Item B-1 Supplemental Specifications

View the file

Other files

File Type Posted
S-10-0286_amend_3.pdf PDF
AG-82B1-S-10-0286_amend_2.pdf PDF
AG-82B1-S-10-0286_amend_1.pdf PDF
mocus_pt_historical.pdf PDF
eagle_mtn_historical.pdf PDF
boulder_creek_current.pdf PDF
AG-82B1-S-10-0286.pdf PDF
mcconnell_mtn_current.pdf PDF
boulder_creek_historical.pdf PDF
item_b-2_supplemental_specs.pdf PDF
solicitation_coversheet.pdf PDF
warm_springs_historical.pdf PDF
split_creek_current.pdf PDF
eagle_mtn_current.pdf PDF
4th_of_july_historical.pdf PDF
warm_springs_current.pdf PDF
split_creek_historical.pdf PDF
4th_of_july_current.pdf PDF
mcconnell_mtn_historical.pdf PDF
mocus_pt_current.pdf PDF
Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

i

FOREST SERVICE

SUPPLEMENTAL SPECIFICATIONS

CLEARWATER NF ARRA

FOREST WIDE TRAIL BRIDGE REPAIRS

WARM SPRINGS BRIDGE - TRAIL 49, MP 0.0

SPLIT CREEK BRIDGE – TRAIL 133, MP 0.5

EAGLE MOUNTAIN BRIDGE – TRAIL 206, MP 0.0

MOCUS POINT BRIDGE – TRAIL 469, MP 0.0

BOULDER CR. BRIDGE REMOVAL - TRAIL 211, MP 0.0

U.S.D.A Forest Service Powell and Lochsa Ranger Districts

Clearwater National Forest Idaho County, Idaho

Prepared by:

GREAT WEST ENGINEERING

2501 Belt View Drive

Helena, MT 59604 ii

FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS

TABLE OF CONTENTS

PREFACE

101 - TERMS, FORMAT, AND DEFINITIONS

102 - BID, AWARD, AND EXECUTION OF CONTRACT

103 - SCOPE OF WORK

104 - CONTROL OF WORK

106 - ACCEPTANCE OF WORK

107 - LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

108 - PROSECUTION AND PROGRESS

109 - MEASUREMENT AND PAYMENT

155 – SCHEDULES FOR CONSTRUCTION CONTRACTS

156 – PUBLIC TRAFFIC

203 – REMOVAL OF STRUCTURES AND OBSTRUCTIONS

555 – TOWER JACKING AND BRACING SYSTEM

623 – GENERAL LABOR

638 – BRIDGE CABLE LUBRICATION

PREFACE

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-03 for construction of

National Forest System Roads.

Substitute the word “trail” for the word “road” for all occurrences throughout FP-03 and these FSSS.

101 - TERMS, FORMAT, AND DEFINITIONS

101.01 Meaning of Terms.

Add the following:

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association

Mine Safety and Health Administration

National Institute of Standards and Technology

National Electrical Safety Code

West Coast Lumber Inspection Bureau

Add the following to (b) SI Symbols:

mp Milepost ppm Part Per Million

Delete (d) Slope notation (vertical: horizontal) and add the following:

Express the slope as the ratio of a number of units horizontal to one unit vertical (1H:1V).

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the

―purchaser‖.

Culvert--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

http://www.nist.gov/

Adjustment in Contract Price--―Equitable adjustment,‖ as used in the Federal

Acquisition Regulations, or ―construction cost adjustment,‖ as used in the Timber Sale

Contract, as applicable.

Change--―Change‖ means ―change order‖ as used in the Federal Acquisition

Regulations, or ―design change‖ as used in the Timber Sale Contract.

Forest Service--The United States of America, acting through the Forest Service, U.S.

Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the

Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, methods of measurement, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

R ig h t o f

W a y

R o a d s id e R o a d s id e

C le a ri n g W id th

R o a d w a y

C le a ri n g

L im it X

Y

G ro u n d

L in e

T ra v e le d

W a y

C L B e rm

S u rf a c e

C o u rs e

B a s e

C o u rs e

F ill

S lo p e

B a c k S lo p e

D ra in a g e D itc h

G ro u n d

L in e

S u b g ra d e

R o a d B e d

S h a p e s a n d d im e n s io n s w ill v a ry t o f it l o c a l c o n d iti o n s

S e e d ra w in g s f o r ty p ic a l s e c tio n s

X a n d Y d e n o te c le a ri n g o u ts id e o f ro a d w a y

N o te

Right - of - Way Line

Right - of - Way Line

Clearing Limit

Shoulder

Shoulder

102 - BID, AWARD, AND EXECUTION OF CONTRACT

102 Bid, Award, and Execution of Contract

Delete Section 102 in its entirety.

103 - SCOPE OF WORK

Deletions

Delete all but subsection 103.01 Intent of Contract.

The project consists of the rehabilitation of four cable suspension trail bridges.

Improvements consist of, but are not limited to, replacement of miscellaneous timber stiffening truss members, repair and adjustments to main and hanger cables, replacement of timber floor beams, and replacement of tower members.

Optional Item # 1 consist of the removal and disposal of the Boulder Creek Trail Bridge located in the Wilderness Gateway Campground.

The projects are located in the Powell and Lochsa Ranger Districts of the Clearwater

National Forest, in Idaho County. Refer to the location map on the title sheet of the plans.

104 - CONTROL OF WORK

104 Control of Work.

Delete sections 104.01, 104.02, and 104.04 and add the following subsections:

104.06 Use of Roads by Contractor

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

104.07. Project Submittals

At a minimum the contractor shall provide project submittals as shown on the below

Submittal Log. Submittal requirements are listed in the Standard Specifications, Supplemental Specifications, and Plans.

SUBMITTAL LOG

No. Description Applicable Spec.

Section or Plans

Date

Rec’d

Date

Approved

1 Tower Sill Replacement Plans Sill replacement procedures

Sill shop drawings

Structural steel connections shop drawings

Temporary bracing and shoring plan.

Jacking system

Concrete adhesive anchors materials

(Required on Mocus Point Trail Bridge)

557 & Plans

2 Bridge Cable Lubrication Materials

Prelube 19 (All bridges)

3 Floor Beam Replacement Plan Replacement procedures

U-Bolt shop drawings

Cable adjustment plan

(Warm Springs and Split Creek Bridges)

Plans

4 Demolition/Removal Plan

(Boulder Creek Trail Bridge only)

Plans

106 - ACCEPTANCE OF WORK

106.01 Conformity with Contract Requirements.

Delete Subsection 106.01 and substitute the following:

Follow the requirements of FAR Clause 52.246-12 Inspection of Construction.

References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.

Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.

Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.

Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.

When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.

The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the

Contractor upon request. Government tests may or may not be performed at the work site.

If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.

Acceptable work conforming to the contract will be paid for at the contract unit bid price.

Four methods of determining conformity and accepting work are described in Subsections

106.02 to 106.05 inclusive. The primary method of acceptance is specified in each Section of work. However, work may be rejected at any time it is found by any of the methods not to comply with the contract.

Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.

(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:

(1) Sampling method;

(2) Number of samples;

(3) Sample transport;

(4) Test procedures;

(5) Testing laboratories;

(6) Reporting;

(7) Estimated time and costs; and

(8) Validation process.

If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program. Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed

Government test results or that produced the test results used as a basis for the dispute.

The CO will review the proposed resolution protocol and may modify it before final approval and execution.

The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the

Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol. If the validity of the Government test results cannot be determined, the Contractor and Government will equally share all costs associated with developing and carrying out the resolution protocol.

(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:

(1) Have the work accepted at a reduced price; or

(2) Be given permission to perform corrective measures to bring the work into conformity.

The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.

106.07 Delete

Delete subsection 106.07.

107 - LEGAL RELATIONS AND RESPONSIBILITY TO THE

PUBLIC

107.05 Responsibility for Damage Claims.

Delete the entire subsection.

107.06 Contractor’s Responsibility for Work.

Delete the following from the first paragraph.

―except as provided in Subsection 106.07‖

107.09 Legal Relationship of the Parties.

Delete the entire subsection:

107.10 Environmental Protection.

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

Exact time and location of spill including a description of the area involved.

Containment procedures.

Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

108 - PROSECUTION AND PROGRESS

108 Delete

Delete Section 108 in its entirety.

109 - MEASUREMENT AND PAYMENT

109 Deletions.

Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

Add the following Definition:

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Add the following:

Contract quantity shall be considered as design quantity for this contract.

Change the following:

―(b) Cubic yard‖ to ―(c) Cubic yard‖.

(p) Thousand Board Feet (MBF). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued-laminated timber, 1,000 board feet is based on actual width, thickness, and length of each piece actually incorporated in the job.

Add the following Subsection:

109.10 Methods of Measurement.

One of the following methods of measurement for determining final payment is

DESIGNATED IN THE SCHEDULE OF ITEMS for each PAY ITEM:

(a) Designed Quantities (DQ). These quantities denote the final number of units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units DESIGNATED IN THE SCHEDULE OF

ITEMS may be authorized under any of the following conditions:

(1) Changes in the work authorized by the CO.

(2) A determination by the CO that errors exist in the original design that cause a Design Quantity PAY ITEM quantity to change by 15 percent or more.

(3) A written request submitted to the CO showing evidence of errors in the original design that cause the quantity of a PAY ITEM to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is in error.

(b) Stake Quantities (SQ). These quantities are determined from staked measurements prior to construction.

(c) Actual Quantities (AQ). These quantities are determined from measurements of completed work.

(d) Vehicle Quantities (VQ). These quantities are measured or weighed in hauling vehicles.

(e) Lump Sum Quantities (LSQ). These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job.

155 – SCHEDULES FOR CONSTRUCTION CONTRACTS

155 Delete

Delete Section 155 in its entirety.

156 – PUBLIC TRAFFIC

156.03 Accommodating Traffic During Work.

Add the following project specific requirements:

Trail shall be closed at the bridge site to public traffic during bridge construction work; however, the rest of the trail shall be kept in an open and passable condition.

The Contractor shall give the Contracting Officer at least 14 days advance written notice prior to any Bridge closure period to allow public notice of the closure period by the Forest Service.

The Contractor shall be responsible for providing, maintaining and removal of all barracades and signs required for the Bridge closure period. Bridge closure shall include barricades at each end of the project limits, as well as, furnish and post at the trailhead a “BRIDGE CLOSED AHEAD” sign to notify the public traffic that the bridge is closed.

Signs shall be retrorefllectorized, construction zone orange with black lettering.

The substrate material may be the Contractor’s preference. All reflective material shall conform to the Manual on Uniform Traffic Control Devices (MUTCD).

Delete the following from the last sentence of the last paragraph:

according to Subsection 106.07(b)

156.08 Traffic and Safety Supervisor.

Delete this subsection in its entirety.

203 – REMOVAL OF STRUCTURES AND OBSTRUCTIONS

203.01 Delete and replace with the following:

This work consists of removing and disposing of bridge members, old connections, clearing slash, and other obstructions as identified in the plans. After removal of bridge members the CO will select various members for salvage as identified in the Work

Summary Table on sheet 3 of the plans, which will be retained by the forest service. The

Contractor shall transport items to the Star Meadows Pole Barn near the Powell Ranger

Station and stockpile the materials at the location as identified by the C.O.

203.05 Disposing of Material.

Modify this subsection as follows:

(a) Remove from project. Add the following:

All materials designated for removal become property of the Contractor and are to be disposed of by removing off of Forest Service Lands in accordance with all local, state, and federal requirements.

(b) Burn. Delete this section.

(c) Bury. Delete this section.

Payment

203.08. Payment for removal and disposal of bridge members, old connections, clearing slash, and other obstructions shall be incidental to other bid items unless noted on the

Schedule of Items.

555 – TOWER JACKING AND BRACING SYSTEM

Add the following.

Description

555.01 Work. Fabricate and erect structural steel, including all required hardware for the jacking and bracing systems, including hydraulic jacks. The plans represent the general steps and materials necessary to replace the timber tower members. The

Contractor may propose an alternate frame system, jacking, and lifting procedures for review. Contractor shall provide detailed shop drawings showing final design of the support frame system, splices, jacking assembly, and connections for review 21 days in advance of fabrication. Design shall be completed and fabrication approved by a

Professional Engineer registered in the State of Idaho.

555.02 Requirements. The Contractor shall furnish material that conforms to specifications in the following section and subsections:

Hardware & Structural Steel................................................. 716.02

Structural Steels.................................................................... 717.01

Bolts and Nuts ...................................................................... 717.01(d)

High Strength bolts, nuts, and washers.................................. 717.01(e)

Measurement

555.21 Use the method of measurement that is DESIGNATED IN THE SCHEDULE OF

ITEMS.

555.22. The accepted quantities will be paid for at the contract price for each PAY ITEM

DESIGNATED IN THE SCHEDULE OF ITEMS.

Payment will be made under:

Pay Item Pay Unit

55705 Treated Glued-Laminated Lumber, Bridge Towers . . . . . . Refer to Bid Schedule

623 – GENERAL LABOR

Delete the first two sentences of the first paragraph and add the following:

Furnish competent workers and appropriate hand tools for work including, but not limited to the following; approach trail work, cable anchor excavation, fencing, etc. as directed by the CO.

638 – BRIDGE CABLE LUBRICATION

638.01 Description – Bridge Cable Lubrication.

Furnish preservative lubricant for field treatment of main suspension cables and hanger cables. Deliver materials in original, unopened containers with manufacturer’s name, labels, product identification, and batch numbers. Damaged materials must be removed from the site. Store all materials off the ground and protect from rain, freezing or excessive heat until ready to use.

Delivery storage and handling, surface preparation, and application shall conform to the manufacturer’s requirements and recommendations. All cables shall receive a minimum of two brush applications per manufacturer’s recommendations.

638.02 Material.

Use materials that meet the following conditions:

(a) Prelube 19 Preservative Lubricant as manufactured by the Grignard Company.

Grignard Company

126 Passaic Street

Newark, NJ 07104

Tel: 973-412-8900

Fax: 973-412-8906 www.grignard.com

Furnish the CO with product literature and certification as required in Section 106.03 for review and approval prior to installation. When requested by the CO, furnish a sample of the material from each lot for verification testing. As specified on the contract plans, the following products meet the above requirements. Prelube 19 - Preservative Lubricant.

Measurement

638.03. Use the method of measurement that is DESIGNATED IN THE SCHEDULE

OF ITEMS.

638.04. The accepted quantities will be paid for at the contract price for each PAY ITEM

DESIGNATED IN THE SCHEDULE OF ITEMS.

http://www.grignard.com/

Payment will be made under:

Pay Item Pay Unit

63801 Bridge Cable Lubrication . . . . . . . . . . . . . . . . . . . . . . . . . . . Lump Sum