NOTICE TO ALL OFFEROR(S) The enclosed revised/amended SECTION F is the replacement for the Solicitation AG-82B1-S-10-0374. ALL TERMS AND CONDITIONS REMAINS UNCHANGED.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION F - Deliveries or Performance
52.211-10 Commencement, Prosecution, and Completion of Work. (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 15 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 31 August 2011. The time stated for completion shall include final cleanup of the premises.
(End of Clause)
52.242-14 Suspension of Work. (APR 1984)
452.236-75 Maximum Workweek - Construction Schedule. (NOV 1996)
Within 15 calendar days after receipt of a written request from the Contracting Officer, the Contractor must submit the following in writing for approval:
(a) A schedule as required by FAR clause 52.236-15, Schedules for Construction Contracts, and
(b) The hours (including the daily starting and stopping times) and days of the week the Contractor proposes to carry out the work.
The maximum workweek that will be approved is Monday thru Saturday.
(End of Clause)