AG-82X9-S-12-0103 Amend 3.pdf

PDF 96 KB Posted

Attached to
Vallecito Road Construction Federal contract opportunity
Solicitation number
AG-82X9-S-12-0103
Issued by
Department of Agriculture Forest Service R2-Rocky Mountain Region

About this file

Amendment 0003

View the file

Other files for this federal contract opportunity

Other files attached to Vallecito Road Construction, newest first.
File Type Posted
AG-82X9-S-12-0103 Amend 2.pdf PDF
Signin.pdf PDF
Amendment 0001.pdf PDF
AG-82X9-S-12-0103.pdf PDF
Attachment 4.pdf PDF
Attachment 6.pdf PDF
Attachment 1 - Specifications.pdf PDF
Attachment 2 - Plans.pdf PDF
Attachment 5.pdf PDF
Attachment 3.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

AG-82X9-S-12-0103

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

82X9

DURANGO CO 81301

15 BURNETT COURT

ROCKY MOUNTAIN REGION ATTN AQM

USDA FOREST SERVICE

08/17/20120003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

07/16/2012

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

TITLE: VALLECITO ROAD CONSTRUCTION, SAN JUAN NATIONAL FOREST, COLORADO

This amendment is hereby issued to provide for the following:

1. Section B, Page 4 of 38, of the solicitation is hereby amended and replaced in its entirety and is attached.

2. By pen and ink change, FP-03 Section 251, titled RipRap is hereby incorporated.

3. The proposal due date remains unchanged, August 28, 2012

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

Solicitation No. AG-82X9-S-12-0103 – Amendment 0003 Page 4 of 38 Vallecito Road Construction

SECTION B - Supplies or Services and Prices/Costs Schedule of Items

B.1 SCHEDULE OF ITEMS:

ITEM NO.

DESCRIPTION

UNIT OF ISSUE EST.

QTY.

UNIT

PRICE

TOTAL

AMOUNT

15101 Mobilization LS 1 $ $ 15212 Slope, reference, and clearing and grubbing stakes; method I, tolerance C

LS 1 $ $

15255(a) Grade finishing stakes, top of subgrade, tolerance D

LS 1 $ $

15255(b) Grade finishing stakes, base course, tolerance A

LS 1 $ $

15255(c) Grade finishing stakes, asphalt pavement, tolerance A

LS 1 $ $

15702 Silt fence FT 3,500 $ $ 20101 Clearing and grubbing ACRE 7 $ $ 20422 Topsoil (stockpiled) CY 3,300 $ $ 20455 Embankment construction CY 23,702 $ $ 20950 Pipe bedding material CY 20 $ $ 20951 Pipe backfill, method C CY 40 $ $ 20956 Pipe culvert excavation CY 60 $ $

30103(a) Aggregate base, grading B, compaction method C

CY 2,620 $ $

30103(b) Aggregate base, grading, CDOT Class 6, compaction method C

CY 2,413 $ $

40450 Minor hot asphalt concrete, Colorado State DOT, grading S

TON 2,221 $ $

60271 ADS 24” pipe culvert FT 363 $ $ 61901(a) Fence, chain-link, height 7'-0" FT 1,707 $ $ 61901(b) Fence, Barbed Wire, height 4'-0" FT 5,366 $ $ 61902(a) Gate, sliding chain-link, height 6'-0" EA 6 $ $ 61902(b) Gate, panel type, height 5'-0" FT 62 $ $

62406 Placing conserved topsoil ACRE 7 $ $ 62506 Seeding, hydraulic method ACRE 3.5 $ $ 62513 Mulching, hydraulic method ACRE 3.5 $ $ 63301 Sign system EA 4 $ $

63406(a) Pavement markings, type K (color yellow) LS 1 $ $ 63406(b) Pavement markings, type K (color white) LS 1 $ $

25101 Riprap,Class 1 CY 5 $ $

TOTAL $

NOTE: Payment will be made on actual work performed as described in Supplemental Specification to FP-03, 109.01, unless otherwise noted.

Payment for bond premiums shall be made in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contract, and shall not be in addition to the contract price. Include all costs for bond payments under Item 15101, Mobilization.

52.232-18 Availability of Funds. (APR 1984)

Funds are not presently available for this contract. The Government's obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer. (End of clause)