About this file

LAKE CREEK DOCUMENTS

View the file

Other files

File Type Posted
AG-82B1-S-10-0237.pdf PDF
Lake Creek Vinal Lake Ltr of Intent.pdf PDF
experience questionnaire.pdf PDF
04Drainage Listing.pdf PDF
01Title.pdf PDF
02ProjectMap.pdf PDF
03SumQuan.pdf PDF
08Pit Plan.pdf PDF
04Typicals.pdf PDF
Exp. Qstnr.docm DOCM document
11SedimentBasinDetail.pdf PDF
08PitSections.pdf PDF
09CulvertDetails.pdf PDF
07PitPlan.pdf PDF
02ProjectMap.pdf PDF
12DrainDipDetail.pdf PDF
09CulvConstDetails.pdf PDF
06Reconstruction Log 593.pdf PDF
07Reconstruction Log 746.pdf PDF
10PowderRiverGate.pdf PDF
06SparLakeCGBarrierRockPlacement.pdf PDF
sf 1442.pdf PDF
Wage Determination.txt TXT text file
AG-82B1-S-10-0237.pdf PDF
05Reconstruction Log 593.pdf PDF
Specs.docx DOCX document
05ReconLogRd384.pdf PDF
10OpenTopBoxCulvertDetail.pdf PDF
01Title.pdf PDF
03SumQuantDetailsWork.pdf PDF
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Table of Contents

Table of Contents1
Preface6
101 - Terms, Format, and Definitions7
101.01 Meaning of Terms7
101.03 Abbreviations.7
101.04 Definitions.7
102 - Bid, Award, and Execution of Contract10
102 Bid, Award, and Execution of Contract10
103 - Scope of Work11
Deletions11
104 - Control of Work12
Deletions12
104.06 Use of Roads by Contractor12
105 - Control of Material13
105.02 Material Sources.13
105.02(a) Government-provided sources.13
105.02 Material Sources13
105.05 Use of Material Found in the Work.13
106 - Acceptance of Work15
106.07 Delete15
107 - Legal Relations and Responsibility to the Public16
107.05 Responsibility for Damage Claims.16
107.06 Contractor’s Responsibility for Work.16
107.09 Legal Relationship of the Parties.16
107.10 Environmental Protection.16
108 - Prosecution and Progress18
108 Delete.18
109 - Measurement and Payment19
109 Deletions19
109.02 Measurement Terms and Definitions.19
109.02 Measurement Terms and Definitions.19
109.03 Weighing Procedures and Devices.20
151 - Mobilization21
151.01 Description21
151.02 Measurement22
153 - Contractor Quality Control23
153.04 Records.23
155 - Schedules for Construction Contracts24
155 Delete.24
156 - Public Traffic25
157 - Soil Erosion Control28
157.02 Materials28
157.03 General.28
201 - Clearing and Grubbing29
201.01 Description29
201.04 Clearing. (c)29
203 - Removal of Structures and Obstructions31
203.01 Description.31
203.05 Disposing of Material.31
203.05 Disposing of Material.32
204 - Excavation and Embankment33
204.06 Roadway Excavation33
204.11 Compaction33
204.14 Disposal of Unsuitable or Excess Material.34
204.15 Acceptance34
204.09 Preparing Foundation for Embankment Construction.35
204.13 Sloping, Shaping, and Finishing.35
Table 204-2 Construction tolerances.35
204.15 Acceptance36
Table 204-1 Sampling and Testing Requirements.36
204.16 Measurement.36
209 - Structure Excavation and Backfill37
209.07 Dewatering37
209.10 Backfill.37
209.11 Compacting.38
209.12Acceptance.38
209.13 See Subsection 109.0538
251 - Riprap39
251.01 Description39
251.02 Material.39
251.07 Acceptance39
251.09 Payment.39
303 - Road Reconditioning40
303.03 Ditch Reconditioning40
303.04 Shoulder Reconditioning40
303.05 Roadbed Reconditioning40
303.07 Roadway Reconditioning41
303.09 Acceptance41
303.10 Measurement41
306 - Dust Palliative42
306.03 General.42
306.06 Acceptance.42
Table 306-1—Sampling and Testing.43
320 - Stockpiled Aggregates45
320.0145
320.0245
321 - Major Aggregate Courses47
409 - Asphalt Surface Treatment56
409.02 Material.56
409.06 Weather.56
409.06 Date & Time.56
409.08 Asphalt Application.57
409.10 Fog Seal.57
409.11 Single Course Surface Treatments.57
Table 409-1 Approximate Quantities of Material-Single Course Surface Treatment58
Table 409-2 Approximate Quantities of Material – Double Course Surface Treatments59
409.13 Acceptance.60
Table 409-4 Sampling and Testing Requirements.60
602 - Culverts and Drains61
602.03 General61
602.05 Laying Metal Pipe61
602.03 General.61
622 - Rental Equipment62
622.02 Rental Equipment62
625 - Turf Establishment63
625.03 General.63
625.04 Preparing Seedbed.63
625.05 Watering63
625.06 Fertilizing.63
625.07 Seeding.64
625.08 Mulching.64
625.09 Protecting and Caring for Seeded Areas.64
625.11 Measurement64
650 - Road Closure Devices66
651 - Development of Pits & Quarries68
703 - Aggregate69
703.05 Subbase, Base, and Surface Course Aggregate69
Table 703-2 Correction70
Table 703-2 Correction71
705 - Rock72
705.02 Riprap Rock72
718 - Traffic Signing and Marking Material73
718.05 Aluminum Panels73
725 - Miscellaneous Material74
725.02 Calcium Chloride, Calcium Chloride Flakes and Magnesium Chloride.74
725.20 Lignin Sulfonate.74
725.30 Bentonite.74

Preface Preface_wo_03_15_2004_m Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.

101 - Terms, Format, and Definitions 101.00_nat_us_07_25_2005

101.01_nat_us_01_22_2009

101.01 Meaning of Terms

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03_nat_us_06_16_2006

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau

Add the following to (b) SI symbols:

mp
Milepost
ppm
Part Per Million

101.04_nat_us_03_29_2007

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.

Culvert--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following:

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.

Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

102 - Bid, Award, and Execution of Contract 102.00_nat_us_02_16_2005 102 Bid, Award, and Execution of Contract

Delete Section 102 in its entirety.

103 - Scope of Work 103.00_nat_us_02_16_2005 Deletions

Delete all but subsection 103.01 Intent of Contract.

104 - Control of Work 104.00_nat_us_06_16_2006 Deletions

Delete Sections 104.01, 104.02, and 104.04.

104.06_nat_us_02_17_2005 Add the following subsection:

104.06 Use of Roads by Contractor

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 - Control of Material 105.02_nat_us_01_18_2007

105.02 Material Sources.

105.02(a) Government-provided sources.

Add the following:

Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.

105.02_01_us_08_20_2004

105.02 Material Sources

Add the following before the first paragraph.

Sources have been designated for this project as follows:

Crushed Aggregate Source- Government Furnished. A source for aggregate material is located in Section 31, T30N, R33W, at the Lake Creek Pit approximately 7 miles from this project.

Waste Site – Government Furnished – A waste site for excess and unsuitable material is located in Section 31, T30N, R33W, at the Lake Creek Pit approximately 7 miles from this project. This site is to be used for the disposal of unsuitable or excess excavated material only. All other materials designated for removal and disposal must be disposed of away from Forest Land as per Section 203.

Under (b) Contractor-located sources add the following:

Prior to any pit development or use of materials, the pit site shall be approved by the CO that the pit site is free of noxious weed as listed on the "All States Noxious Weeds List”.

105.05_nat_us_05_12_2004

105.05 Use of Material Found in the Work.

Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:

Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.

106 - Acceptance of Work 106.07_nat_us_05_11_2004

106.07 Delete

Delete subsection 106.07.

107 - Legal Relations and Responsibility to the Public 107.05_nat_us_05_11_2004

107.05 Responsibility for Damage Claims.

Delete the entire subsection.

107.06_nat_us_06_16_2006

107.06 Contractor’s Responsibility for Work.

Delete the following from the first paragraph.

“except as provided in Subsection 106.07”.

107.09_nat_us_06_16_2006

107.09 Legal Relationship of the Parties.

Delete the entire subsection.

107.10_nat_us_06_16_2006

107.10 Environmental Protection.

Add the following:

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

· Exact time and location of spill including a description of the area involved.

· Containment procedures.

· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

108 - Prosecution and Progress 108.00_nat_us_02_16_2005 108 Delete.

Delete Section 108 in its entirety.

109 - Measurement and Payment 109.00_nat_us_02_17_2005 109 Deletions Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

109.02_nat_us_06_16_2006

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Add the following:

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

Change the following:

“(b) Cubic yard” to “(c) Cubic yard”.

Add the following definition:

(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

109.02_0114_us_06_09_2008

109.02 Measurement Terms and Definitions.

Add the following definition:

(q) Actual quantity. (AQ) These quantities are determined from measurements of completed work.

109.03_nat_us_03_29_2005

109.03 Weighing Procedures and Devices.

(c) Project weighing system.

Add the following:

For aggregates weighed for payment, adjust scale weights of material to deduct the daily average moisture content in excess of 2 percentage points over optimum moisture as determined by AASHTO T 99 or the designated compaction method. If moisture determination is necessary, determine the daily average moisture content in accordance with AASHTO T 255, from not less than three representative samples of aggregate taken at random intervals each day that aggregate is being weighed.

151 - Mobilization 151.01_0114_us_08_04_2005

151.01 Description

Add the following:

This work consists of washing and treating construction equipment and vehicles necessary for equipment transport to remove seeds, plants, and plant fragments before the equipment is used on Forest Service lands.

Wash the sides, tops, and undercarriages of all construction equipment. Remove all seeds, plants, plant fragments, dirt, and debris from the construction equipment. Only equipment inspected by the Forest Service will be allowed to operate within the project area. All subsequent move-ins of equipment to the project area will be treated in the same manner as the initial move-in. This requirement does not apply to cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas off the National Forest.

Equipment will be considered free of soil, seed, and other such debris when a visual inspection does not disclose such material. Disassembly of equipment, components or the need for specialized inspection tools is not required.

Notify the CO in writing at least 24 hours before moving any construction equipment onto the national forest. Notification will include an agreed upon location where the equipment will be available for inspection by the Forest Service. Inspection will be required after every cleaning.

Use methods of cleaning and locations for cleaning approved by the C.O.

For work at a commercial washing facility, use an approved facility.

New infestations of noxious weeds of concern to Forest Service and identified by either Contractor or Forest Service, on the Project Area or on the haul route, will be promptly reported to the other party. Contractor and Forest Service will agree on treatment methods to reduce or stop the spread of noxious weeds when new infestations are found. A current list of noxious weeds of concern to Forest Service is available at each Forest Service office.

151.02 Measurement

Clean equipment prior to moving onto this project. The initial cleaning will not be included in the measurement for payment. Payment under this item will only be made if subsequent cleanings are ordered by the CO. Measurement shall be on an “each” basis, meaning one complete cleaning of all equipment required for this contract. Subsequent cleanings necessitated by the Contractor’s actions but not directed by the CO will not be included in the measurement for payment.

153 - Contractor Quality Control 153.04_nat_us_10_24_2007

153.04 Records.

Delete all but the first sentence

155 - Schedules for Construction Contracts 155.00_nat_us_05_11_2004 155 Delete.

Delete Section 155 in its entirety.

156 - Public Traffic 156.00_nat_us_04_17_2007 Delete Section 156 in its entirety and replace with the following:

Description

156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.

Material

156.02 Conform to the MUTCD and the following Sections and Subsections:

Construction sign panels633
Retro-reflective sheeting718.01
Temporary concrete barrier618
Temporary plastic fence710.11
Temporary traffic control devices718.22

156.03 General. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Delays may not exceed 60 minutes at any one time followed by an open period of no less than 10 minutes.

Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved. Post construction signs and traffic control devices in conformance with MUTCD. All required signs will be in place and approved prior to beginning work on project.

If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.

156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the MUTCD. Install and maintain traffic control devices as follows:

(a) Furnish and install traffic control devices before the start of construction operations.

(b) All detours outside of clearing limits will be approved in writing by the Contracting Officer as part of the traffic control plan.

(c) Install only those traffic control devices needed for each stage or phase.

(d) Relocate temporary traffic control devices as necessary.

(e) Remove devices that no longer apply to the existing conditions.

(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.

(g) Keep temporary traffic control devices clean.

(h) Remove all temporary traffic control devices upon contract completion or when approved.

(i) When required, use flaggers certified by the American Traffic Safety Services Association, the National Safety Council, the International Municipal Signal Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.

156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s). Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.

Prior to closing roads during construction, give written notice to the Contracting Officer at least 10 days in advance.

Table 156-1 Temporary Road Closures

Road Number
From Terminus
To Terminus
Maximum Consecutive Days of Closure
Minimum Consecutive Days Open

156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.

Measurement and Payment

156.07 Do not measure Public Traffic for payment. Compensation is made as an indirect payment.

157 - Soil Erosion Control 157.02_01_us_08_23_2004

157.02 Materials

Add the following:

Provide bales, wattles, logs and rolls from a certified noxious weed free source.

157.03 General

Prior to the start of construction, submit a written plan for review that provides permanent and temporary erosion control measures to minimize erosion and sedimentation during and after construction. Include methods to minimize disturbance to the stream and prevent runoff from the construction site entering directly into the stream. The “Soil Erosion Control Plan” must address construction activities that have the potential for stream sedimentation.

201 - Clearing and Grubbing 201.01_nat_us_02_18_2005

201.01 Description

Replace with the following

This work consists of clearing and grubbing within clearing limits and other designated areas.

201.04_nat_us_02_22_2005

201.04 Clearing. (c)

Delete paragraph (c) and replace with the following:

(c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to within 12 inches or one-third of the stump diameter of the ground, whichever is higher, measured on the side adjacent to the highest ground. For timber sales, stump heights will meet the requirements of the Timber Sale contract.

201.04 Clearing.

Delete subsection (d) and replace with the following:

(d) Do not cut vegetation less than 3 feet tall and less than 3 inches in diameter, that is within the clearing limits but beyond the roadway and not in a decking area, and that does not interfere with sight distance along the road.

Add the following:

(e) Trim branches of remaining trees or shrubs to give a clear height of 14 feet above the roadbed unless otherwise indicated. Trim tree limbs as near flush with the trunk as practicable.

(f) Remove brush from log decks. Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.

201.06_nat_us_11_09_2005

201.06 Disposal

Delete the first sentence of this paragraph and substitute the following:

Limb and deck logs that meet utilization standards at locations approved by the CO or otherwise designated. Deck logs according to 201.04 (f).

203 - Removal of Structures and Obstructions 203.01_nat_us_02_25_2005

203.01 Description.

Delete and replace with the following:

This work consists of disposing of construction slash and debris, salvaging, removing, and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions.

203.05_nat_us_02_18_2005

203.05 Disposing of Material.

Add the following:

(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toeline of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees. Obtain approval for pioneer roads. A pioneer road may be constructed to provide an area for placement of windrows, provided the excavated material is kept within the clearing limits and does not adversely affect the road construction.

(f) Scattering. Scatter construction slash outside the clearing limits without damaging trees. Limb all logs. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations.

(g) Chipping or Grinding. Use an approved chipping machine to grind slash and stumps greater than 3 inches in diameter and longer than 3 feet. Deposit chips or ground woody material on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.

(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.

(i) Decking Firewood Material. Remove brush from decks. Limb and deck logs that do not meet Utilization Standards according to Subsection 201.04 as directed by the CO. Cut logs to lengths less than 30 feet. Ensure that logs stacks are stable and free of brush and soil.

(j) Removal to designated locations. Remove construction slash to designated locations.

(k) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps. Cut unmerchantable logs into lengths of less than 20 feet.

(l) Placing Slash on Embankment Slopes. Place construction slash on completed embankment slopes to reduce soil erosion. Place construction slash as flat as practicable on the completed slope. Do not place slash closer than 2 feet below subgrade. Priority for use of available slash is for: (1) through fills; (2) insides of curves; and (3) ditch relief outlets.

(m) Hydrological Sensitive Placement. Where required use this method in combination with other designated methods to dispose of material to reduce erosion and to aid in re-vegetation:

1. Place windrow segments on contours, wrap in type I geotextile.

2. Place logs as log erosion barriers on contours. Place logs so that 80% of their length is on the ground surface.

3. Scatter slash on bare or disturbed areas within or outside the clearing limits as directed.

4. Scatter chips or ground woody material on bare or disturbed areas within or outside the clearing limits as directed.

Place stumps in swales or on sites to form planting pockets. Place windrow segments on contours, wrap in type I geotextile.

203.05_0114_us_02_15_2005

203.05 Disposing of Material.

(a) Remove from project.

Delete the last two sentences

204 - Excavation and Embankment 204.06_nat_us_03_02_2005

204.06 Roadway Excavation

(a) General.

Add the following:

Retrieve material deposited outside of the clearing limits as directed by the CO. Place unsuitable material in designated areas.

204.06_0114_us_07_06_2005

204.06 Roadway Excavation

Add the following:

(d) Drainage Excavation. Drainage excavation includes construction of side ditches, minor channel changes, inlet and outlet ditches, furrow ditches, rolling drainage dips, surface water deflectors and other minor earth drainage structures as shown on the plans. Compaction for drainage excavation is as shown on the plans.

204.11 Compaction

Delete the first paragraph and replace it with the following:

For compaction according to method (a), (b), or (c), use AASHTO T 27 to determine the amount of material retained on a Number. 4 sieve. For compaction methods (d), (e), or (f) no sieve test is required.

Add the following compaction methods:

(d) Hauling and Spreading Equipment. Adjust the moisture content to a level suitable for compaction. Compact the material by operating equipment over the full width of the roadway.

(e) Roller Compaction. Adjust the moisture content to a level suitable for compaction. Operate Rollers over the full width of each layer until visual displacement ceases, but not fewer than three complete passes. Use rollers that meet the following requirements:

(1) Steel wheeled rollers, other than vibratory, capable of exerting a force of not less than 250 pounds per inch of width of the compression roll or rolls.

(2) Vibratory steel wheeled rollers equipped with amplitude and frequency controls with a minimum weight of 6 tons, specifically designed to compact the material on which it is used.

(3) Pneumatic-tired rollers with smooth tread tires of equal size that will provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 psi.

(4) Sheepsfoot, tamping, or grid rollers capable of exerting a force of 250 lbs/inch of width of roller drum.

(f) Mechanical Tamper. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact each 6 inch layer with a minimum of three complete passes with a mechanical tamper, approved by the CO.

204.14 Disposal of Unsuitable or Excess Material.

Delete the text of the first paragraph and substitute the following:

Dispose of unsuitable or excess material at designated sites or legally off the project.

204.15 Acceptance

Delete the first paragraph.

204.09_nat_us_03_02_2005

204.09 Preparing Foundation for Embankment Construction.

Delete subsection (a) and replace it with the following:

(a) Embankment less than 4 feet high over natural ground. When designated, remove topsoil and break up the ground surface to a minimum depth of 6 inches by plowing or scarifying. Compact the ground surface according to Subsection 204.11.

204.13_0114_us_03_21_2008

204.13 Sloping, Shaping, and Finishing.

Delete section (d) and add the following:

(d) Finishing. Finish the roadbed to be smooth and uniform, and shaped to conform to the typical sections. Remove unsuitable material from the roadbed and replace with suitable material. Finish roadbeds to the designated tolerance class as shown in table 204-2.

Ensure that the subgrade for both surfaced and unsurfaced roads is visibly moist during shaping and dressing. Scarify to 6 inches below the bottom of low sections, holes, cracks, or depressions and bring back to grade with suitable material. Maintain proper ditch drainage.

Use the designated methods to finish the roadbed:

(1) Method A. Remove all material larger than 6 inches from the top 6 inches of the roadbed and replace with suitable material.

(2) Method B. Grid roller or approved equal according to Subsection 204.11 (e).

(3) Method C. For roads designated as Construction Tolerance Class K, L, or M, finish the roadbed by spreading the excavation. Eliminate rock berms.

(4) Method D. Reduce in place or remove and dispose of rocks larger than 4 inches extending above the finished road surface.

Add Table 204-2—Construction Tolerances:

Table 204-2 Construction tolerances.

Tolerance Class(a)

A
B
C
D
E
F
G
H
I
J
K
L
M
Roadbed width (ft)
+0.5
+0.5
+1.0
+1.0
+1.0
+1.0
+1.5
+1.0
+2.0
+2.0
+2.0
+2.0
+2.0

Subgrade elevation (ft)

+0.1
+0.2
+0.2
+0.5
+0.5
+1.0
+1.0
+1.5
+2.0
+3.0
+2.0
+3.0
(c)
Centerline alignment (ft)
+0.2
+0.2
+0.5
+0.5
+1.0
+1.0
`+1.5
+1.5
+2.0
+3.0
+3.0
+5.0
(c)
Slopes, excavation, and embankment (% slope(b)
+3
+5
+5
+5
+5
+5
+10
+10
+10
+10
+20
+20
+20

a. Maximum allowable deviation from construction stakes and drawings.

b. Maximum allowable deviation from staked slope measured from slope stakes or hinge points.

c. Unless otherwise shown the centerline alignment and subgrade elevation, as built, have no horizontal curves with a radius of less than 80 feet, and no vertical curves with a curve length of less than 80 feet when the algebraic difference in the grade change is less than 10 percent, or a curve length of less than 100 feet when the algebraic difference of the grade change is greater than or equal to 10 percent. The centerline grade is not to exceed 20 percent in 100 feet of length.

204.15_nat_us_02_07_2007

204.15 Acceptance

Table 204-1 Sampling and Testing Requirements.

Add the following note to the table:

(2) When compaction methods (d) or (e) are used AASHTO M 145, T 99, T 180, and T 310 are not required for earth embankment test methods.

204.16_0114_us_02_25_2005

204.16 Measurement.

b) Unclassified borrow, select borrow, and select topping

Delete first paragraph and add the following:

Measure by the cubic yard in place.

209 - Structure Excavation and Backfill 209.00_01_us_10_11_2006

209.07 Dewatering

Delete the subsection and add the following:

Submit a Dewatering Plan 5 days prior to beginning excavation.

Construct diversion prior to performing any excavation. Construct diversions using water tight, non-eroding methods. Employ settling basins or other methods so that muddy water is not returned to stream. Install, operate, and remove diversions in a manner that minimizes erosion and sedimentation.

209.10 Backfill.

(a) General.

Add the following:

Replace any pipe that is distorted by more than 5 percent of nominal dimensions, or that is ruptured or broken.

Do not place or backfill pipe that meets any of the following conditions until the excavation and foundation have been approved in writing by the CO:

· Embankment height greater than 6 feet at subgrade centerline.

· Installation in a protected streamcourse.

· Round pipe with a diameter of 48 inches or greater.

· Pipe arches with a span of 50 inches or greater.

· Any box culvert of structure other than pipe culverts.

(b) Pipe Culverts.

(1) Pipe culverts with compacted backfill.

Add the following:

On each side of the pipe, excavate an area at least as wide as the diameter of the pipe. Backfill without damaging or displacing the pipe. Complete backfilling of the trench with suitable material.

209.11 Compacting.

Delete the subsection and add the following:

Compact backfill using designated compaction method A, B, C, or D:

Method A. Ensure that backfill density exceeds the density of the surrounding embankment.

Method B. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact each layer 6 inch layer with a minimum of three complete passes or until visual displacement ceases using a mechanical tamper, (wacker-packer type or approved equal). For compaction under sections 252, 254, 255, 257, 258 and 262 compact with a vibratory steel wheeled roller with a mass of at least 8 tons.

Method C. Compact each layer of backfill with a minimum of two passes with mechanical tamper, (wacker-packer type, or approved equal).

Method D. Determine optimum moisture content and maximum density according to AASHTO T 99 method C. Adjust the moisture content of the backfill material to a moisture content suitable for compaction. Compact material placed in all layers to at least 95 percent of the maximum density. Determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.

0. Acceptance.

Sampling and Testing Requirements Add the following:

Compaction methods (A),(B), and (C) do not require AASHTO T-99 or T-310 test methods for foundation fill.

209.13 See Subsection 109.05

Delete the first sentence and replace with the following:

Do not measure structure excavation, bedding, and backfill for payment.

251 - Riprap 251.00_01_us_10_11_2006

251.01 Description

Delete the first sentence and add the following:

This work consists of furnishing, hauling, and placing of riprap for bank protection, slope protection, drainage structures, erosion control, and other features shown on the plans.

251.02 Material.

Add the following:

When shown on the plans stone from the project site may be utilized.

251.07 Acceptance

Delete sampling and testing requirements of Table 251-1 and certification requirements of Subsection 106.03.

251.09 Payment.

The cost of excavation, embankment and haul required for placement of riprap is incidental to pay items listed in the bid schedule. No payment will be made under Item 251.

303 - Road Reconditioning 303.03_0114_us_08_04_2005

303.03 Ditch Reconditioning

Delete the last sentence and add the following:

Dispose of waste as shown on the plans.

303.04 Shoulder Reconditioning

Delete the last sentence and add the following:

Dispose of waste as shown on the plans.

303.05 Roadbed Reconditioning

Delete and add the following:

Repair soft and unstable areas according to Subsection 204.07. Remove all organic, deleterious material larger than 6 inches from the top 6 inches of subgrade. Dispose of waste as shown on the plans. Scarify and shape the traveled way and shoulders at locations and to the depth and width designated on the plans. Remove surface irregularities and shape to provide a uniform surface.

Dispose of rock larger than 4 inches brought to the surface during scarification in areas designated on the plans.

For portions of roads not requiring scarification, the roadbed may contain rocks larger than 4 inches provided they do not extend above the finished roadbed surface. Reduce in place or remove rock extending above the finished roadbed surface. Dispose of removed rock in areas designated on the plans.

Compact using the following method as specified:

(a) Compaction A. Operate equipment over the full width.

(b) Compaction B. Operate rollers over the full width of each layer until visual displacement ceases, but not fewer than three complete passes. Use rollers that meet the following requirements:

(1) Steel wheeled rollers, other than vibratory, capable of exerting a force of not less than 250 pounds per inch of width of the compression roll or rolls.

(2) Vibratory steel wheeled rollers equipped with amplitude and frequency controls with a minimum weight of 6 tons, specifically designed to compact the material on which it is used.

(3) Pneumatic-tired rollers with smooth tread tires of equal size that will provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 psi.

303.07 Roadway Reconditioning

Add the following:

Blade and shape the subgrade for both surfaced and unsurfaced roads when moisture content is suitable for compaction.

303.09 Acceptance

Delete the first sentence.

303.10 Measurement

Delete the first sentence of the third paragraph and replace with:

Measure roadbed reconditioning, aggregate surface reconditioning, roadway reconditioning, and pulverizing by the mile, by the station, or by the square yard.

306 - Dust Palliative 306.03_nat_us_03_02_2005

306.03 General.

Add the words “or rainy” after the word “foggy” in the third sentence.

306.06_nat_us_03_02_2005

306.06 Acceptance.

Submit certification and samples as specified in Table 306-1.

306.10_nat_us_03_02_2005 Add Table 306-1:

Table 306-1—Sampling and Testing.

Material or Product
Type of Acceptance (Subsection)
Characteristic
Test Method Specification
Sampling Frequency
Point of Sampling
Spilt
Reporting Time
Production Certification (Subsection 106.03)
Chemical Composition
Subsection 725
1 per type of material
Source of materials
No
Prior to construction
Toxicity Tests(1)
EPA Standard Operating Procedure 2022
“
“
“
“
Specific Gravity Chart (2) (liquid non-petroleum products only)
-
“
“
“
“
Material Safety Data Sheet
-
“
“
“
“
Quality
-
First load and determined by the CO thereafter
Hauling vehicle (3)
Samples submitted to the Government
During construction

Note: 1) 96-Hour static toxicity test using Daphnia and juvenal rainbow trout (Oncorhynchus mykiss).

2) Specific Gravity Chart: Correlation of Specific Gravity with percent solids of constituent presented in 1 percent increments beginning with a 5 percent solution up to, including, and exceeding 5 percent (or the solubility limit of the product) the proposed concentration of the undiluted product.

3) If the product is liquid, obtain a two-liter sample from the transfer load. If the product is solid obtain a 1-pound sample from the load.

320 - Stockpiled Aggregates 320.00_nat_us_12_19_2008 Description

320.01 This work consists of furnishing and placing aggregate in a stockpile at an existing site or constructing a new site and placing the aggregate at the new site.

Material

320.02 Conform to the following Section:

Aggregate 703 Provide the gradation and quality requirements specified in the Section identified in the pay item.

Construction Requirements

320.03 Stockpile Site. Prepare existing sites as necessary to accommodate the quantity of aggregate to be stockpiled.

For new sites, clear and grub according to Section 201. Grade and shape the site to a uniform cross-section that drains. Compact the floor of the site with at least three passes using compaction equipment conforming to Subsection 204.11. Place, compact, and maintain a minimum 6 inches of crushed aggregate over the stockpile site and access roads. Prevent contamination of the stockpiles.

320.04 Stockpile. After a representative quantity of aggregate is produced, submit proposed target values for the appropriate sieve sizes along with a representative 350-pound sample.

Set target values within the gradation ranges shown in Table 703-2 or 703-3 for the required grading.

Request site approval before stockpiling aggregates. Make the stockpiles neat and regular in shape. Make the side slopes no flatter than 1:1.5.

Build the stockpiles in layers not exceeding 3 feet thick. Complete each layer before depositing aggregates in the next layer. Do not allow aggregates from the one layer to run down over lower layers of the stockpile. Do not drop aggregates from a bucket or spout in one location to form a cone-shaped pile.

Construct stockpile layers by spreading aggregates with trucks or other approved pneumatic-tired equipment. Do not push aggregates into piles.

When operating trucks on stockpiles, avoid tracking dirt or other deleterious material onto the stockpiled material.

Space stockpiles far enough apart or separate stockpiles by suitable walls or partitions to prevent the mixing of the different aggregate gradations.

320.05 Acceptance. Aggregate for stockpiling will be evaluated under Subsection 301.08 and Table 301-1. The point of sampling will be the belt or stockpile.

Preparation of stockpile sites and construction of stockpiles will be evaluated under Subsections 106.02 and 106.04.

Clearing will be evaluated under Section 201.

Measurement

320.06 Measure the 320 items listed in the bid schedule according to subsection 109.02.

Payment

320.07 The accepted quantities, measured as provided in subsection 109.02 and above, will be paid at the contract price per unit of measurement for the Section 320 pay items listed in the bid schedule except the stockpiled aggregate.

321 - Major Aggregate Courses 321.00_01_us_10_11_2006 Description

321.01 This work consists of constructing one or more courses of aggregate on a prepared surface. Work includes producing aggregate by grid rolling, screening, or crushing methods, or placing pit-run or Government-furnished aggregate. Work may include additive mineral filler, or binder.

Surface aggregate grading is designated as shown in Table 703-3.

Subbase and base aggregate grading is designated as shown in Table 703-2.

Screened aggregate grading is designated as shown in Table 703-16.

Material

321.02 Conform to the following Subsections:

Aggregate703.05
Water725.01
Bentonite725.30
Calcium Chloride flake725.02
Magnesium Chloride or Calcium Chloride liquid725.02
Lignin Sulfonate725.20

Construction Requirements

321.03 General. Prepare the surface on which the aggregate course is placed according to Section 204 or 303 as applicable.

Written approval of the roadbed is required before placing aggregate.

Develop and use Government provided sources according to Section 105.

Develop, haul, and apply water in accordance with Section 170.

Submit a written quality control plan and perform the Contractor quality control and inspections according to Section 153.

After a representative quantity of subbase, base, or surface aggregate is produced, submit proposed target values for the appropriate sieve sizes along with a representative 75-pound sample at least two days before incorporating the aggregate into the work. Submit target values within the gradation ranges shown in Table 703-2 or 703-3 for the required grading. After reviewing the Contractor’s proposed target values the CO will determine the final values for the gradation and notify the Contractor in writing.

No quality requirements or no gradation other than maximum size will be required for pit run and grid-rolled material. For grid rolling, use all suitable material that can be reduced to maximum size.

After processing on the road, remove all oversize material from the road and dispose of it as directed by the CO.

Provide additives or binder, if required, at the proportions specified.

If the aggregate is produced and stockpiled before placement, handle and stockpiled according to Section 320. Establish stockpile sites at approved locations.

321.04 Mixing and Spreading. Mix the aggregate and adjust the moisture content to obtain a uniform mixture with a moisture content suitable for the specified compaction method. Spread and shape the mixture on the prepared surface in a uniform layer with no segregation of size, and to a loose depth that will provide the required compacted thickness.

Do not place in layers exceeding 6 inches in compacted thickness for aggregate base and surface courses or twice the maximum particle size for screened aggregate. When more than one layer is necessary, compact each layer according to Subsection 321.05 before placing the next layer. Route hauling and leveling equipment uniformly over the full width.

When placing aggregate over geotextile, place aggregate in a single lift to the full depth specified.

When additives are specified ensure that aggregate, additives, and any required water, mineral filler, and binder are mixed by the specified method. Control additive proportions to 0.5 percent dry weight.

Additive Mixing Methods:

(a) Stationary Plant Method. Mix the aggregate with other required materials in an approved mixer. Add water during the mixing operation in the amount necessary to provide the moisture content for compacting to the specified density. After mixing, transport the aggregate to the jobsite while it contains the proper moisture content, and place it on the roadbed or base course using an aggregate spreader.

(b) Travel Plant Method. After placing the aggregate for each layer with an aggregate spreader or windrow-sizing device, uniformly mix it with other required materials using a traveling mixing plant or rotary mixer. During mixing, add water to provide the necessary moisture content for compacting to the specified density.

(c) Road Mix Method. After placing the aggregate for each layer, mix it with other required materials at the required moisture content for compacting to the specified density until a uniform distribution is obtained.

321.05 Compacting. Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.

Compact the aggregate using one of the following methods as specified:

Compaction A. Adjust the moisture content to a level suitable for compaction. Operate spreading and hauling equipment over the full width of each layer of the aggregate.

Compaction B. Operate rollers and compact as specified in Subsection 204.11.

Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a).

Compaction D. Compact each layer of aggregate to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 99, method C or D.

Compaction E. Compact each layer of aggregate to a density of at least 96 percent of the maximum density, as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).

Compaction F. Compact each layer of aggregate to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 180, method C or D.

Compaction G. Compact each layer of aggregate to a density of at least 100 percent of the maximum density as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).

Compaction H. Compact the aggregate by operating compaction equipment over the total width until visible deformation ceases. A minimum of five complete passes shall be made at a moisture content suitable for compaction.

Compaction I. Adjust the moisture content to a level suitable for compaction. Operate rollers over the full width of each layer until visual displacement ceases, but not fewer than three complete passes. Use rollers that meet the following requirements:

(1) Steel wheeled rollers, other than vibratory, capable of exerting a force of not less than 250 pounds per inch of width of the compression roll or rolls.

(2) Vibratory steel wheeled rollers equipped with amplitude and frequency controls with a minimum weight of 6 tons, specifically designed to compact the material on which it is used.

(3) Pneumatic-tired rollers with smooth tread tires of equal size that will provide a uniform compacting pressure for the full width of the roller and capable of exerting a ground pressure of at least 80 psi.

For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.

321.06 Construction Tolerance. If grade finishing stakes are required, finish the surface to within ±0.05 feet from staked line and grade elevation.

If grade finishing stakes are not required, shape the surface to the required template and check the surface with a 10-foot straightedge. Defective areas are surface deviations in excess of 1/2 inch in 10 feet between any two contacts of the straightedge with the surface.

Correct all defective areas by loosening the material, adding or removing material, reshaping, and compacting.

Ensure that the compacted thickness is not consistently above or below the specified thickness. The allowable average thickness of four random measurements for any ½ mile of road segment is within + ¼ inch of the specified thickness. The maximum variation from the compacted specified thickness is ½ inch.

Ensure that the compacted width is not consistently above the specified width. The allowable average width of any four random measurements along any ½ mile of road segment is within +4 inches of the specified width. The maximum variation from the specified width will not exceed +12 inches at any point.

321.07 Maintenance. Maintain the aggregate course to the correct line, grade, and crosssection by blading, watering, rolling, or any combination thereof until placement of the next course. Correct all defects according to Subsection 321.06.

321.08 Acceptance. See Table 321-1 or Table 321-2…