- Attached to
- RECOVERY - LAKE CREEK AGGREGATE/VINAL LAKE/LAKE MEADOWS RESURFACING - KOOTENAI NATIONAL FOREST
- Solicitation number
- AG-82B1-S-10-0237
About this file
Abstract
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Lake Creek Vinal Lake Ltr of Intent.pdf | ||
| experience questionnaire.pdf | ||
| 04Drainage Listing.pdf | ||
| 01Title.pdf | ||
| 02ProjectMap.pdf | ||
| 03SumQuan.pdf | ||
| 08Pit Plan.pdf | ||
| 04Typicals.pdf | ||
| Exp. Qstnr.docm | DOCM document | |
| 11SedimentBasinDetail.pdf | ||
| 08PitSections.pdf | ||
| 09CulvertDetails.pdf | ||
| 07PitPlan.pdf | ||
| 02ProjectMap.pdf | ||
| 12DrainDipDetail.pdf | ||
| 09CulvConstDetails.pdf | ||
| 06Reconstruction Log 593.pdf | ||
| 07Reconstruction Log 746.pdf | ||
| 10PowderRiverGate.pdf | ||
| 06SparLakeCGBarrierRockPlacement.pdf | ||
| sf 1442.pdf | ||
| SuppSpecs.docx | DOCX document | |
| Wage Determination.txt | TXT text file | |
| AG-82B1-S-10-0237.pdf | ||
| 05Reconstruction Log 593.pdf | ||
| Specs.docx | DOCX document | |
| 05ReconLogRd384.pdf | ||
| 10OpenTopBoxCulvertDetail.pdf | ||
| 01Title.pdf | ||
| 03SumQuantDetailsWork.pdf |
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project:
Recovery - Lake Creek Aggregate and Vinal
Lake/Long Meadows Resurfacing
Solicitation # AG-82B1-S-10-0237
Sol. Type IFB
Item # Description Qty Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Amount
Lake Creek Aggregate
15101 Mobilization 1 LS $9,000.00 9,000.00$ $25,000.00 25,000.00$ $5,860.00 5,860.00$ $17,500.00 17,500.00$
15707 Bales Straw 10 EA $20.00 200.00$ $8.00 80.00$ $9.60 96.00$ $50.00 500.00$
20102 Clearing and Grubbing 1 LS $2,000.00 2,000.00$ $1,500.00 1,500.00$ $4,890.00 4,890.00$ $24,500.00 24,500.00$
20301 Removal, Metal Culvert 3 EA $116.00 348.00$ $100.00 300.00$ $250.00 750.00$ $200.00 600.00$
20401
Roadway Excavation, Compaction Method E, Finishing
Method D 2000 CY $11.35 22,700.00$ $14.00 28,000.00$ $5.20 10,400.00$ $18.00 36,000.00$
20416 Waste, Excess material 649 CY $16.25 10,546.25$ $16.00 10,384.00$ $4.15 2,693.35$ $9.00 5,841.00$
20425 Boulder Placement, Barrier Rocks 50 EA $60.59 3,029.50$ $20.00 1,000.00$ $35.00 1,750.00$ $160.00 8,000.00$
25101 Placed RipRap, Class 1 5 CY $23.51 117.55$ $30.00 150.00$ $35.00 175.00$ $65.00 325.00$
30359 Road Reconditioning, Compaction method B 64.04 Station $44.26 2,834.41$ $50.00 3,202.00$ $24.90 1,594.60$ $17.00 1,088.68$
32001 Stockpiled Aggregate, Subsection 703.05, Grading D-SR 7085 TON $6.64 47,044.40$ $5.65 40,030.25$ $5.85 41,447.25$ $5.85 41,447.25$
32111
Aggregate Surface Course, Grading D-SR, Compaction, Method I 1544 CY $23.82 36,778.08$ $14.90 23,005.60$ $12.90 19,917.60$ $26.00 40,144.00$
60270
18" CMP (Incl Culv Exc), Thickness: Steel .064" or
Aluminum .075", Compaction Method B 118 LF $37.67 4,445.06$ $25.00 2,950.00$ $24.90 2,938.20$ $30.00 3,540.00$
62201a Equipment Rental, Hydraulic Excavator with Thumb 4 HR $140.76 563.04$ $105.00 420.00$ $95.00 380.00$ $127.00 508.00$
62301 General Labor 4 HR $41.59 166.36$ $45.00 180.00$ $52.00 208.00$ $44.00 176.00$
62550 Seeding and Fertilizing, Dry Method 1 ACRE $450.00 450.00$ $450.00 450.00$ $250.00 250.00$ $1,650.00 1,650.00$
65002
Install Road Closure Device, Type Powder River Style
Gate 1 EA $500.00 500.00$ $1,200.00 1,200.00$ $475.00 475.00$ $1,000.00 1,000.00$
140,722.65$ 137,851.85$ 93,825.00$ 182,819.93$
Additive Bid Item 1
30650 Calcium Choride, Solid 94% 9.9 TON $468.75 4,640.63$ $510.00 5,049.00$ $489.00 4,841.10$ $567.00 5,613.30$
4,640.63$ 5,049.00$ 4,841.10$ 5,613.30$
Additive Bid Item 2
40904 Emulsified Asphalt Grade CRS-2P 66 TON $500.00 33,000.00$ $721.00 47,586.00$ $789.00 52,074.00$ $770.00 50,820.00$ 40950 Pavement Surface Preparation 14444 SY $1.92 27,732.48$ $3.81 55,031.64$ $3.24 46,798.56$ $4.10 59,220.40$
60,732.48$ 102,617.64$ 98,872.56$ 110,040.40$
Additive Bid Item 3
32001 Stockpiled Aggregate, Subsection 703.05, Grading D-SR 3000 TON $5.74 17,220.00$ $4.00 12,000.00$ $5.85 17,550.00$ $5.90 17,700.00$
17,220.00$ 12,000.00$ 17,550.00$ 17,700.00$
Subtotal
Subtotal
Subtotal
Noble Excavating, Inc.
P.O. Box 1592
Libby, MT 59923
Government Estimate Thompson Contracting, Inc
P.O. Box 449
Libby, MT 59923
Western Reclamation, LLC
506 Quartz Loop
Superior, MT 59872
Subtotal
Vinal Lake/Long Meadows Resurfacing
15101 Mobilization 1 LS $14,000.00 14,000.00$ $30,000.00 30,000.00$ $7,740.00 7,740.00$ $35,000.00 35,000.00$
15710 Sediment Traps 1 EA $140.00 140.00$ $25.00 25.00$ $245.00 245.00$ $200.00 200.00$
20301 Removal, Culvert 11 EA $46.00 506.00$ $100.00 1,100.00$ $240.00 2,640.00$ $200.00 2,200.00$
20301 Removal, Culvert Ends 2 EA $25.00 50.00$ $50.00 100.00$ $48.00 96.00$ $100.00 200.00$
20419 Draniage Excavation, Type Open Box Culvert 232 LF $15.00 3,480.00$ $20.00 4,640.00$ $14.40 3,340.80$ $30.00 6,960.00$
20419 Drainage Excavation, Type outlet Ditch 65 LF $6.00 390.00$ $2.00 130.00$ $3.75 243.75$ $25.00 1,625.00$
20420 Drainage Excavation, Type Drainage Dip 5 EA $310.00 1,550.00$ $250.00 1,250.00$ $425.00 2,125.00$ $200.00 1,000.00$
23050 Brushing 11.59 MILE $428.71 4,968.75$ $800.00 9,272.00$ $600.00 6,954.00$ $520.00 6,026.80$
25101 Placed RipRap, Class 1 21 CY $75.46 1,584.66$ $30.00 630.00$ $35.00 735.00$ $65.00 1,365.00$
25101 Placed RipRap, Class 2 7 CY $75.46 528.22$ $30.00 210.00$ $35.00 245.00$ $70.00 490.00$
25101 Placed RipRap, Class 3 4 CY $75.46 301.84$ $30.00 120.00$ $35.00 140.00$ $80.00 320.00$
30122 Pit Run Maximum Size 1-1/2", Compaction Method B 820 CY $6.84 5,608.80$ $15.05 12,341.00$ $7.25 5,945.00$ $19.00 15,580.00$
30322 Roadway Reconditioning, Compaction Method B 17.28 MILE $2,359.40 40,770.43$ $2,300.00 39,744.00$ $750.00 12,960.00$ $875.00 15,120.00$
30650 Calcium Chloride Flake 20 TON $470.00 9,400.00$ $450.00 9,000.00$ $480.00 9,600.00$ $547.00 10,940.00$
32109
Aggregate Surface Course, Grading D-SR, Compaction
Method I 19049 TON $10.28 195,823.72$ $10.05 191,442.45$ $11.35 216,206.15$ $11.95 227,635.55$
32134 Furnishing and Applying Bentonite, Method C 35 TON $227.24 8,862.36$ $275.00 9,625.00$ $255.00 8,925.00$ $455.00 15,925.00$
60253
66" Span, 51" Rise corrugated Steel Pipe Arch, (Incl
Culv Exc), 0.109" Thickness, Compaction method B 64 LF $148.72 9,518.08$ $135.00 8,640.00$ $149.00 9,536.00$ $265.00 16,960.00$
60270
18" CMP (Incl Culv Exc), Thickness: Steel .064", Compaction Method B 614 LF $27.46 16,915.36$ $25.00 15,350.00$ $24.90 15,288.60$ $30.00 18,420.00$
60270
24" CMP (Incl Culv Exc), Thickness: Steel .064", Compaction Method B 70 LF $32.43 2,270.10$ $30.00 2,100.00$ $38.00 2,660.00$ $34.00 2,380.00$
60270
18" CMP (Incl Culv Exc), Thickness: Steel .064", Compaction Method B 48 LF $50.16 2,407.68$ $25.00 1,200.00$ $24.90 1,195.20$ $32.00 1,536.00$
60710 Reconditioning Drainage Structures, Culverts 10 EA $70.00 700.00$ $50.00 500.00$ $125.00 1,250.00$ $200.00 2,000.00$
62550 Seeding and Fertilizing, Dry Method 3 ACRE $450.00 1,350.00$ $450.00 1,350.00$ $250.00 750.00$ $1,800.00 5,400.00$
65002
Install Road Closure Device, Type 16' Powder River
Style Gate 1 EA $500.00 500.00$ $1,200.00 1,200.00$ $475.00 475.00$ $1,000.00 1,000.00$
321,626.00$ 339,969.45$ 309,295.50$ 388,283.35$
Additive Bid Item 1
30650 Calcium Chloride Flake 45.2 TON $470.00 21,244.00$ $450.00 20,340.00$ $480.00 21,696.00$ $567.00 25,628.40$
21,244.00$ 20,340.00$ 21,696.00$ 25,628.40$
Additive Bid Item 2
30650 Calcium Chloride Flake 28.9 TON $470.00 13,583.00$ $450.00 13,005.00$ $480.00 13,872.00$ $567.00 16,386.30$
13,583.00$ 13,005.00$ 13,872.00$ 16,386.30$
Additive Bid Item 3
32001 Stickpiled Aggregate, Subsection 703.05, Grading D-SR 5000 TON $5.43 27,150.00$ $3.75 18,750.00$ $5.85 29,250.00$ $5.90 29,500.00$
27,150.00$ 18,750.00$ 29,250.00$ 29,500.00$
Additve Bid Item 4
32001 Stickpiled Aggregate, Subsection 703.05, Grading D-SR 5000 TON $5.43 27,150.00$ $3.70 18,500.00$ $5.85 29,250.00$ $5.90 29,500.00$
27,150.00$ 18,500.00$ 29,250.00$ 29,500.00$
Subtotal
Subtotal
Subtotal
140,722.65$ 137,851.85$ 93,825.00$ 182,819.93$
82,593.11$ 119,666.64$ 121,263.66$ 133,353.70$
223,315.76$ 257,518.49$ 215,088.66$ 316,173.63$
321,626.00$ 339,969.45$ 309,295.50$ 388,283.35$
89,127.00$ 70,595.00$ 94,068.00$ 101,014.70$
410,753.00$ 410,564.45$ 403,363.50$ 489,298.05$
634,068.76$ 668,082.94$ 618,452.16$ 805,471.68$
Yes Yes Yes
Yes Yes Yes
Yes Yes Yes
Yes Yes Yes
Yes Yes Yes
Active Active Active
Yes Yes Yes
Active Active Active
Government estimate qty is different from what is one solicitation, qty matches solicitation, but $ matches government estimate.
ORCA/Rep and Certs
Received on Time (# of Copies)
SF 1442
DUNS and TIN # Provided
Experience/Technical Provided
Bid Guarantee Received
Total Vinal Lake
CCR Checked
EPLS Checked