Attachment 8 Questions and Answers from Pre-Proposal Meeting

View the file

Other files

File Type Posted
Attachment 7 - Plot Survey.TIF TIF image
Attachment 6 - Legal Description.rtf RTF text file
Amendment 1.pdf PDF
AG82X9S120023.pdf PDF
Attachment 1 Worksheets.pdf PDF
Attachment 4 Model Report Outline.pdf PDF
Attachment 2 Building Photos.pdf PDF
Attachment 3 ESA Conveyance.pdf PDF
Attachment 5 Wage Determination 05-2081.txt TXT text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Dillon Site Assessment Attachment 8 Solicitation Number AG-82X9-S-12-0023

Notes from the Pre Proposal meeting held on Wednesday February 15, 2012.

Clarifications:

· Contracting Officer for this project will be Malinda Jiminez. The contract administrator will be John Acha.

· The planned schedule is to award in early March and a Notice to Proceed will be issued to start the count of contract time.

· Offerors shall submit the items identified in Section M.1 of the solicitation to the address identified in Block 8 of the SF33.

· Amendments to the solicitation process will be posted on the Federal Business Opportunities webpage, www.fbo.gov. The website location for the contract clauses referenced in the solicitation is www.acquistion.gov/far/. & www.usda/procurement/policy/agar.html . These web site addresses are also included in the Solicitation.

· The successful offeror must be registered in the Central Contractor Registration (CCR). The web sites to register in these systems are www.ccr.gov .

· Section J of the solicitation package includes the applicable Attachments, Specifications and Wage Rate Determinations.

· The contract for this project will result in a Firm-Fixed Price contract.

The following questions have been asked at either the pre-proposal meeting or submitted afterwards. Some of the answers were provided and the meeting. Other answers have been determined after the meeting by the Government. These questions have been paraphrased to be more concise and do not reflect the word-for-word questions received.

1. Question: Are there any known underground storage tanks (UST’s)?

Answer: Yes, all UST’s have been removed and the last tank was removed in 1987. Prior to 1987, the Forest Service did have a fuels station on this site. The tanks were removed and disposed of in accordance with all federal, state, EPA and local laws in effect at that time. The records of this disposal shall be made available to the awardee upon request.

2. Question: A half missing placard was observed and made reference to on the small shed adjacent to the fuels storage shed.

Answer: This was a plastic “Fuels” placard which had weathered and been blown away in the wind.

3. Question: Stains were observed and commented on the concrete slab within the fuels storage shed.

Answer: It was confirmed that the stains on the concrete slab in the fuels storage shed were petroleum based stains that may have been Kerosene.

4. Question: There are potential unknowns covered in snow on in the boneyard and other areas, does WRNF know what they are and if not, how will they be dealt with regarding the scope of work?

Answer: This area was used as a “boneyard” for miscellaneous items to be stored. In order to address any issues that may arise from this question or question 5, the clause covering differing site conditions has been added (FAR 52.236-2).

5. Question: A pile of rusted cans near the trash container was commented upon.

Answer: At one time, it was the White River National Forest policy to collect and catalog any cans and bottles that were found on the forest which were believed to be in excess of 50 years old. The rusted pile of cans near the trash containers are a result of this policy, and these cans can now be disposed of.

6. Question: The existence of what once were trailer parking pads was commented upon.

Answer: This location does have local water and sewer hook-ups, however, there are no septic tanks, leach field or underground propane tanks.

Site Visit Attendees

NameCompany Name
Jonathan HarrisHRL Compliance Inc.
Melissa ValentineBurean Ventas
Jason KahlertRMC Consultants
Brian WilliamsIHI Environmental
Lilly GriffinWalsh Environmental
Julie CurneltePinyon Environmental
Olivia GarciaWRNF
John AchaWRNF