A-5 Bid Bond clause.doc
DOC document 24 KB Posted
- Solicitation number
- AG-82B1-S-10-0051
About this file
Attachment to Amendment No. 5 Bid Bond clause
View the file
Other files
| File | Type | Posted |
|---|---|---|
| a-5 S-10-0051.doc | DOC document | |
| A-4 S10-0051.pdf | ||
| A-3 S10-0051.pdf | ||
| A-2 10-0051.pdf | ||
| A-1 S-10-0051.pdf | ||
| Attachment Clause 52.214-26 .docx | DOCX document | |
| 10-0051 Beaver Cr 4 of 5.pdf | ||
| FH 10-0051 2 of 4.pdf | ||
| FP 03 10-0051.docx | DOCX document | |
| Constr.Wage Determination Montana.pdf | ||
| Sect B thru L 10-0051 Beaver Creek.doc | DOC document | |
| FH 10-0051 3 of 4.pdf | ||
| 3 of 5 10-0051.pdf | ||
| BC 10-0051 2 of 5.pdf | ||
| FH 10-0051 4 of 4.pdf | ||
| BC 0 10-0051 1 of 5.pdf | ||
| FH 10-0051 1 of 4.pdf | ||
| 10-0051 COVER PAGE.pdf | ||
| BC 5 of 5 10-0051.pdf |
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
52.228-1 Bid Guarantee.
BID GUARANTEE (SEPT 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier’s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be _20_ percent of the bid price or $_100,000.00_, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of provision) 52.211-10 Commencement, Prosecution, and Completion of Work
COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within _10_ calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than _30 September 2010. The time stated for completion shall include final cleanup of the premises.
(End of clause)