AG-82B1-S-10-0375 FSSS.pdf
PDF 128 KB Posted
- Attached to
- Kootenai National Forest Trailhead Construction Federal contract opportunity
- Solicitation number
- AG-82B1-S-10-0375
About this file
AG-82B1-S-10-0375 FSSS
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| AG-82B1-S-10-0375 Body.pdf | ||
| AG-82B1-S-10-0375 Maps for Kootenai trailheads.pdf | ||
| AG-82B1-S-10-0375 SF 18.pdf | ||
| GENERAL DECISION MT20100001 06-04-2010 MT1.pdf | ||
| AG-82B1-S-10-0375 Other maps files for Kootenai trailheads.pdf | ||
| AG-82B1-S-10-0375 solicitation_coversheet.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Table of Contents
Table of Contents
Preface
Project Specifications
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources
106 - Acceptance of Work
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims
107.06 Contractor’s Responsibility for Work
107.09 Legal Relationship of the Parties
107.10 Environmental Protection
108 - Prosecution and Progress
108 Delete
109 - Measurement and Payment
109 Deletions
109.02 Measurement Terms and Definitions
151 – Mobilization
151.01 Description
151.02 Measurement
152 – Construction Survey and Staking
153 – Contractor Quality Control
153.07 Project Submittals
155 - Schedules for Construction Contracts
155 Delete
156 - Public Traffic
156.03 Accommodating Traffic During Work
156.08 Traffic and Safety Supervisor
201 – Clearing and Grubbing
201.10 Timber Harvest
203 - Removal of Structures and Obstructions
203.03 Salvaging Material
203.05 Disposing of Material
204 - Excavation and Embankment
204.11 Compaction
204.14 Disposal of Unsuitable or Excess Material
324 - Minor Aggregate Courses - Commercial Source
625 – Turf Establishment
625.03 General
625.04 Preparing Seedbed
625.05 Watering
625.07 Seeding
625.08 Mulching
625.09 Protecting and Caring for Seeded Areas
625.11 Measurement
637 – Facilities and Services
637.01 Vault Toilet
637.03 Picnic Tables
637.04 Fire Rings
Miscellaneous
Appendix A - Schedule of Items
Appendix B - Engineers Estimate
Preface
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of
National Forest System Roads.
101 - Terms, Format, and Definitions
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association
Mine Safety and Health Administration
National Institute of Standards and Technology
National Electrical Safety Code
West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition
Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or
“design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96
Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the
Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36
CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
Deletions
Delete Sections 104.01, 104.02, and 104.04.
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02 Material Sources
Add the following before the first paragraph.
Sources have been designated for this project as follows:
Crushed Aggregate Source- Contractor Furnished. There is no available Government source for Select Borrow for this project.
Waste Site – Government Furnished. The following waste sites are available for excess and unsuitable material:
• Krinklehorn: Joshua Quarry located in SE1/4 NE1/4, Section 7, T35N, R25W approximately 6 miles Southeast from site on road 7069
• Foundation: Frozen Lake/Weasel Cabin Pit located in SE1/4 SE1/4, Section 8, T37N, R24W, approximately 3.5 miles north on Road 319.
These sites are to be used for the disposal of unsuitable or excess excavated material only. All other materials designed for removable and disposal must be disposed of away from National Forest System Land and per FSSS Section 203.
Materials Stockpile Site- Contractor Furnished. There is no available Government
Materials Stockpile Site for this project.
Add the following to section (b) Contractor-located sources.
Prior to any pit development or use of materials, the Contractor shall provide to the CO a
State certification that the pit site is free of noxious weed as listed on the "All States
Noxious Weeds List”.
106 - Acceptance of Work
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
151 – Mobilization
151.01 Description
This work consists of washing and treating construction equipment and vehicles necessary for equipment transport to remove seeds, plants, and plant fragments before the equipment is used on National Forest System Lands.
Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment. Only equipment inspected by the Forest Service will be allowed to operate within the project area. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in. This requirement does not apply to cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas off the National Forest.
Equipment will be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment, components or the need for specialized inspection tools is not required.
Notify the CO in writing at least 24 hours before moving any construction equipment onto the national forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Forest Service. Inspection will be required after every cleaning.
Use methods of cleaning and locations for cleaning approved by the C.O.
For work at a commercial washing facility, use an approved facility.
New infestations of noxious weeds of concern to Forest Service and identified by either
Contractor or Forest Service, on the Project Area or on the haul route, will be promptly reported to the other party. Contractor and Forest Service will agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found. A current list of noxious weeds of concern to Forest Service is available at each Forest Service office.
151.02 Measurement
Clean equipment prior to moving onto this project. The initial cleaning will not be included in the measurement for payment. Payment under this item will only be made if subsequent cleanings are ordered by the CO. Measurement shall be on an “each” basis, meaning one complete cleaning of all equipment required for this contract. Subsequent cleanings necessitated by the Contractor’s actions but not directed by the CO will not be included in the measurement for payment.
152 – Construction Survey and Staking
152.01 (a) Personnel.
Add the following.
Conduct all construction staking under the direction of a licensed professional engineer or land surveyor who is closely associated and familiar with construction staking.
153 – Contractor Quality Control
Add the following.
153.07 Project Submittals
At a minimum the contractor shall provide project submittals as shown on the below Submittal
Log. Submittal requirements are listed in the Standard Specifications, Supplemental
Specifications, and Plans.
Submittal Log
Log
No.
Incidental to Pay
Item(s)
Description of Submittal Type of
Submittal
Requirement found in
Specification No.
/Drawings
Additional
Specification
References
1 15101 Weed Free Material Source
Certification
Material
Certification FSSS 105.02(b)
2 15101 Hazardous Spill Plan Plan FSSS 107.10
3 15101 Contractor Quality Control Plan Plan 153.02
4 15101 Traffic Control Plan Plan FSSS 156.03
5 32401 Aggregate Gradation Material
Certification FSSS 324.03 Drawings
6 63702 Structural Concrete: Mix Design Mix Design
Drawing S1-S3 Drawings
7 63702 Structural Concrete: Testing Test Results
Drawing S1-S3 Drawings
8 63701 Precast Concrete Structures Shop Drawing FSSS 637.01
9 63701 Precast Concrete Structures: PCI
Certification
Fabrication
FSSS 637.01
10 63701 Precast Concrete Structures: Testing Test Results FSSS 637.01
11 63702 Timber Structures Shop Drawing Drawing S1-S3 Drawings
12 63702 Timber Structures: Materials Material
Certification Drawing S1-S3 Drawings
13 62508 Fertilizer, Seed Mix, & Mulch Material
FSSS 625
155 - Schedules for Construction Contracts
155 Delete.
Delete Section 155 in its entirety.
156 - Public Traffic
156.03 Accommodating Traffic During Work.
Delete the first paragraph and replace with the following:
Accommodate traffic according to the requirements set forth below, MUTCD, and Section 635.
Submit a traffic control plan for acceptance at least 30 days before intended use.
Add the following project specific requirements:
The Contractor will be allowed to close each trailhead site for five (5) consecutive days, Monday through Friday. The trailhead sites must be opened on the weekends. Advanced warning signs shall be placed the nearest intersection to the trailhead should as approved by the CO. The
Contractor shall give the CO at least four weeks advanced written notice prior to any trailhead closure.
Delete the following from the last sentence of the last paragraph:
according to Subsection 106.07(b)
156.08 Traffic and Safety Supervisor.
Delete this subsection in its entirety.
201 – Clearing and Grubbing
Add the following section:
201.10 Timber Harvest
Timber
All merchantable sawlog trees will be limbed and lopped. A merchantable tree will be any tree that contains an 8’ log with a 5.6” small end. Trees will be decked tree length, or log length by agreement, at a site determined by the Forest Service.
All slash will be piled at a location determined by the Forest Service. Slash shall be accumulated into piles that are compact and relatively free of dirt and decomposed duff. Piles shall not be less than 6 feet in height and not more than 15 feet in width. When piles cannot meet the specifications outlined above, a Forest Officer may authorize the scattering of debris. No stumps shall be placed in piles.
Stumps will be scattered as directed by Forest Service unless needed for project.
Product Removal
If the contractor requests and Contract Officer agrees to allow removal of timber products from material that is required to be slashed or piled, the contractor will obtain the necessary permits from the district office. All product removal is subject to rates of payment and road maintenance deposits depending on the quantity and commercial value of the product being removed. If no charge for removal is determined, road deposits may still apply.
203 - Removal of Structures and Obstructions
203.03 Salvaging Material.
Add the following to the last paragraph:
As shown on the drawings or at a location approved by the CO.
203.05 Disposing of Material.
Modify this subsection as follows:
(a) Remove from project. Add the following:
All materials designated for removal become the property of the Contractor and are to be disposed of by removing off of National Forest System Lands in accordance with all local, state and federal requirements.
(b) Burn. Delete this section.
(c) Bury. Delete this section.
(e) Placing Slash on Embankment Slopes. Place construction slash on completed embankment slopes or scatter as directed by the CO to reduce soil erosion. Place construction slash as flat as practicable on the completed slope. Priority for use of available slash is for: (1) through fills; (2) insides of curves; and (3) ditch relief outlets. All slash material not suitable for embankment slopes shall be disposed off National Forest System Lands in accordance with all local, state and federal requirements or as approved by the CO.
204 - Excavation and Embankment
204.11 Compaction.
Delete section and add the following:
Layer Placement (Roller Compaction) Method. Place material by end dumping to the minimum depth needed for operation of spreading equipment. Adjust the moisture content of the material to obtain a mass that will not visibly deflect under the load of the hauling and spreading equipment. Operate compaction equipment over the full width of each layer until visible deformation of the layer ceases or, in when a sheepsfoot roller is used, the roller “walks out” of the layer. Make at least three complete passes.
204.14 Disposal of Unsuitable or Excess Material.
Delete the text of the first paragraph and substitute the following:
Dispose of unsuitable or excess material at designated sites approved by the CO.
324 - Minor Aggregate Courses - Commercial Source
Description
324.01 This work consists of constructing one or more courses of aggregate on a prepared surface. Work includes producing aggregate by crushing methods.
Material
324.02 Conform to the following Subsections:
Aggregate 703.06
Water 725.01
Construction Requirements
324.03 General. Prepare the surface on which the aggregate course is placed according to Section
204 or 303 as applicable.
Request approval of the roadbed in writing before placing aggregate.
Develop, haul, and apply water in accordance to Section 170.
Submit aggregate gradations for approval by the CO.
After processing on the road, remove all oversize material from the road and dispose of it as directed by the CO.
If the aggregate is produced and stockpiled before placement, handle and stockpiled according to
Section 320. Establish stockpile sites at approved locations.
324.04 Mixing and Spreading. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with moisture content suitable for the specified compaction method. Spread and shape the mixture on the prepared surface in a uniform layer with no segregation of size, and to a loose depth that will provide the required compacted thickness. Place the mixture in a maximum compacted layer thickness of 6 inches.
When more than one layer is necessary, compact each layer according to Subsection 324.05 before placing the next layer. Route hauling and leveling equipment uniformly over the full width.
When placing aggregate over geotextile, place aggregate in a single lift to the full depth specified.
324.05 Compacting. Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
Compaction A. Operating spreading and hauling equipment over the full width of the travelway.
Compaction B. Operate rollers and compact as specified in FSSS 204.11.
Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in FSSS 204.11.
Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.
Compaction E. Compact to a density of at least 96 percent of the maximum density, as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box
7669, Missoula, MT 59807).
Compaction F. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 180, method C or D.
Compaction G. Compact to a density of at least 100 percent of the maximum density as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box
7669, Missoula, MT 59807).
For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
324.06 Construction Tolerance. If grade finishing stakes are required, finish the surface to within ±0.10 feet from staked line and grade elevation.
If grade finishing stakes are not required, shape the surface to the required template and check the surface with a 10-foot straightedge. Defective areas are surface deviations in excess of 1/2 inch in
10 feet between any two contacts of the straightedge with the surface.
Correct all defective areas by loosening the material, adding or removing material, reshaping, and compacting.
Ensure that the compacted thickness is not consistently above or below the specified thickness.
The maximum variation from the compacted specified thickness is ½ inch.
Ensure that the compacted width is not consistently above the specified width. The maximum variation from the specified width will not exceed +12 inches at any point.
324.07 Maintenance. Maintain the aggregate course to the correct line, grade, and cross-section by blading, watering, rolling, or any combination thereof until placement of the next course.
Correct all defects according to Subsection 324.06.
324.08 Acceptance. See Table 324-1 for sampling and testing requirements.
Aggregate gradation and surface course plasticity index will be evaluated under Subsection 106.03 and 106.04. Other aggregate quality properties will be evaluated under Subsections 106.02 and
106.03. Placement of aggregate courses will be evaluated under Subsections 106.02 and 106.04.
Preparation of the surface on which the aggregate course is placed will be evaluated under Section
204 or 303 as applicable.
Measurement
324.09 Measure the Section 324 items listed in the bid schedule according to Subsection 109.02 and the following as applicable.
Measure square yard width horizontally to include the top of aggregate width including designed widening. Measure the square yard length horizontally along the centerline of the roadway.
If the measurement for aggregate is by cubic yard using contract quantities then measure aggregate by the cubic yard in-place once compacted, otherwise measurement for aggregate by the cubic yard is measured by the cubic yard in the hauling vehicle.
Measure thickness perpendicular to the grade of the travelway.
Measure width perpendicular to the centerline.
Payment
324.10 The accepted quantities will be paid at the contract price per unit of measurement for the
Section 324 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
T a b le
-1
S m p li n g a n d
T es ti n g R eq u ir em en ts
R ep o rt in g im e
B ef o re u si n w o rk h o u rs p li t
S a m le
Y es w h re q u es te d
P in t o f
S a m p li u rc e o f m at er ia l
F ro m w in d ro w o r ro ad b ed a ft er ro ce ss in g o r fr o m a p p ro v ed cr sh er s am p li ev ic e
S a m p li
F q u cy er t y p e so rc e o f m at er ia l p er ay t M et h o d s
S p ec if ic a ti o n s
A A
S H
T O
T
A
S H
T O
T
S H
T O
T
T M
D
S H
T O
C te g ry a ra ct er is ti c
L A a b ra si
(c ar se
S o d iu m s u lf at e so u n d n es s lo ss ar se f e)
D ra b il it y i n ex ar se f e) ra ct u fa ce s
S am y p e o f
A cc ep ta
(S b se ct io n
M ea su re d a st fo r co n fo rm an
(1
.0
M ea su re d a co n fo rm
.0
M te ri a l o r
P ro d ct g re g at e so u rc e q u al it
.0 b b as e, B as e, a n d S u rf ac e co u rs b le
-1 co n ti n u ed
S a m p li n g a n d
T es ti n g R eq u ir em ts
R ep o rt im e
B ef o re u si n g i w rk
B ef o re p la ci ex t la li t
S a m w q u es
P in t o f
S a m p li u rc e o f m at e ri al
In -p la m p li q u cy er t y p e so rc e o f m at er ia l ay t M et h o d s
S p ec if ic a ti o n s
A A
S H
T O
T
(1
R -1
M ar sh al l
A A
S H
T O
(1
R -1
M ar sh al l
A A
S H
T O
T o th er a p p ro v ro ce d u re s
C a te g ry a ra ct er is ti c
M o is tu re -d en si ty et h o
D is tu re -d en h o
E is tu re -d en h o is tu re -d en h o
G
In -p la ce d en m o is tu co te n t
T y p e o f
A cc ep ta
(S b se ct io n
M ea su re d a co n fo rm
.0
M a te ri a l o r
P ro d ct b b as e, B as e, a n d S u rf ac e
625 – Turf Establishment
625.03 General.
Delete the first sentence and add the following:
Apply turf establishment to portions of slopes, ditches, waste areas, and other disturbed areas within 14 days after being constructed to template lines unless otherwise specified in writing by the C.O..
625.04 Preparing Seedbed.
Delete the second sentence of the first paragraph.
Delete the third paragraph.
625.05 Watering
Delete the entire paragraph.
625.07 Seeding.
Delete the first sentence and add the following.
Apply seed mix shown in (c) below by the following methods.
(a) Dry method.
Delete the third sentence.
Add the following after subsection (b).
(c) Seed Mix. Government Furnished
625.08 Mulching.
No mulching required.
625.09 Protecting and Caring for Seeded Areas.
Delete the first sentence and add the following.
Protect and care for seeded areas until final acceptance.
625.11 Measurement
Delete the second paragraph and add the following.
Measure seeding, fertilizing, and mulching by the acre on the ground surface or by lump sum.
637 – Facilities and Services
Delete Section 637 in its entirety and add the following.
637.01 Vault Toilet
Plant-Precast Structural Concrete
PART 1 - GENERAL
1.01 WORK INCLUDED
A. This Section includes plant-precast structural concrete units, including the following:
1. Structural roof, wall and slabs for precast concrete structures including the
Aspen-style vault toilet buildings.
1.02 REFERENCES: (Latest Editions)
A. The Contractor shall comply with all requirements of the following codes and standards except as modified herein:
1. ACI 301 “Recommended Practice for Concrete Inspection.”
2. ACI 318 “Building Code Requirements for Reinforced Concrete.”
3. ACI 305R “Hot Weather Concreting.”
4. ACI 306.1 “Specification for Cold Weather Concreting.”
5. ACI 211.1 “Practices for Selecting Proportions for Normal, Heavyweight, and Mass Concrete.”
6. AWS D1.1-98: Structural Welding Code – Steel
7. AWS D1.4: Structural Welding Code – Reinforcing Steel
8. Concrete Reinforcing Steel Institute (CRSI) Manual of Standard Practice
9. PCI MNL 116: Manual for Quality Control for Plants and Production of
Precast and Prestressed Concrete Products
10. PCI MNL 120: PCI Design Handbook – Precast and Prestressed Concrete
11. PCI MNL 127: Recommended Practice for Erection of Precast Concrete
1.03 PERFORMANCE REQUIREMENTS
A. Structural Performance:
1. Size components to withstand design loads indicated in the drawings in a restrained condition.
2. Maximum Allowable Total Deflection: 1/480 span.
3. Design members exposed to the weather to provide for movement of components without damage, failure of joint seals, undue stress on fasteners or other detrimental effects, when subject to seasonal or cyclic day/night temperature ranges.
4. Design system to accommodate construction tolerances, deflection of other building structural members and clearances of intended openings.
5. Calculate structural properties of framing members in accordance with ACI
318.
1.04 SUBMITTALS
A. Product Data: For each type of product indicated.
B. Design Mixes: For each concrete mix.
C. Shop Drawings: Detail fabrication and installation of precast structural concrete units. Indicate member locations, plans, elevations, dimensions, shapes, cross sections, openings, and types of reinforcement, including special reinforcement.
1. Indicate welded connections by AWS standard symbols. Detail loose and cast-in hardware, inserts, connections, and joints, including accessories.
2. Indicate locations and details of anchorage devices to be embedded in other construction.
3. Comprehensive engineering analysis signed and sealed by the qualified professional engineer responsible for its preparation.
1.05 QUALITY ASSURANCE
A. Supplier Qualifications: An experienced supplier who has completed precast structural concrete work similar in material, design, and extent to that indicated for this Project and whose work has resulted in construction with a record of successful in-service performance.
B. Fabricator Qualifications: A firm that complies with the following requirements and is experienced in manufacturing precast structural concrete units similar to those indicated for this Project and with a record of successful in-service performance.
1. Assumes responsibility for engineering precast structural concrete units to comply with performance requirements. This responsibility includes preparation of Shop Drawings and comprehensive engineering analysis by a qualified professional engineer.
2. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of precast structural concrete that are similar to those indicated for this Project in material, design, and extent.
3. Participates in PCI's Plant Certification program and is designated a PCI-certified plant for Group C, Category C1.
4. Has sufficient production capacity to produce required units without delaying the Work.
C. Design Standards: Comply with ACI 318 and the design recommendations of PCI
MNL 120, "PCI Design Handbook--Precast and Prestressed Concrete."
D. Quality-Control Standard: For manufacturing procedures and testing requirements, quality-control recommendations, and camber and dimensional tolerances for types of units required, comply with PCI MNL 116, "Manual for
Quality Control for Plants and Production of Precast and Prestressed Concrete
Products."
E. Product Options: Drawings indicate size, profiles, and dimensional requirements of precast concrete units and are based on the specific types of units indicated.
Other fabricators' precast concrete units complying with requirements may be considered.
F. Welding: Qualify procedures and personnel according to AWS D1.1, "Structural
Welding Code--Steel"; and AWS D1.4, "Structural Welding Code--Reinforcing
Steel."
1.06 DELIVERY, STORAGE, AND HANDLING
A. Deliver precast structural concrete units to Project site in such quantities and at such times to ensure continuity of installation. Store units at Project site to prevent cracking, distorting, warping, staining, or other physical damage, and so markings are visible.
B. Lift and support units only at designated lifting and supporting points as shown on
Shop Drawings.
1.07 SEQUENCING
A. Furnish anchorage items to be embedded in other construction without delaying the Work. Provide setting diagrams, templates, instructions, and directions, as required, for installation.
PART 2 - PRODUCTS
2.01 FABRICATORS
A. Precast Structure Fabricators: Subject to compliance with requirements, provide products by one of the following:
1. Missoula Concrete Construction
2. Other accepted alternate.
2.02 MOLD MATERIALS
A. Molds: Provide molds and, where required, form-facing materials of metal, plastic, wood, or another material that is nonreactive with concrete and dimensionally stable to produce continuous and true precast concrete surfaces within fabrication tolerances and suitable for required finishes.
2.03 REINFORCING MATERIALS
A. Reinforcing Bars: ASTM A 615/A 615M, Grade 60, deformed.
B. Low-Alloy-Steel Reinforcing Bars: ASTM A 706/A 706M, deformed.
C. Steel Bar Mats: ASTM A 184/A 184M, assembled with clips, as follows:
1. Steel Reinforcement: ASTM A 615/A 615M, Grade 60, deformed bars.
D. Plain-Steel Wire: ASTM A 82, galvanized.
E. Deformed-Steel Wire: ASTM A 496.
F. Plain-Steel Welded Wire Fabric: ASTM A 185, fabricated from galvanized steel wire into flat sheets.
G. Deformed-Steel Welded Wire Fabric: ASTM A 497, flat sheet.
H. Supports: Manufacturer's bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars and welded wire fabric in place according to CRSI's "Manual of Standard Practice," PCI MNL 116, and as follows:
1. For uncoated reinforcement, use all-plastic bar supports.
2.04 CONCRETE MATERIALS
A. Portland Cement: ASTM C 150, Type I or Type III, of same type, brand, and source.
B. Normal-Weight Aggregates: Requirements of PCI MNL 116.
C. Water: Potable; free from deleterious material that may affect color stability, setting, or strength of concrete and complying with chemical limits of
PCI MNL 116.
D. Air-Entraining Admixture: ASTM C 260, certified by manufacturer to be compatible with other required admixtures.
E. Water-Reducing Admixture: ASTM C 494, Type A.
F. Retarding Admixture: ASTM C 494, Type B.
G. Water-Reducing and Retarding Admixture: ASTM C 494, Type D.
H. High-Range, Water-Reducing Admixture: ASTM C 494, Type F.
I. High-Range, Water-Reducing and Retarding Admixture: ASTM C 494, Type G.
J. Plasticizing Admixture: ASTM C 1017.
2.05 STEEL CONNECTION MATERIALS
A. Carbon-Steel Shapes and Plates: ASTM A 36/A 36M.
B. Carbon-Steel Headed Studs: ASTM A 108, AISI 1018 through AISI 1020, cold finished; AWS D1.1, Type A or B, with arc shields.
C. Malleable Steel Castings: ASTM A 47.
D. Deformed-Steel Wire or Bar Anchors: ASTM A 496 or ASTM A 706/A 706M.
E. Carbon-Steel Bolts and Studs: ASTM A 307, Grade A; carbon-steel, hex-head bolts and studs; carbon-steel nuts; and flat, unhardened steel washers.
F. High-Strength Bolts and Nuts: ASTM A 325, Type 1, heavy hex steel structural bolts, heavy hex carbon-steel nuts, and hardened carbon-steel washers.
G. Finish: For exterior steel items, and items indicated for galvanizing, apply zinc coating by hot-dip process according to ASTM A 123/A 123M, after fabrication, and ASTM A 153/A 153M, as applicable.
1. Galvanizing Repair Paint: High-zinc-dust-content paint with dry film containing not less than 94 percent zinc dust by weight, and complying with DOD-P-21035A or SSPC-Paint 20.
H. Shop-Primed Finish: Prepare surfaces of nongalvanized steel items, except those surfaces to be embedded in concrete, according to requirements in SSPC-SP 3 and shop-apply lead- and chromate-free, rust-inhibitive primer, complying with performance requirements in FS TT-P-664 according to SSPC-PA 1.
I. Welding Electrodes: Comply with AWS standards.
J. Accessories: Provide clips, hangers, plastic shims, and other accessories required to install precast structural concrete units.
2.06 GROUT MATERIALS
A. Sand-Cement Grout: Portland cement, ASTM C 150, Type I, and clean, natural sand, ASTM C 144. Mix at ratio of 1 part cement to 2-1/2 parts sand, by volume, with minimum water required for placement and hydration.
B. Nonmetallic, Nonshrink Grout: Premixed, nonmetallic, noncorrosive, nonstaining grout containing selected silica sands, portland cement, shrinkage-compensating agents, plasticizing and water-reducing agents, complying with ASTM C 1107, of consistency suitable for application.
C. Epoxy Grout: ASTM C 881, 2-component epoxy resin, of type, grade, and class to suit requirements.
2.07 CONCRETE MIXES FOR STRUCTURES
A. Prepare design mixes for each type of concrete required.
B. Design mixes may be prepared by a qualified independent testing agency or by qualified precast plant personnel at precast structural concrete fabricator's option.
C. Limit water-soluble chloride ions to the maximum percentage by weight of cement permitted by ACI 318.
D. Normal-Weight Concrete: Proportion mixes by either laboratory trial batch or field test data methods according to ACI 211.1, with materials to be used on
Project, to provide normal-weight concrete with the following properties:
1. Compressive Strength (28 Days): 4000 psi.
2. Maximum Water-Cementitious Materials Ratio: 0.40.
3. Add air-entraining admixture at manufacturer's prescribed rate to result in normal-weight concrete at point of placement having an air content as follows, with a tolerance of plus or minus 1-1/2 percent:
a. Air Content: 6 percent for 1-inch- nominal maximum aggregate size.
b. Air Content: 6 percent for ¾-inch- nominal maximum aggregate size.
c. Air Content: 7 percent for ½-inch- nominal maximum aggregate size.
E. Other Admixtures: Use water-reducing, high-range water-reducing, water-reducing and accelerating, or water-reducing and retarding admixtures according to manufacturer's written instructions.
F. Concrete Mix Adjustments: Concrete mix design adjustments may be proposed if characteristics of materials, Project conditions, weather, test results, or other circumstances warrant.
2.08 FABRICATION
A. Formwork: Accurately construct forms, mortar tight, of sufficient strength to withstand pressures due to concrete-placement operations and temperature changes and for pretensioning and detensioning operations. Maintain formwork to provide completed precast concrete units of shapes, lines, and dimensions indicated, within fabrication tolerances.
1. Coat surfaces of forms with bond-breaking compound before reinforcement is placed. Provide commercial-formula, form-coating compounds that will not bond with, stain, or adversely affect concrete surfaces and that will not impair subsequent treatments of concrete surfaces requiring bond or adhesion. Apply in compliance with manufacturer's written instructions.
2. Unless forms for precast, prestressed concrete units are stripped before detensioning, design forms so stresses are not induced in precast concrete units because of deformation or movement of concrete during detensioning.
B. Built-in Anchorages: Accurately position built-in anchorage devices and secure to formwork. Locate anchorages where they do not affect position of main reinforcement or concrete placement. Do not relocate bearing plates in units unless accepted by Engineer.
C. Cast-in openings larger than 10 inches in diameter or 10 inches square according to Shop Drawings. Smaller holes may be field cut by trades requiring them, as accepted by Engineer.
D. Reinforcement: Comply with recommendations in CRSI's "Manual of Standard
Practice" for fabricating, placing, and supporting reinforcement.
1. Clean reinforcement of loose rust and mill scale, earth, and other materials that reduce or destroy the bond with concrete.
2. Accurately position, support, and secure reinforcement against displacement by formwork, construction, or concrete-placement operations. Locate and support reinforcement by metal chairs, runners, bolsters, spacers, and hangers, as required.
3. Place reinforcement to obtain at least the minimum coverage for concrete protection. Arrange, space, and securely tie bars and bar supports to hold reinforcement in position while placing concrete. Set wire ties so ends are directed into concrete, not toward exposed concrete surfaces.
4. Install welded wire fabric in lengths as long as practicable. Lap adjoining pieces at least one full mesh and lace splices with wire. Offset laps of adjoining widths to prevent continuous laps in either direction.
E. Mix concrete according to PCI MNL 116 and requirements in this Section. After concrete batching, no additional water may be added.
F. Place concrete in a continuous operation to prevent seams or planes of weakness from forming in precast concrete units. Comply with requirements in
PCI MNL 116 for measuring, mixing, transporting, and placing concrete.
G. Thoroughly consolidate placed concrete by internal and external vibration without dislocating or damaging reinforcement and built-in items. Use equipment and procedures complying with PCI MNL 116.
H. Comply with ACI 306.1 procedures for cold-weather concrete placement.
I. Comply with ACI 305R recommendations for hot-weather concrete placement.
J. Identify pickup points of precast concrete units and orientation in structure with permanent markings, complying with markings indicated on Shop Drawings.
Imprint casting date on each precast concrete unit on a surface that will not show in finished structure.
K. Cure concrete, according to requirements in PCI MNL 116, by moisture retention without heat or by accelerated heat curing using low-pressure live steam or radiant heat and moisture.
L. Product Tolerances: Fabricate precast structural concrete units straight and true to size and shape with exposed edges and corners precise and true so each finished unit complies with PCI MNL 116 product tolerances.
M. Finish formed surfaces of precast structural concrete as indicated for each type of unit, and as follows:
1. Grade B Finish: Fill air pockets and holes larger than ¼ inch in diameter with sand-cement paste matching color of adjacent surfaces. Grind smooth form offsets or fins larger than 1/8 inch.
N. Screed finish unformed surfaces. Strike off and consolidate concrete with vibrating screeds to a uniform finish. Hand screed at projections.
O. Smooth steel trowel finish unformed surfaces. Consolidate concrete, bring to proper level with straightedge, float, and trowel to a smooth, uniform finish.
2.09 STRUCTURAL FRAMING UNITS
A. Type: Precast, conventionally reinforced structural concrete framing units.
B. Furnish units free of voids and honeycombs.
C. Provide Grade B finish to precast concrete units.
D. Reinforce units to resist transportation and erection stresses.
E. Include cast-in weld plates where required.
F. Coordinate with other trades for installation of cast-in items.
PART 3 - EXECUTION
3.01 EXAMINATION
A. Examine substrates and conditions for compliance with requirements for installation tolerances, true and level bearing surfaces, and other conditions affecting performance. Proceed with installation only after unsatisfactory conditions have been corrected.
3.02 INSTALLATION
A. Install precast structural concrete. Shore and brace precast concrete units to maintain location, stability, and alignment until permanent connections are installed.
B. Welding: Perform welding in compliance with AWS D1.1 and AWS D1.4, with qualified welders. All welding shall be performed at the fabrication site, as precast structures shall be shipped as a single unit.
1. Protect precast concrete units and bearing pads from damage by field welding or cutting operations and provide noncombustible shields as required.
2. Repair damaged metal surfaces by cleaning and applying a coat of galvanized repair paint to galvanized surfaces.
3. Repair damaged metal surfaces by cleaning and repriming damaged painted surfaces.
C. Fasteners: Do not use drilled or powder-actuated fasteners for attaching accessory items to precast, prestressed concrete units unless approved by Architect.
D. Erection Tolerances: Install precast concrete units level, plumb, square, and true, without exceeding the recommended erection tolerances in PCI MNL 127, "Recommended Practice for Erection of Precast Concrete."
E. Grouting Connections and Joints: After precast concrete units have been placed and secured, grout open spaces at keyways, connections, and joints as follows:
1. Provide forms or other approved method to retain grout in place until hard enough to support itself. Pack spaces with stiff grout material, tamping until voids are completely filled. Place grout to finish smooth, level, and plumb with adjacent concrete surfaces. Keep grouted joints damp for not less than 24 hours after initial set. Promptly remove grout material from exposed surfaces before it hardens.
3.03 CLEANING
A. Clean exposed surfaces of precast concrete units after erection to remove weld marks, other markings, dirt, and stains.
1. Wash and rinse according to precast concrete fabricator's written recommendations. Protect other work from staining or damage due to cleaning operations.
2. Do not use cleaning materials or processes that could change the appearance of exposed concrete finishes.
637.03 Picnic Tables
1. Size:
Picnic table tops shall be 92 inches long by a minimum 33 inches wide. Table top surface shall be 2 feet 8 inches off of finish grade. Picnic table benches shall be 92 inches long by 11 inches wide and be 18 inches off of finish grade as measured from top surface. Bench and table planks shall be Glu-lam timbers. Concrete base shall be a minimum 4 inches thick.
2. Style
Picnic table top and bench top shall be Glu-lam timbers and attached as shown on the drawings.
Bottom of legs to extend entire width of the table to supply a large footprint, so that no base slab is required, allowing product to be placed directly on grass, sand or other surfaces if desired.
Picnic table top shall be 6 inches from inside edge of seat to permit standing once inside. Bench and table supports shall not exceed 10 inches to allow easy access to the seating area. Picnic table to have wheelchair clearance at both ends.
3. Material Specifications
Table base to be made with Portland Cement. Mix shall be minimum 8.5 sacks per yard.
Aggregates to be free of injurious amounts of organic impurities. Maximum rock size to be ¾” in aggregate mix. Units to be reinforced with sizes #4 and #5 rebar grid, fabricated so that all connection points are welded. Rebar frame set a minimum of 2 inches from outside edges.
Cured concrete shall attain minimum compressive strength of 7000 PSI at 28 days.
5. Finish
All formed surfaces and edges shall be fully rounded and smooth finished. Furnish of all exposed surfaces to have a concrete graffiti-resistant sealer applied.
637.04 Fire Rings
As shown on drawings.
File details come from the government source that posted it. Updated .