Crooked River Road Specs
View the file
Other files
| File | Type | Posted |
|---|---|---|
| amend 004.docx | DOCX document | |
| stew.amend4cr.pdf | ||
| Amendment 003 | — | |
| Amendment 003 | — | |
| Crooked River Stewardship All_final(amend 002).pdf | ||
| Amend 2 Crooked river(signed).pdf | ||
| Signed Amendment 001.JPG | JPG image | |
| Amend 01 Attachment Final.pdf | ||
| Amendment 001 | — | |
| Crooked River Project Map1.pdf | ||
| ARRA signs contract specs.doc | DOC document | |
| Crooked River Appendices 12209.doc | DOC document | |
| Crooked River Road DesignSpecs.pdf | ||
| ARRA Signs for contract.pdf | ||
| Crooked River Project Map2.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TABLE OF CONTENTS
Table of Contents ......................................................................................................... 47-48 PNF-SPS-201 Clearing and Grubbing
201.01 Description
201.02 Material
201.03 General
201.04 Clearing
201.05 Grubbing
201.06 Disposal
201.07 Acceptance
PNF-SPS-203 Removal of Structures and Obstructions
203.01 Description
203.05 Disposal of Material
PNF-SPS-204 Excavation and Embankment
204.10 Embankment Construction
204.11 Compaction
204.13 Sloping, Shaping, and Finishing
PNF-SPS-209 Structure Excavation and Backfill
209.04 General
PNF-SPS-251 Riprap
251.05 Hand-Placed Riprap
PNF-SPS-301 Untreated Aggregate Courses
301.03 General
301.04 Mixing and Spreading
301.05 Compacting
PNF-SPS-303 Road Reconditioning
303.03 Ditch Reconditioning
303.04 Shoulder Reconditioning
303.05 Roadbed Reconditioning
303.06 Aggregate Surface Reconditioning
303.08 Pulverizing
303.09 Acceptance
PNF-SPS-322 Crushed Aggregate PNF-SPS-576 Precast Box Culvert
576.01 Description
576.02 Requirements
576.03 Design Requirements
576.04 Design Calculations and Drawings
576.05 General
576.06 Performance
576.07 Measurement
576.08 Payment
PNF-SPS-602 Culverts and Drains
602.03 General
602.08 Acceptance
PNF-SPS-619 Fences, Gates, and Cattleguards
619.07 Concrete Foundation
PNF-SPS-625 Turf Establishment
625.02 Material
Table 625-1
625.03 Seeding Seasons
625.07 Seeding
625.08 Mulching
625.11Measurement PNF-SPS-648 Stream Simulation
648.01 Description
648.02 Material
648.03 General
648.04 Placed Stream Simulation Rock and Fish Rest Stops
648.05 Foundation Fill
648.06 Acceptance
648.07 Measurement
648.08 Payment
PNF- 651- Development of Pits and Quarries PNF- SPS-703 Aggregate PNF- SPS - 705 Rock
705.07 Channel Rock
705.08 Stream Bed Simulation
PNF SPS-201
201 – Clearing and Grubbing
Description 201.01 Delete and replace with the following:
This work consists of clearing and grubbing within clearing limits and other designated areas.
Material
201.02 Delete Tree wound dressing material reference.
Construction Requirements
201.03 General
Delete the first sentence.
Delete the last sentence.
201.04 Clearing.
Delete paragraph (c) and replace with the following:
(c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to within 12 inches or one-third of the stump diameter of the round, whichever is higher, measured on the side adjacent the highest ground. For timber sales, stump height will meet the requirements of the Timber Sale Contract.
Delete paragraph (d) and replace with the following:
(d) Do not cut vegetation less than 3 feet tall and less than 3 inches in diameter which is within the clearing limits but beyond the roadway and not in a decking area and that does not interfere with sight distance along the road.
Add the following:
(e) Trim branches of remaining trees or shrubs to give a clear height of 14 feet above the roadbed unless otherwise indicated. Trim tree limbs as near flush with the trunk as practicable.
APRIL 2009
PNF-SPS-201-1 (Continued)
(f) Remove brush from log decks. Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll.
(g) Remove dead trees over 6 inches in diameter measured at 12 inches above the ground that lean toward the road and are tall enough to reach the roadbed.
Add the following:
All merchantable R/W timber is included timber of Crooked River Stewardship Contract.
Utilization standards for merchantable timber are listed in A2. Fall and buck merchantable material into suitable lengths. Pieces (logs) meet utilization standards when such pieces would have met Utilization Standard if bucking lengths were varied to include such material.
Utilization Standards
SEE A2
Scaling Services
SEE A14
201.05 Grubbing.
Delete and replace with the following:
Grub all embankment areas. Undisturbed stumps may be left in place if they protrude less than 6 inches above the original ground and will be covered with more than 2 feet of embankment.
201.06 Disposal.
Delete the second sentence and replace with the following:
Dispose of merchantable timber designated for removal according to the provisions of the Timber Sale Contract.
Dispose of clearing and grubbing material by method (1), scattering or method 2, Windrowing construction slash.
PNF-SPS-201-01 (Continued)
(1) Scattering. Scatter construction slash outside the roadway without damaging trees.
Limb all logs not meeting utilization standards. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations.
(2) Windrowing Construction Slash. Clear areas to accommodate the windrow slash.
Place construction slash outside the roadway in neat, compacted windrows laid approximately parallel to and along the toeline of the embankment slopes. Do not permit the top of the windrows to extend above the top of the subgrade. Use construction equipment to form a compact and uniform pile. Construct breaks of a least 15 feet at 200 foot intervals along the windrow. Do not place windrows against trees.
201.07 Acceptance.
Delete the second and third sentences.
PNF-SPS-203
Section 203 – REMOVAL OF STRUCTURES AND OBSTRUCTIONS
203.01 Description
Add the following:
The existing structures to be removed shall be removed and disposed of away from Forest land according to all applicable local, state and federal regulations and 203.05(a).
Temporary soil erosion control measures shall be in place prior to commencing.
203.01_nat us 06_08_2005
203.05 Disposing of Material
e. Placing Slash on Embankment Slopes. Place construction slash on completed embankment slope to reduce soil erosion. Place construction slash as flat as practicable on the completed slopes. Do not place slash closer than 2 feet below the top of the embankment. Leave stumps on tree trunks and cut off branches. Set the tree trunks so they are laying parallel to the contour lines.
PNF-SPS-204
Section 204 – EXCAVATION AND EMBANKMENT
204.10 Embankment Construction.
Add the following
(e) Side Casting and End Dumping. Embankment may be placed by side casting and end dumping. Build solid embankments by working smaller rocks and fines in with larger rocks and fines to fill the voids. Operate hauling and spreading equipment uniformly over the full width of the embankment.
For Embankment Construction Method (e) no compaction testing is required.
204.11 Compaction
Delete in its entirety and replace with the following:
Add the following:
Method (e) Compaction will be accomplished by operating hauling equipment and spreading equipment uniformly over the full width of each layer. Moisture content of the material shall be adjusted to obtain a level adequate for compaction.
204.13 Sloping, Shaping, and Finishing.
(D) Finishing.
Delete the paragraph and add the following:
The road surface shall be finished to a reasonably smooth, uniform shape conforming to the typical section SHOWN ON THE PLANS. Remove unsuitable material from the roadbed and replace it with suitable material.
Compact the subgrade as required and finish roadbeds to within ± 1’ (one foot) of the staked lines and grades.
PNF- PNF-SPS-209
Section 209 – STRUCTURE EXCAVATION AND BACKFILL
209.04 General
Delete and add the following:
Excavate trenches and foundation pits according to Subsection 208.04.
Conserve material and sort it for the following types of material: general embankment, embankment in the zone next to the metal pipe or precast concrete, and stream simulation material.
Dispose of excess or unsuitable material at the area designated by the Engineering Representative (ER). The material shall be incorporated into the fillslope at the edge of the existing road.
PNF-SPS-251
Section 251 – RIPRAP
251.05 Delete and replace with the following:
251.05 Hand-Placed Riprap. Hand-placed riprap is rock place by hand on a prepared surface. Use class 2 Riprap as shown below:
Class Percent of Mass Approximate Cubic Rock by Mass Dimensions (pounds) (inches)
2 20 50 to 110 8 to 10 30 22 to 55 6 to 8 40 2 to 22 3 to 6 10 0 to 2 0 to 3
Riprap is to be placed to its full depth by manual methods to obtain a compact uniformly thick blanket with a reasonably smooth surface.
PNF-SPS-301
Section 301 – UNTREATED AGGREGATE COURSES
301.03 General
Delete the last two sentences.
301.04 Mixing and Spreading.
Delete the first paragraph and replace with the following:
Adjust moisture content of the aggregate as needed to obtain a moisture level adequate for compaction.
301.05 Compacting.
Delete the first and third paragraphs and add the following:
Compact the aggregate using one of the following methods as specified:
Method A.
Compact each layer by operating spreading and hauling equipment over the full width of each layer of aggregate.
Method B.
Process the pit run aggregate by utilizing a bulldozer, D-6 or larger. Obtain compaction by walking the dozer over the full width of each layer of aggregate a minimum of three times. If a roller is used to obtain compaction, use a roller specifically designed to break down rocky material and the following requirements, unless otherwise approved by the Contracting Officer:
1. Sheepsfoot, tamping or grid rollers shall be capable of exerting a force of 3000 lb/ft of width of roller drum.
2. Vibratory steel-wheel rollers shall have a minimum weight of 5 Tons. The compactor shall be equipped with amplitude and frequency controls.
PNF-SPS-303
Section 303 – ROAD RECONDITIONING
303.03 Ditch Reconditioning.
Delete and replace with the following:
Remove all slide material, rocks and debris from existing ditches and culvert inlets and outlets. Leave vegetation in ditch if it does not interfere with the flow of the ditch.
303.04 Shoulder Reconditioning.
Delete and replace with the following:
Repair as needed for berm removal, drainage, safety and smooth alignment.
303.05 Roadbed Reconditioning.
Delete and replace with the following:
Blade roadbed only as needed to remove slide material, rocks, debris, and surface irregularities such as wheel ruts, waterbars, slumps, etc. Leave vegetation in place if the template is smooth and in good condition. Maintain existing drainage patterns, such as driveable dips, as much as possible. Adjust the moisture content of the material as needed to obtain compaction. (Water is incidental to Road Reconditioning). Compact the roadbed according to Subsection 301.05.
303.06 Aggregate Surface Reconditioning.
Delete
303.08 Pulverizing.
Delete
303.09 Acceptance
Delete and replace with the following:
Acceptance for road reconditioning work is based on visual inspection of the work for compliance with the contract.
PNF-SPS- 322
Section 322 – CRUSHED AGGREGATE
322.01 This work consists of furnishing and placing crushed aggregate for roadway aggregate course. Crush the aggregate at the Moonshine Pit No. 121-0070-S located in the NE ¼ Sec. 23, T 18 N, R 3 W.
The roadway aggregate compaction method is designated as shown in Subsection 322.05.
Roadway aggregate grading is designated as shown in Table 703-02.
322.02 Conform to the following Subsections:
Crushed Aggregate Table 703-02 and 703.05
322.03 Preparing Surface. Prepare the surface on which the aggregate course is to be placed according to Section 303.07.
Roadbed shall be approved in writing by the CO before placing base of surface course.
Prior to placing gravel, the Contractor shall mark outside edges of proposed gravel placement for approval by the Contracting Officer.
Install screens on the intake of pumps for the water truck with a maximum opening of 3/32 inch. This is in order to protect aquatic organisms.
322.04 Placing Crushed Aggregate. Mix the aggregate and adjust the moisture content suitable for compaction. Spread and shape the mixture on the prepared surface in a uniform layer.
Do not place the mixture in a layer exceeding 6 inches in compacted thickness. When more than one layer is necessary, compact each layer according to Subsection 322.05 before placing the next layer.
November 2009
322.05 Compacting Crushed Aggregate. Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road.
Roadway aggregate. Compact the aggregate using one of the following methods:
(1) Method 1. Moisten or dry the aggregate to a uniform moisture content suitable for compaction. Operate a vibratory steel-wheeled roller having a minimum weight of 5 ton, equipped with amplitude and frequency controls, over the full width of each layer until visual displacement ceases, making not fewer than three complete passes.
(2) Method 2. Compact each layer of aggregate to a density of at least 95 percent of the maximum density, as determined by ASSTO T99, method C or D.
Blade the surface of each layer during the compaction operations to remove irregularites and produce a smooth and even surface.
322.06 Acceptance. See Table 703-02 for gradation requirements and Table 322-2 for sampling and testing requirements, and Figure 322-1 for responsibility for process control, quantity and quality assurance.
Crushed aggregate will be evaluated under Subsection 106.02 and 106.03. Furnish a certification including gradation and quality properties for each source.
Preparation of the surfaces on which crushed aggregate is placed will be evaluated under Section 303.
Figure 322-1: Quality, Quantity and Payment Process
‘X’ denotes primary responsibility for indicated task
Contracto r
FS Quality &
Tasks Frequency Process Quantity Control Assurance
Aggregate Quality Sampling and Testing During As Desired by Contractor x Initial Tests
Crushing Results Checked Acceptance sampling for During placement on x Sampling gradation Road surface Checked Acceptance for Plasticity During Crushing x Sampling
Index Checked Perform test on acceptance As samples become ~ x samples available Calculate pay factor on As test results become ~ x
Acceptance samples available Aggregate Quantity
Measurements of aggregate After compaction on each x Measurements Thickness and width Road segment is completed Checked
Determination of final After measurements on all ~ x Payment quantity segment are completed
Aggregate Payment As Pay Factor and Quantity Data Become Available
~ x
Measurement
322.07 Measure the Section 322 items listed in the bid schedule according to Subsection
109.02 and the following as applicable.
Measurement for aggregate is by cubic yard using contract quantities, measured by cubic yard in-place once compacted.
Measure thickness perpendicular to the grade of the travelway.
Measure width perpendicular to the centerline.
Table 322-2 Sampling and Testing Requirements
Material Type of Test Sampling Point of Split Reporting or Acceptance Characteristic Category Methods Frequency Sampling Sample Time Product (Subsection) Specificat-ions
Aggregate Measured Source And tested L.A abrasion - AASHTO 1 per type Source of Yes, Before Quality For conform- (coarse) T96 & source material using
703.05 ance of material in work
(106.04 106.05) Sodium sulfate - AASHTO “ “ “ “ soundness loss T 104 (coarse & fine)
Durability - AASHTO “ “ “ “ Index T 210 (coarse & fine)
Fractured - AASHTO “ “ “ “ faces D 5821
Plasticity - AASHTO “ “ index T 90
Gradation - AASHTO Contractor Contractor Contractor T 27 & Process Process Process T11 Control Control: Control:
Tests: Crusher 48 hours 1 per 1000 Acceptance:
Tons or From Acceptance less Roadbed Samples:
20 per After 72 hours project Process-ing
Surface Measured & Width - - 4 per each Roadbed - 4 hours Tested for 0.5 mile For Conformance compaction (106.04) Thickness - - “ “ - “
Payment
322.08 The accepted quantities will be paid at the contract price per unit of measurement For the Section 322 pay item listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
PNF-SPS-576
Section 576 – PRECAST BOX CULVERT
OLING RANCH ROAD NO. 50511
576.01 This work consists of designing, fabricating, and installing precast concrete box culvert sections and precast footings AS SHOWN ON THE DRAWINGS. The precast concrete sections shall be contractor designed “AMCOR” units as detailed on the drawings, or approved equal. Alternate design may be submitted for approval (see section 576.03 below). The work also includes steel connection plates for deck joints, grout for joints, shop drawings, and other incidentals as required.
Materials
576.02 Requirements. Furnish materials that meet the requirements specified in the following sections:
Concrete compressive strength, structural steel tensile strength, concrete finish and designation, and other material specifications shall be as required or if not listed in the contract documents, take them from the manufacture’s drawings, and have them approved by the Contracting Officer prior to fabrication. Maintain adequate records of all inspections and tests.
576.03 Design requirements. For required loadings use the most recent AASHTO “Standard Specifications for Highway Bridges”>
Submit plans and calculations signed and stamped by a professional engineer registered in the state of Idaho.
Design requirements are:
Vehicle design loads: HS20-44
Soil Pressure: Allowable= 4,000 pounds per square foot.
Internal friction – 36 degrees
Lateral Earth Pressure passive = 45 pounds per square foot
Cover: There will be 6 inches of Pit Run Aggregate on the top of the structure.
Deck weldment and deck joint to be designed by contractor for a lateral distribution of a 16,000 wheel load.
All exposed corners shall have a ¾ inch chamfer.
Individual segments shall not weigh more than 20,000 pounds, or the maximum weight that the contractor determines he can set.
The structure shall be designed so it will fit together on a slope not to exceed 2% in the stream channel.
Rig precast concrete box culvert and precast footings with permanent lifting devices to facilitate efficient installation and removal of these items. Place lifting devices so as not to interfere with traffic when culvert is installed as a road crossing over a stream.
576.04 Design Calculations and Drawings. Submit design drawings (24 inches by 36 inches), calculations, or shop drawings at least 7 days in advance of the start of fabrication to allow time for review and correction of any changes and approval by the Engineering Representative (ER). Include plan, elevation, and section views of the box culvert and footings, dimensions of all components, welding and connection details, and general and specific notes regarding design and construction.
576.05 General. Perform excavation, backfill, and embankment work under Sections 204, 208, 209, and 301.
576.06 Performance. Notify the Engineering Representative (ER) at least 7 days before delivering the concrete box culvert sections and footings.
576.07 Measure the Section 576 items listed in the bid schedule according to Subsection 109.02.
576.08 The accepted quantities, measured as provided in Subsection 109.02 and above, will be paid at the contract price per unit of measurement for the Section 576 pay items.
Payment will be full compensation for the work prescribed in this Section.
April 2009
PNF-SPS-602
Section 602 – CULVERTS AND DRAINS
602.03 General
Delete the last sentence and add the following:
Compaction Method D. Construct the width of trenches in natural ground to permit satisfactory joining of the culvert sections and thorough tamping of the bedding material under and around the culvert. Excavate trenches to a minimum width equal to the culvert diameter plus 2 feet.
Excavate unstable material below grade line and replace with suitable material. Ensure that the foundation material is at a moisture level that is suitable for compaction.
Compact foundation material using compaction equipment designed for this purpose until visual displacement ceases. Cover the foundation with a blanket of loose material to a depth sufficient to allow the corrugations to become filled with material.
Place backfill in horizontal layers that do not exceed 6 inches. Ensure the backfill material is at a moisture level that is suitable for compaction. Do not use rocks larger than 3 inches with 12 inches of the pipe. Compact each layer using compaction equipment designed for this purpose until visual displacement ceases.
Bring backfill up evenly on all sides. Continue backfilling and compacting until backfill is equal to the road grade elevation.
Culvert pipe furnished by the Government shall be located at the Council Ranger District Council, Idaho. Culvert is located in the parking area for the Council warehouse.
602.08 Acceptance
Delete the words “and 106.04” from the second paragraph.
Delete the third paragraph.
JUNE 2009
PNF-SPS-619
Section 619 – FENCES, GATES, AND CATTLEGUARDS
619.07 Cattle Guards
(B) Concrete foundation.
Delete in its entirety and add the following:
Cattle guard foundation shall be precast concrete and shall meet or exceed BIG “R” MANUFACTURING requirements.
JUNE 2009
PNF-SPS-625
Section 625 – TURF ESTABLISHMENT
625.02
Hydro-mulch shall contain a colored dye that is non-injurious to plant growth and that fade rapidly with exposure to light.
Fertilizer shall be time release having a N:P:K ratio of 1:1:1 (or approved substitute).
Duration of release shall be at least 2 months. Application equipment shall be according to manufacturers recommended method.
Table 625-1 Species #/ Acre Fertilizer Smooth Brome Grass 9 Orchard Grass 3 Yes* Pubescent Wheat 10 Yellow Sweet Clover 0.5 ---- *shall be applied at
20.5 a rate of 28# of elemental Nitrogen per Acre.
625.03 Seeding Seasons
Apply seed to finished slope and ditches between May and November. All newly constructed or disturbed areas shall be treated prior to the end of each field season unless directed otherwise. Do not apply seed during windy weather or when the weather is excessively wet, or ground is frozen, snow covered, or extremely dry.
625.07 Seeding
(a) Dry Method.
Remove the last sentence “Lightly compact the seedbed with 24 hours after seeding.”
PNF-SPS-625 (Continued)
625.08 Mulching
(a) Dry Method. Spread all mulch material, except wood and grass cellulose fibers, by a mulch spreader using forced air to blow the mulch onto the seeded area.
Apply the straw or wood cellulose mulch at a rate of 2000 #/acre.
(b) Hydraulic Method. Mix the seed or seed and fertilizer with water in the amounts and mixture shown above. When wood cellulose or straw mulch are to be incorporated as an integral part of the slurry mix, add them after all other materials have been thoroughly mixed in the tank
625.11
Delete and replace with the following:
Seeding and mulching acreage shall not be measured. Design quantities as shown on the plans shall be considered the contract acreage amounts.
April 2009
PNF-SPS-648
Section 648 – STREAM SIMULATION
648.01 This work consists of placing rock and fill to simulate natural stream profile and streambed through culverts and other structures.
Obtain rocks that meet the gradation requirements for Stream Simulation rock from the following sources:
1)Salvage from the material excavated for the structure. The contractor shall replace the volume of material that is used with an equal volume of embankment material from off the site, at no additional cost to the Government.
2) The borrow source for simulation material AS SHOWN ON THE PLANS (Page 8 of 46).
3) Moonshine Pit No. 121-0070-S if approved by the Engineering Representative (ER).
648.02 Conform to the following Subsections.
Stream Bed Simulation Rock 705.08 Channel Rock 705.07
648.03 General Place stream simulation rock on a prepared surface to form a well-graded, low permeability mass, similar in appearance and texture to the natural streambed.
The placement of stream simulation rock and channel rock shall be done when the channel is dewatered. Before the stream is diverted back into the new channel, wash the new channel, and collect the sediments (if any) and remove the sediments from the channel via the use of SEDIMAT or approved equal.
All stream simulation material and channel rock shall be in place and the channel approved by the Engineering Representative (ER) prior to the introduction of the stream.
648.04 Placed Stream Simulation Rock and Fish Rest Stops.
a) Method A, Machine Placed. Place stream simulation rock in one or more layers with a layer depth less than 1 ½ times the maximum dimension of the stream simulation rock. Place stream simulation bedrock by methods that do not cause segregation or damage to the prepared surface. Place or rearrange individual rocks by mechanical methods to obtain a compact low permeability mass matching stream simulation bed details. Fill voids with foundation fill before placing the next lift. Place fish rest stop rock as designated.
b) Method B, End Dumped. Dump stream simulation rock in one or more layers with a layer depth less than 1 ½ times the maximum dimension of the stream simulation rock. Distribute larger rocks throughout the mass of stone. Obtain a uniformly dense, compact, low permeability bed with a surface matching stream simulation bed details.
Fill voids before placing next lift. Place fish stop rock as designated.
c) Method C, Hand Placed. Place stream simulation rock using hand labor.
Material may be hand carried, or carried in wheelbarrows and end dumped to obtain its full thickness. Compact each load using hand operated mechanical equipment to obtain uniformly dense, compact, low permeability bed with a surface matching stream simulation bed details. Fill voids before placing the next lift. Place fish rest stop rock as designated.
648.04 Foundation Fill. Fill all voids left during placement of Stream Bed Simulation Rock with fines. The fines shall be well-graded compactable material free of muck, frozen lumps, roots, sod or other deleterious material. Use water pressure, metal tamping rods, and similar hand operated equipment to force material into all surface and subsurface voids between the structure and individual rocks. The purpose of filling the voids with fines is to create a streambed that will be non-porous enough to keep water flowing on the top surface, even at low flows.
648.05 Acceptance. Placing stream simulation material will be evaluated under Subsections 106.02 and 106.04.
648.06 Measure the items listed in the schedule according to Subsecion 109.02
648.07 The accepted quantities, measured as provided in Subsection 109.02, will be paid at the contract unit price per unit of measurement for Section 648 pay items listed in the schedule. Payment will be full compensation for the work prescribed in this Section.
PNF- SPS- 651
Section 651 –Development of Pits and Quarries
651.00_0402_us_01_10_2007
651.01 This work consists of clearing, grubbing, stripping topsoil, removing overburden, constructing access roads, conducting restoration activities, and performing other incidental work required for pit or quarry development. The existing government pit shall be developed within the existing plan footprint.
651.02 General. Submit a plan of operations according to Section 105. Perform all work in accordance with Sections 105, 201, 203, 204, 625, and 635, landscape preservation requirements, and the approved pit and quarry development plan of operations. Perform the work in accordance with MSHA 30 CFR, part 56.
651.03 Acceptance. Developing pits and quarries will be evaluated under Subsections
106.02 and 106.04.
651.04 Restoration. After excavation has been completed in part or all of the area, slope and grade the sides to 1.33 V : 1 H or flatter, and smooth the general pit area.
651.05 Pit Development is considered a subsidiary item to Sections 204, 251, 252, 253, 301, 302, 321, or 322. No separate payment will be made under this Section or Sections 204, 251, 252, 253, 301, 321, ,322, or 409.
PNF- SPS- 703
Section 703 - Aggregate
Delete 703.05 and replace with the following:
703.05 Subbase, Base, Surface Course, and Screened Aggregate.
(a) Subbase or base aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation Table 703-2
(2) Liquid limit, AASHTO T 89 25 max.
(3) Plastic limit, AASHTO T 90 Nonplastic
(4) Los Angeles abrasion, AASHTO T 96 40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210 35 min.
(7) Durability index (fine), AASHTO T 210 35 min.
(8) Fractured faces, ASTM D 5821 50% min.
(9) Free from organic matter and lumps or balls of clay
Do not use material that breaks up when alternately frozen and thawed or wetted and dried.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary.
Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(b) Surface course aggregate. Furnish hard, durable particles or fragments of crushed stone, crushed slag, or crushed gravel conforming the following:
(1) Gradation Table 703-3
(2) Liquid limit, AASHTO T 89 35 max.
(3) Plastic Index, AASHTO T 90
a) If the percent passing the No. 200 sieve is less than 12% 2 to 9
b) If the percent passing the No. 200 sieve is greater than 12% Less than 2
(4) Los Angeles abrasion, AASHTO T 96 40% max.
(5) Sodium sulfate soundness loss (5 cycles), 12% max.
AASHTO T 104
(6) Durability index (coarse), AASHTO T 210 35 min.
(7) Durability index (fine), AASHTO T 210 35 min.
(8) Fractured faces, ASTM D 5821 75% min.
(9) Free from organic matter and lumps or balls of clay
Do not furnish material that contains asbestos fibers.
PNF-SPS-703 (continued)
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary.
Fine aggregate, material passing the No. 4 sieve, shall consist of natural or crushed sand and fine mineral particles.
(c) Screened aggregate – Furnish hard, durable particles or fragments of stone, slag, or gravel conforming the following:
(1) Gradtion Table 703-16
(2) Plastic Index, AASHTO T 90 Less than 9
(3) Los Angeles abrasion, AASHTO T 96 55% max.
(4) Free from organic matter and lumps or balls of clay.
Obtain the aggregate gradation by crushing, screening, and blending processes as necessary.
PNF-SPS-705
Section 705-ROCK
705.07 CHANNEL ROCK
Add the following
Table 705-4 Gradation requirement for channel rock
Rock Class
Mass (Pounds) Approximate Cubic Dimension (inches)
1 2-6 4-5.5 2 7-22 6-8 3 33-77 9-12 4 77-175 12-16 5 175-440 16-21.25 6 350-880 20-26.75 7 620-1540 24-32 8 1210-2880 30-40 9 2112-5060 36-48 10 3300-8160 42-56.25
705.08 Stream Bed Simulation Rock.
Table 705-5 – Gradation requirements for streambed simulation rock, inches or sieve size
Bed Class
100% passing
84% passing
50% passing
16% passing
10% passing
50 5 2 ¾ ¼ No. 10 100 10 4 1 ¾ 0.530 No. 10 150 14 6 2 ½ ¾ No. 10 225 22 9 3 ½ 1.06 No. 10 300 29.5 12 5 1 ½ No. 10 375 35.5 14 6 1 ¾ No. 10 450 45 16.5 7 2 ½ No. 10 600 59 23.5 10 3 No. 10 750 74 29.5 12 3 ½ No. 10 900 88.5 35.5 14 4.24 No. 10 1050 103 45 16.5 5 No. 10