RECOVERY - Groundhog and Morrison Trail Bridge Replacements - San Juan NF
Solicitation number
AG-82B1-S-10-0085
Issued by

About this file

QUESTIONS AND ANSWERS - AMEND 4

View the file

Other files

File Type Posted
SF AMEND 2.PDF PDF
SF 30 AMEND 4.PDF PDF
Morrison Trail 3.jpg JPG image
Morrison Trail 1.jpg JPG image
SF 30 AMEND 3.pdf PDF
Groundhog Trail 2.jpg JPG image
Groundhog Trail 3.jpg JPG image
Groundhog Trail.jpg JPG image
Morrison Trail 2.jpg JPG image
SF 30 AMEND 1.COM.pdf PDF
Wage determination.txt TXT text file
Groundhog.MAPS.pdf PDF
AG-82B1-S-10-0085.pdf PDF
Groundhog.SPECS.pdf PDF
Groundhog.trails_bridge_dm.pdf PDF
OF 336.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Morrison and Groundhog Bridge Q & A's
Question:Reply:
Are there any photos of the current bridges?Yes, photos are available from the last bridge inspections.
Are helicopters needed for this project.Helicopter use is not anticipated for this project.
Is there a designated wood source for this project.No.
Can a fiberglass bridge be installed instead of the bridge as shown on the plans.A new design or new material will need to be designed and stamped by a Colorado registered professional engineer. If an alternate design is proposed it will need to meet all characteristics of the Agency design and will be subject to meeting visual resource criteria. There is no guarantee that even if a new bridge is designed to applicable engineering standards, it may not meet the standards set forth for visual resource quality.
Can an alternate steel truss be used.If an alternate truss is proposed, the truss will need to be designed by a Colorado registered professional engineer. The design will need to show the truss and supporting calculations for dead load deflection, live load deflection, and wind load deflection. The design will also show connection details and wooden member connection details.
The 7'-4" steel rod that is shown on page 3 of the plans in cross section view, how many steel rods are to be installed.A steel rod will be installed at every up right handrail post.
Can ATV's get to the bridge sites.ATV's will be allowed to the sites. The trails leading to the sites are not normally open to motorized vehicles, but they will be allowed for construction of these bridges. The trail to the Groundhog bridge is on fairly flat terrain. The trail to the Morrison bridge is a more technical and difficult trail.
Can larger equipment such as bobcats and pickups get to the site.While they could probably get to the sites, they will NOT be allowed at the sites. No equipment larger than an ATV will be allowed at the site.
What material are the current bridges made of?The current bridges are both nail/glue laminated wooden structures, supported on either end with concrete abutments.
Can the current bridges be sawn and burned at the sites.No, they must be removed from the site as shown on the plans, and stated in the specifications.
Do you have GPS coordinates of the bridges?No, the legal description of the bridges is shown both on the plans and written in the specifications.
How far from Forest Service roads are these bridges.The Groundhog bridge is approximately 0.3 miles from the trailhead, and the Morrison bridge is approximately 0.5 miles from the trailhead.
Does the lumber need to be cut to size and holes drilled prior to assembly.The plans state on page 3, lumber shall be cut to size and pre-drilled prior to treatment.
When is the anticipated start date of this project.Snow will generally be gone from the sites around the first week in June. June 1 will be the desired start date.
How long will it take to assemble the bridges at the site.Past bridges have ranged from 3 days to more than 6 weeks, it is contractor dependant.
Is the Groundhog bridge in the Lizard Head wilderness?No, the bridge is not within the wilderness boundaries.
Why on Page 3 of the Solicitation, Offer and Award, Optional Form 336 does it say delivery by September 30, 2013This date is wrong. These bridges will be built in Early 2010, as soon as the ground conditions permit.
Will the measurements need to be verified prior to ordering the trusses.Yes, the contractor is responsible for verifying measurements prior to ordering materials.
Can lumber be drilled and cut on site?The plans and specifications state the lumber will be cut and drilled prior to treatment of the lumber.