood in exposed areas.
No members shall be spliced unless approved by the COR.
All work shall be installed to details shown, plumb, level, true to line, and securely anchored. Nails shall be neatly set and all wood raised in the driving of nails removed. Exterior corner joints shall be mitered.
Prepare all woodwork installed hereunder by cleaning and sanding as required to receive finishes specified in Section 09900.
Hammer or toolmarks or marred surfaces and edges will not be acceptable on exposed finished surfaces, and shall be the basis for rejection of such work.
PART 4 - MEASUREMENT AND PAYMENT
4.1 - Measurement
The work specified herein will not be measured for payment.
4.2 - Payment
This work is incidental to other items in this contract and direct separate item payment will not be made.
END OF SPECIFICATION 06100
SECTION 7
CAULKING AND SEALANTS - 07900
PART 1 - GENERAL
1.1 - Scope A. Provide all materials, labor, equipment, and perform all operations for the complete installation of work in this section:
1. Caulk around new and existing windows and doors subject to repair and restoration.
1.2 - Related Sections A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
B. The work described in this section is related to work described in the following Sections:
1. Section 06100 Carpentry
2. Section 08710 Finish Hardware
3. Section 09255 Gypsum Board Assemblies
4. Section 09900 Painting
5. Section 10800 Toilet and Bath Accessories
6. Section 15430 Soil, Waste, and Drain Systems
PART 2 - PRODUCTS
2.1 - Product Delivery, Storage and Handling
Caulking shall be transferred to site in the original containers with labels intact and seals unbroken. Storage location and method shall be approved by the COR.
2.2 - Submittals
A. Manufacturer's Data: Submit copies of manufacturer's specifications, recommendations and installation instructions for sealants. Sample of caulking for CORs approval.
2.2 - Product Schedule
A. Compatibility: Sealant shall be compatible with joint surfaces, joint fillers and other materials in joint system. Provide only manufacturer's recommended materials which are known to be fully compatible with the actual installation condition, as shown by manufacturers' published data or certification. Color to be approved by COR.
B. Polyurethane Sealant: Non-staining, non-sagging, gun-grade, flexible, durable, polyurethane compound of approved manufacture. "Sikaflex 1A" manufactured by Sika Corp., Lyndhurst, N.J. or approved equal.
PART 3 - EXECUTION
3.1 - Installation
A. Clean joint surfaces immediately before installation of sealant. Remove dirt, old caulking, insecure coatings, moisture, and other substances which would interfere with bond of sealant. Joints and spaces to receive sealant shall be thoroughly dry before installation.
B. Employ only proven installation techniques, which will ensure that sealants will be deposited in uniform, continuous ribbons without gaps or air pockets.
C. Do not allow sealants or compound to overflow or spill onto adjoining surfaces, or to migrate into voids.
D. Cure sealant compound in compliance with manufacturer's instructions, in order to obtain cohesive strength and surface durability.
E. All work and adjacent surfaces shall be left in a clean and undamaged condition.
PART 4 - MEASUREMENT AND PAYMENT
4.1 - Measurement The work specified herein will not be measured for payment.
4.2 - Payment This work is incidental to other items in this contract and direct separate item payment will not be made.
END OF SPECIFICATION 07900
SECTION 8 - DOORS & WINDOWS
FINISH HARDWARE - 08710
PART 1 - GENERAL
1.1 - Description This section includes furnishing and installing finish hardware for doors, as required for a complete installation as SHOWN ON THE DRAWINGS and specified herein.
1.2 - Approved Manufacturers This specification is based on products manufactured or furnished by manufacturing companies as specified below. Equivalent products of other manufacturers will be acceptable subject to conformity with design, function, materials, finishes and hardware of specified products. All products must meet all ADA accessibility requirements.
1.3 - Submittals Submit the following to the COR:
Product Data - Manufacturer's current catalog with description of finish, construction, hardware, and specifications. Include samples of manufacturer's complete current line of available colors for selection.
Proposed Hardware Schedule - Work on this item shall not commence until the COR’s approval has been obtained for these submittals.
1.4 - Product Handling Hardware shall be delivered and stored in packages that permit handling without damage to the contents. Each package shall be marked to permit easy identification and shall contain fastening and installation instructions.
PART 2 - PRODUCTS
2.1 - Manufacturer Hardware shall be new, well manufactured commercial heavy-duty quality or better, free of defects, and suitable for use in the installation indicated. Any items found defective or deficient shall be removed and replaced.
(a) Items for application to metal shall be manufactured to standard templates and furnished with machine or self-tapping screws; others shall be furnished with wood screws.
(b) Exposed fastenings shall be finished to match the item fastened.
2.2 - Requirements
All items must meet all Americans with Disabilities Act Accessibility Guidelines (ADAAG) requirements.
2.2 - Materials The following products shall have its salient characteristics:
1. Locksets: Must conform to all handicap codes and ADA requirements. Non-Handed and will fit door thickness of 1-3/4” and supplied with both backsets of 2-3/8 and 2-3/4”. ANSI Grade 2 rated for light/medium commercial usage. Falcon Lock, Model 915225, Privacy, Satin Chrome, or approved equal.
2. Door Pull Plate, Push Plate, and Kick Plate for restroom doors only. Dimensions for these items are on the drawing. Best, Stanley, Ives or approved equal.
3. Overhead Door Holders w/ closers. Closers should be barrier-free type. ADA compliant with less than 5 lbs of force to open.
4. Stops for each door.
5. Door Trim Units: Edge trim and related trim.
6. Door: 3’ x 7’ x 1-3/4” heavy duty 16 gauge steel, with 16 gauge steel matching frame. Curries or approved equal.
7. Heavy Duty Hinges. Haggar, Stanley, H. Soss or approved equal
8. Windows: to be replaced by a single pane tempered glass with alumnium frame and frosted film to be approved by COR. 10 mm thick clear perspex sheet to match glass size and to be properly fastened on outside of window. Trim finish the perspex sheet.
PART 3 - EXECUTION
3.1 - Installation Every hinged door shall be fitted hardware as specified herein. All hardware shall be installed straight, plumb and true to provide smooth operation.
PART 4 - MEASUREMENT AND PAYMENT
4.1 – Measurement
Finish hardware will not be measured for payment.
4.2 – Payment
This work is incidental to other items in this contract and direct separate item payment will not be made.
END OF SPECIFICATION 08710
SECTION 9 – FINISHES
GYPSUM BOARD ASSEMBLIES - 09255
PART 1 - GENERAL
1.1 - Scope Furnish and install gypsum board assemblies for all the interior walls specified and ceiling for tape and joint compound finish for the restrooms.
PART 2 - PRODUCTS
2.1 - Submittals
Submit product data.
2.2 - Standards
1. Gypsum Association, Washington, D.C., “Application and Finishing of Gypsum Board”, GA-216-89.
2.3 -Materials
1. Gypsum Board:
a. Gypsum Wallboard: ASTM C 36, regular, ½ inch typical thickness, taped edges.
b. Joint Treatment: ASTM C 475 and ASTM C 840, 3-coat system.
c. Installation Standard: ASTM C 840.
2. Texture:
a. Spray texture with “Orange Peel’ finish.
PART 3 - EXECUTION
3.1 - Installation Provide blocking for items such as grab bars, toilet accessories and similar items.
Install gypsum board assemblies true, plumb, level and in proper relation to adjacent surfaces.
Sand and leave ready for finish painting and wall treatment.
All work performed under this section shall be in full compliance with the standard industry specifications and industry guidelines or general industry standards for the United States Gypsum Company.
PART 4 - MEASUREMENT AND PAYMENT
4.1 - Measurement The work specified herein will not be measured for payment.
4.2 - Payment This work is incidental to other items in this contract and direct separate item payment will not be made.
END OF SPECIFICATION 09255
SECTION 9 - FINISHES
COMMERCIAL EPOXY GRIT FLOOR - 09660
PART 1 - GENERAL
1.1 - Scope Provide commercial type Epoxy Grit Floor finish for the entire area of the restrooms.
PART 2 - PRODUCTS
2.1 - Product Delivery, Storage and Handling
Commercial type Epoxy, Clearcoat, and additive for grit finish shall be transferred to site in the original containers with labels intact and seals unbroken.
Storage location and method shall be approved by the COR.
2.2 - Epoxy Schedule A. Restroom: Commercial Epoxy Grit Floor
1. Armorclad Epoxy or approved equal
2. Armorclad Protective Clearcoat or approved equal
3. 36 Grit Non-Skid Additive or approved equal
4. ArmorEtch Cleaning/Etching liquid concentrate or approved equal
2.3 - Submittals Submit examples or literature of the epoxy flooring and color for COR approval.
PART 3 - EXECUTION
3.1 - Installation
1. Prepare surfaces by clearing out loose material
2. Scrub floors with Cleaning/Etching liquid concentrate as directed on instructions
3. Mix and apply epoxy when surface is dry and clear of debris
4. Apply epoxy to a thickness of 1/8 inch
5. Sprinkle Non-Skid Additive evenly on top of epoxy
6. Mix and apply thin layer of Protective Clearcoat on top of epoxy and additive when dry
7. All work performed under this section shall be in full compliance with the standard industry specifications and industry guidelines and general industry standards for the above referenced standards.
PART 4 - MEASUREMENT AND PAYMENT
4.1 - Measurement The work specified herein will not be measured for payment.
4.2 - Payment This work is incidental to other items in this contract and direct separate item payment will not be made.
END OF SPECIFICATION 09660
SECTION 9 - FINISHES
PAINTING - 09900
PART 1 - GENERAL
1.1 - Scope This section covers furnishing all labor, materials and equipment necessary to apply specified paints. Provide painting and surface preparation for interior unfinished surfaces.
PART 2 - PRODUCTS
2.1 - Product Delivery, Storage and Handling
Deliver material to the site in the original containers with labels intact and seals unbroken.
Storage location and method shall be approved by the COR. Remove cloths and waste material which may constitute a fire hazard from the project site daily.
2.2 - Paint Schedule A. Restroom: Gypsum Drywall, Gypsum Ceiling, Trim, and Doors.
Semi Gloss with Smooth Texture
1 coat latex primer
2 coats latex finish
2.3 - Submittals Prepare 8" x 8" samples of top coat finish when requested by the Contracting Officer. When possible apply finishes on identical materials to which they will be applied on project.
Identify each sample as to finish, formula, color name and number and sheen name and gloss units.
PART 3 - EXECUTION
3.1 - Preparation of Surfaces Surfaces to be painted shall be free of dirt, dust, scale, or any other substance which may interfere with the adhesion of the specified coating.
3.2 - Application Samples: Contractor shall submit samples as requested. Colored finishes shall not be applied until colors are approved by the COR.
Apply materials in strict accordance with manufacturer's recommendations.
Finished surfaces shall be free from runs, drops, ridges, waves, laps, brush marks and other blemishes. Apply additional coatings when undercoats, primers and other conditions show through final coat of paint, until paint film is of uniform finish, color and appearance. Special care shall be taken not to injure or spatter adjacent work. Should adjacent work be injured or spattered, it shall be cleaned and the original finish restored. Furnish and lay dropcloths in all areas where painting is being done over concrete slabs.
Caulk interior and exterior joint between block and steel frames for doors. Smooth all caulk joints into a concave surface with finger.
Cloth, cotton wastes, or other materials which constitute a fire hazard shall be placed in closed metal containers or be destroyed at the end of each day's work.
Environmental Conditions: Surfaces shall be painted only when they are free from moisture. Receiving surfaces shall be properly dried out before proceeding with the work
PART 4 - MEASUREMENT AND PAYMENT
4.1 - Measurement The work specified herein will not be measured for payment.
4.2 - Payment This work is incidental to other items in this contract and direct separate item payment will not be made.
END OF SPECIFICATION 09900
SECTION 10 - SPECIALTIES
TOILET AND BATH ACCESSORIES - 10800
PART 1 - GENERAL
Furnish and install the toilet and bath accessories as follows in these specifications and as SHOWN ON THE DRAWINGS:
1. Water Closets
2. Toilet Seats
3. Toilet Paper Holders
4. Toilet Grab bars for people with disabilities
5. Toilet Seat Cover dispensers
6. Soap dispensers
7. Metal Framed Mirrors
8. Sanitary napkin disposal units
9. Paper Towel/Trash receptacle units
10. Partition walls
11. Lavatory Sink
12. Lavatory Faucet
13. Service Sink Faucet
14. Drinking Fountain
1.2 - Related Work Specified Elsewhere 09900 - Painting
1.3 - Approved Manufacturers This specification is based on products manufactured or furnished by the designated manufacturer. Equivalent products of other manufacturers will be acceptable subject to conformity with salient features of specified products.
1.4 - Submittals Alternate Products If the Contractor chooses to install an alternate product to those specified above, the following shall be submitted to the COR for approval:
Product Data - Manufacturer's current catalog with description of finish, construction, hardware, and specifications, including complete current line of available colors, textures, finishes, etc...
Approval - Work on this item shall not commence until the COR approves all these submittals.
PART 2 - PRODUCTS
2.1 - Toilet Accessories:
Sizes and types of accessories shall be as follows:
1. Water Closet: shall be American Standard, model INSTANTO TOILET #2511.012; Elongated bowl, wall mounted, vitreous china with olsenite #10CC seat. Use Sloan Flushometer Royal 152-3, install w/ carrier assembly. Or approved equals.
2. Toilet Seats: shall be American Standard toilet seat to match water closet.
3. Surface Mounted Toilet Paper Holder: shall be a Bobrick B-274 model, satin finish stainless steel or approved equal. Installation shall meet all ADA height requirements.
4. Toilet Grab Bars: shall be Franklin Brass, Model L-820021, 1-1/2-inch diameter toilet compartment bars, satin finish, with 24" and 42" bars, exposed mount or approved equal.
5. Toilet Seat Cover Dispenser: shall be a Bobrick B-221 model, satin finish stainless steel or approved equal. Installation shall meet all ADA height requirements.
6. Soap Dispenser: shall be a Bobrick ClassicSeries™ Surface Mounted Black Soap Dispenser, or approved equal. Installation shall meet all ADA height requirements.
7. Metal Framed Mirrors: shall be McMaster Carr, Model 2799K21, 16”x 30”, ¼ inch thick, copper-plated plate glass, tapered tilt mirror, 18 gauge stainless steel frames.
8. Sanitary Napkin Disposal Unit: shall be Bobrick B-270 Contura Series Surface-Mounted Sanitary Napkin Disposal, satin finish stainless steel.
9. Paper Towel/Trash receptacle units: shall be Bobrick (B-43949) – Stainless Steel Paper Towel Dispenser and 15 gal Waste Receptacle or approved equal.
10. Partition Walls: shall be Stainless Steel satin finish partions that covers the restrooms distance, see drawing. The partions shall be a minimum of 1” thick, ¼” radius on all exposed edges, have a 3’ door, and meet ADA requirements.
11. Lavatory Sink: Wall hung lavatory with 4” anti-splash back, white china. Eljer, 18”x 20” wall hung lav, white vitreous china, 4” centers with 4” anti-splash back, Model 404701, or approved equal.
12. Lavatory faucet: Must conform to all ADA requirements. EZ-Flo, Model 10247, Classic Two handle bath faucet, chrome finish, or approved equal.
13. Service Sink Faucet: Two handle wash down faucet, chrome finish, compression function, 4 to 8-3/8” adjustable centers, bracket mount. Chicago Faucets, Model 415060, Mfg #897RCF, or approved equal. To be installed outside at new height complying with ADA, by drinking fountain and drain, see drawing.
14. Drinking Fountain: Bohlmann DFWM-19-FR-GRAY outdoor drinking fountain with freeze protection, or approved equal. To be installed outside at new height complying with ADA, see drawing.
PART 3 - EXECUTION
3.1 - Condition of Surfaces
All surfaces shall be dry, clean, free from all foreign matter, and ready for installation of toilet room accessories. Interior wall finish shall be completed and dry before installation may begin.
3.2 - Installation All items shall be installed with vandal-resistant fasteners and in conformance with the manufacturer's printed specifications. All installations shall comply with all ADA requirements for mounting, projection, and position in toilet rooms.
Mounting Install accessories such that mounting is rigid, straight and plumb, with all horizontal lines level. Anchor connections securely to appropriate walls.
Defect Repair Replace damaged items, Government will not be held accountable for damages found to be caused by improper installation. Make sure all surfaces are free from oil, grease, dirt, or other foreign matter.
PART 4 - MEASUREMENT AND PAYMENT
4.1 - Measurement
The work specified herein will not be measured for payment.
4.2 - Payment This work is incidental to other items in this contract and direct separate item payment will not be made.
END OF SPECIFICATION 10800
SECTION 15
GENERAL PIPING SYSTEMS - 15430
PART 1 - GENERAL
1.1 - Scope This section covers furnishing all labor, materials and equipment necessary to install new water lines, waste lines, and drain lines for the floor drain, sinks, lavatories, drinking fountain, and toilets. Water, waste, and drain lines to be replaced are going to be primarily focused on the piping near the fixtures. All piping that can be problematic due to cold weather shall be properly winterized.
PART 2 - PRODUCTS
2.1 – Piping
A. The Contractor shall replace any needed pipe lines to move new fixtures at required heights to meet ADA specifications. No-Hub cast iron pipe and fittings with stainless steel joint couplings and neoprene gaskets are acceptable above and below ground. Code approved plastic pipe and fittings will be acceptable if approved by local codes for the building construction.
PART 3 - EXECUTION
3.1 - Installation Provide and erect, in a workmanlike manner, according to the best practices of the trade, all piping required to complete installation of new fixtures, tieing into the exisiting lines. The piping may have to be offset, lowered or raised as required or as directed at the site. This does not relieve the Contractor from the responsibility for the proper erection of systems of piping in every respect suitable for the work intended as described in the specifications and approved by the COR. In the erection of all piping, it shall be properly supported and proper provisions shall be made for expansion, contraction and anchoring of piping. All piping shall be cut accurately for fabrication to measurements established at the construction site. Pipe shall be worked into place without springing and/or forcing, properly clearing all windows, doors, and other openings and equipment. Cutting or other weakening of the building structure to facilitate installation will not be permitted. All pipes shall have burrs, and/or cutting slag removed by reaming or other cleaning methods. All changes in direction shall be made with fittings. All open ends of pipes and equipment shall be properly capped or plugged to keep dirt and other foreign materials out of the system. Plugs of rag, wool, cotton waste or similar materials may not be used in plugging. All piping shall be arranged so as not to interfere. Surfaces to be painted shall be free of dirt, dust, scale, or any other substance which may interfere with the adhesion of the specified coating. All piping that can be problematic due to cold weather shall be properly winterized and the method shall be approved by the COR. Additional pipe work may be required, the COR will work with Contractor to see what additional pipe work is necessary. All work and installations shall follow national and local codes.
3.2 - Traps A. Each fixture and piece of equipment connecting to the drainage system shall be equipped with a trap. Each trap shall be placed as near to the fixture as possible and no fixture shall be double trapped.
B. Lavatory drain shall be provided with undersink protective pipe covers for ADA compliance. Undersink protective pipe covers shall be TRUEBRO, Lavguard, china white, or approved equal.
PART 4 - MEASUREMENT AND PAYMENT
4.1 - Measurement The work specified herein will not be measured for payment.
4.2 - Payment This work is incidental to other items in this contract and direct separate item payment will not be made.
END OF SPECIFICATION 15430
SECTION 16 - ELECTRICAL
GENERAL PROVISIONS - 16100
PART 1 - GENERAL
1.1 - Description This section specifies furnishing all labor, equipment, supplies and materials in performing all operations, including cutting, channeling, and chasing, necessary for the installation of a complete system for power, lighting and the exhaust fan.
1.2 - Submittals Submit sufficient descriptive literature to demonstrate like quality and function of products submitted as "equal" to products listed in the drawings or specifications. Substitutions which require alterations to the structural or aesthetic design of adjacent project elements will not be acceptable.
Contractor shall submit an electrical plan to the COR for approval prior to installation of any electrical circuits. Include wire sizes, types, and color codes. Show location of all electrical equipment, accessories, and conductors as circuits
1.3 - Quality Assurance
Codes and Standards All products shall be Underwriters Laboratory approved and shall be the standard catalogued product of a manufacturer regularly engaged in the manufacture of the product.
All work shall be done in accordance with the National Electrical Code and the National Electrical Safety Code except where local regulations are more stringent.
All work shall be done by electricians licensed by the State of New Mexico.
PART 2 - PRODUCTS
2.1 – Material Surface Mounted Fluorescent Ceiling Fixture: shall be Lithonia Lighting, Model 324951, 4’ Two Lights, T-8 32W, Fluorescent Ceiling Fixture-120 Volt Electronic Ballast-White Enameled Steel Base, Clear acrylic prismatic diffuser with injection molded luminous ends, or approved equal. Supply two 32W T-8 Fluorescent Lamps per fixture.
Exhaust Fan: shall be NuTone exhaust fan, 120 Volt, 110 CFM, 4.0 Sones, White Plastic Grill, or approved equal. To be installed on wall or ceiling close to the toilet. Supply flexible ducts leading outside to a ceiling or wall. Finish with a roof or wall cap, letting the air out. To be determined where exhaust fan and accessories will be easiest to install.
PART 3 - EXECUTION
3.1 - Installation
Installation of all electrical equipment as mentioned herein shall be done under the supervision of a licensed electrician and in accordance with the National Electrical Code, most current addition.
All work will comply with specifications and methods established by local jurisdictions and/or utility companies.
Contractor shall furnish and install two surface mounted fluorescent fixtures and exhaust fan inside the restroom. The exhaust fan shall be wired so that it will turn on when the light is turned on.
PART 4 - MEASUREMENT AND PAYMENT
4.1 - Measurement The work specified herein will not be measured for payment.
4.2 - Payment This work is incidental to other items in this contract and direct separate item payment will not be made.
END OF SPECIFICATON 16100
PRICE RANGE
Contract magnitude is:
Between $25,000 and $100,000.
AGAR 452.211-72 Statement of Work/Specifications (FEB 1988)
The Contractor shall furnish the necessary personnel, material, equipment, services and facilities (except as otherwise specified), to perform the Statement of Work/Specifications referenced in Section J.
AGAR 452.211-73 Attachments to Statement of Work/Specifications (FEB 1988)
The attachments to the Statement of Work/Specifications listed in Section J are hereby made part of this solicitation and any resultant contract.
SECTION D--PACKAGING AND MARKING
{For this Solicitation, there are NO clauses in this Section}
SECTION E--INSPECTION AND ACCEPTANCE
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-1 Contractor Inspection Requirements (APR 1984)
52.246-12 Inspection of Construction (AUG 1996)
SECTION F--DELIVERIES OR PERFORMANCE
FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.242-14 Suspension of Work (APR 1984)
FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984)
The Contractor shall be required to (a) commence work under this contract within _10_ calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than __90 days__ . The time stated for completion shall include final cleanup of the premises.
AGAR 452.236-75 Maximum Workweek – Construction Schedule (NOV 1996)
Within _ 10__ calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following information in…