FSS DOCUMENT

View the file

Other files

File Type Posted
0365.pdf PDF
SF 30.pdf PDF
Additional ARRA Clauses.doc DOC document
ARRA Clauses.doc DOC document
ID15_04162010 Wage Determination.pdf PDF
Kelly Creek Bridge 100 .pdf PDF
Lake Creek Bridge 100 .pdf PDF
AG-82B1-S-10-0365.pdf PDF
SF 1442 AG-82B1-S-10-0365.pdf PDF
Kelly Forks Bridge 100 .pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UPPER NORTH FORK BRIDGE MAINTENANCE

Clearwater National Forest Idaho

FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS

Table of Contents

Table of Contents1
Preface3
101 - Terms, Format, and Definitions4
101.01 Meaning of Terms4
101.03 Abbreviations.4
101.04 Definitions.4
102 - Bid, Award, and Execution of Contract7
102 Bid, Award, and Execution of Contract7
104 - Control of Work8
Deletions8
104.06 Use of Roads by Contractor8
105 - Control of Material9
105.02 Material Sources9
106 - Acceptance of Work10
106.07 Delete10
107 - Legal Relations and Responsibility to the Public11
107.05 Responsibility for Damage Claims.11
107.06 Contractor’s Responsibility for Work.11
107.09 Legal Relationship of the Parties.11
108 - Prosecution and Progress12
108 Delete.12
109 - Measurement and Payment13
109 Deletions13
109.02 Measurement Terms and Definitions.13
153 – Contractor Quality Control (Kelly Forks Bridge)14
153.07. Project Submittals14
153 – Contractor Quality Control (Kelly Creek Bridge)15
153.07. Project Submittals15
153 – Contractor Quality Control (Lake Creek Bridge)16
153.07. Project Submittals16
155 - Schedules for Construction Contracts17
155 Delete.17
203 - Removal of Structures and Obstructions18
203.03 Salvaging Material.18
203.05 Disposing of Material.18
251 - Riprap19
251.01 Description19
251.07 Acceptance19
308 - Minor Crushed Aggregate20
404 - Minor Hot Asphalt Concrete22
404.02 Composition of Mix (Job-Mix Formula).22
404.07 Compacting (a).22
404.09 Acceptance.22
622 - Rental Equipment23
622.02 Rental Equipment23

Preface Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.

101 - Terms, Format, and Definitions

101.01 Meaning of Terms

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau

Add the following to (b) SI symbols:

mp
Milepost
ppm
Part Per Million

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.

Culvert--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following:

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.

Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

102 - Bid, Award, and Execution of Contract 102 Bid, Award, and Execution of Contract

Delete Section 102 in its entirety.

104 - Control of Work Deletions

Delete Sections 104.01, 104.02, and 104.04.

Add the following subsection:

104.06 Use of Roads by Contractor

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 - Control of Material

105.02 Material Sources

Add the following before the first paragraph.

Sources have been designated for this project as follows:

Kelly Forks Bridge (255 – 0.0)

· Riprap Source – Government Furnished, from Garner Point Quarry, located in Section 13, Township 39 North, Range 9 East.

Lake Creek Bridge (250 – 67.0)

· Aggregate Base – Government Furnished, from Kelly Forks stockpile, located near milepost 46.3 on Primary Forest Route 250, in Section 13, Township 39 N, Range 9 E.

· Gabion Rock – Commercial Source – There is no available Government source for gabion rock for this project.

· Riprap – Reuse existing riprap from site.

Add the following to section (b) Contractor-located sources.

Prior to any pit development or use of materials, the Contractor shall provide to the CO a State certification that the pit site is free of noxious weed as listed on the "All States Noxious Weeds List”.

106 - Acceptance of Work

106.07 Delete

Delete subsection 106.07.

107 - Legal Relations and Responsibility to the Public

107.05 Responsibility for Damage Claims.

Delete the entire subsection.

107.06 Contractor’s Responsibility for Work.

Delete the following from the first paragraph.

“except as provided in Subsection 106.07”.

107.09 Legal Relationship of the Parties.

Delete the entire subsection.

108 - Prosecution and Progress 108 Delete.

Delete Section 108 in its entirety.

109 - Measurement and Payment 109 Deletions Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Add the following:

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

Change the following:

“(b) Cubic yard” to “(c) Cubic yard”.

Add the following definition:

(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

153 – Contractor Quality Control Kelly Forks Bridge (255 – 0.0)

Add the following.

153.07. Project Submittals

At a minimum the contractor shall provide project submittals as shown on the below Submittal Log. Submittal requirements are listed in the Standard Specifications, Supplemental Specifications, and Plans.

Submittal Log

Log No.
Incidental to

Pay Item(s)

Description of Submittal
Type of Submittal
Requirement found in Specification No.

/Drawings Additional Specification References

1
151
Hazardous Spill Plan
Plan
Section H,

FSSS 107.10

2
151
Contractor Quality Control Plan
Plan
153.02
552.09
3
151
Traffic Control Plan
Plan
Section H(e), FP03

Section 635

MUTCD

4
151
Construction Schedule
Plan
FAR 52.236-15
5
251
Stream Flow Diversion Plan
Plan
Drawings
6
251
Riprap Installation Plan
Plan
Drawings
7
622
Equipment Rental
Equipment

Approval

FSSS 622.02

Kelly Creek Bridge (581 – 0.0)

Add the following.

153.07. Project Submittals

At a minimum the contractor shall provide project submittals as shown on the below Submittal Log. Submittal requirements are listed in the Standard Specifications, Supplemental Specifications, and Plans.

Submittal Log

Log No.
Incidental to

Pay Item(s)

Description of Submittal
Type of Submittal
Requirement found in Specification No.

/Drawings Additional Specification References

1
151
Hazardous Spill Plan
Plan
Section H,
2
151
Contractor Quality Control Plan
Plan
153.02
552.09
3
151
Traffic Control Plan
Plan
Section H(e), FP03

Section 635

MUTCD

4
151
Construction Schedule
Plan
FAR 52.236-15
5
552
Pier Cap & Grout Fillet Demo & Repair Plan
Plan
Drawings
6
557
Timber Structures: Materials
Material

Certification

557.19
106, 716, Drawings

Lake Creek Bridge (250 – 67.0)

Add the following.

153.07. Project Submittals

At a minimum the contractor shall provide project submittals as shown on the below Submittal Log. Submittal requirements are listed in the Standard Specifications, Supplemental Specifications, and Plans.

Submittal Log

Log No.
Incidental to

Pay Item(s)

Description of Submittal
Type of Submittal
Requirement found in Specification No.

/Drawings Additional Specification References

1
151
Hazardous Spill Plan
Plan
Section H
2
151
Contractor Quality Control Plan
Plan
153.02
552.09
3
151
Traffic Control Plan
Plan
Section H(e), Drawings, FP03 Section 635
MUTCD
4
151
Construction Schedule
Plan
FAR 52.236-15
5
203
Curb & Rail Demo Plan
Plan
Drawings
6
208
Structural Backfill Compaction Testing
Test Results
208.11, 208.12
106
7
251
Stream Flow Diversion Plan
Plan
Drawings
8
404
Asphalt
Mix Design
404.02
106
9
404
Asphalt Testing
Test Results
404.09
106
10
556
Bridge Rail
Shop Drawings
Drawings
11
556
Approach Guardrail
Shop Drawings
Drawings
12
622
Equipment Rental
Equipment

Approval

FSSS 622.02

155 - Schedules for Construction Contracts 155 Delete.

Delete Section 155 in its entirety.

203 - Removal of Structures and Obstructions

203.03 Salvaging Material.

Add the following to the last paragraph:

As shown on the drawings or at a location approved by the CO.

203.05 Disposing of Material.

Modify this subsection as follows:

(a) Remove from project. Add the following:

All materials designated for removal become the property of the Contractor and are to be disposed of by removing off of Forest Service Lands in accordance with all local, state and federal requirements.

(b) Burn. Delete this section.

(c) Bury. Delete this section.

Add the following:

(e) Placing Slash on Embankment Slopes. Place construction slash on completed embankment slopes or scatter as directed by the CO to reduce soil erosion. Place construction slash as flat as practicable on the completed slope. Priority for use of available slash is for: (1) through fills; (2) insides of curves; and (3) ditch relief outlets. All slash material not suitable for embankment slopes shall be disposed off Forest Service Lands in accordance with all local, state and federal requirements or as approved by the CO.

251 - Riprap

251.01 Description

Delete the first sentence and add the following:

This work consists of hauling and placing of riprap for bank protection, slope protection, drainage structures, erosion control, and other features shown on the plans.

Add the following:

251.07 Acceptance

Delete sampling and testing requirements of Table 251-1. (Use only if government furnished material. Otherwise delete this sentence.)

Delete the fourth sentence and add the following:

Structure excavation and backfill will be evaluated under section 208.

Delete Table 251-1. (Use only if government furnished material Otherwise delete this sentence.)

308 - Minor Crushed Aggregate Delete section 308 in its entirety and replace with the following:

Description

308.01 This work consists of placing Government furnished aggregate or furnishing and placing crushed aggregate for bedding, backfill and roadway aggregate course.

Material

308.02 Conform to the following Subsections:

Crushed aggregateGovernment Furnished
Water725.01

Construction Requirements

308.03 Preparing Surface. Prepare the roadway surface on which aggregate course is placed as shown on the plans.

308.04 Placing Crushed Aggregate.

(a) Roadway aggregate. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with a moisture content suitable for compaction. Spread and shape the mixture on the prepared surface in a uniform layer.

Do not place the mixture in a layer exceeding 6 inches in compacted thickness. When more than one layer is necessary, compact each layer according to Subsection 308.05(a) before placing the next layer.

(b) Bedding and backfill aggregate. Place and shape the mixture in layers that, when compacted, do not exceed 6 inches in depth.

308.05 Compacting and Finishing Crushed Aggregate.

(a) Roadway aggregate. Compact using the methods below, specified in the Schedule of Items.

(1) Method 1. Operate equipment over the full width of spread aggregate.

(2) Method 2. Compact the aggregate by operating compaction equipment over the total width until visible deformation ceases. A minimum of three complete roller passes shall be made at a moisture content suitable for compaction.

(b) Bedding and backfill aggregate. Compact in 6 inch lifts by using a Forest Service approved mechanical compactor until no visible deformation is observed over the entire area of aggregate.

308.06 Acceptance. Crushed aggregate will be evaluated under Subsections 106.02 and 106.03. Furnish a production certification including gradation and quality properties for each source.

Construction of roadway aggregate courses will be evaluated under Subsections 106.02 and 106.04. Method 2 compaction will be evaluated under Section 106.04.

Placement of bedding and backfill aggregate will be evaluated under Subsection 106.02 and Section 209.

Preparation of the surfaces on which crushed aggregate is placed will be evaluated under Section 303 and 209 as applicable.

Measurement

308.07 Measure the Section 308 items listed in the bid schedule according to Subsection 109.02 and the following as applicable.

Measure crushed aggregate by the cubic yard in-place on the road.

Measure width horizontally to include the top of aggregate width including designed widenings. Measure the length horizontally along the centerline of the roadway.

Payment

308.08 The accepted quantities will be paid at the contract price per unit of measurement for the Section 308 pay item listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.

404 - Minor Hot Asphalt Concrete

404.02 Composition of Mix (Job-Mix Formula).

Add the following:

After review of the submitted mix design the CO may increase the asphalt content to be used for construction, up to .3% over that recommended by the Laboratory mix design.

404.07 Compacting (a).

Delete the first sentence and add the following:

Compact the mix to a minimum of 92% of maximum specific gravity (density).

404.09 Acceptance.

Add the following:

The acceptable range of asphalt content for the mix will be the CO approved asphalt mix content + or - 0.4%.

622 - Rental Equipment

622.02 Rental Equipment

Delete the first two sentences of the first paragraph and add the following:

Provide equipment of the type listed in the Schedule of Items. Provide equipment of at least the minimum size needed to efficiently perform the work. Submit the model number of the equipment to the CO for approval before delivery to the project site. Equipment shall be no more than 15 years old and shall be reasonably free of leaks and other mechanical deficiencies.

image1.png

File details come from the government source that posted it. Updated .