A13_Q&A_12.27.2016.pdf
PDF 32 KB Posted
- Solicitation number
- AG-82A7-S-17-0004
About this file
12/27/2016: Please see the revised Q&A doc for a new question submitted and the answer.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A13_AG-82A7-S-17-0004_000002.pdf | ||
| A13_0Attch3_DBA_Wage_Dec._11.11.16.pdf | ||
| A13_0AG-82A7-S-17-0004_00001.pdf | ||
| A13_Q A_11.14.2016.pdf | ||
| A12_AG-82A7-S-17-0004.pdf | ||
| A12_Attch3_DBA_Wage_Dec..pdf | ||
| A12_Attch4_Proposal_Subm._Pkg..docx | DOCX document | |
| A12_Attch1_Specs_Dining Career.pdf | ||
| A12_Attch2_Drawings_Dining Career.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AG-82A7-S-17-0004
RFP Q&A Doc for Blackwell HVAC Project
QUESTIONS & ANSWERS REGARDING:
SOLICITATION/REQUEST FOR PROPOSALS NO. AG-82A7-S-17-0004
for Dining/Career Prep HVAC Modification
Blackwell Job Corps Civilian Conservation Center
QUESTIONS RECEIVED AS OF 12/27/2016:
1. This project will require a fair amount of carpentry and finish work. I am unable to find a suitable subcontractor willing to work this project. Is it possible to eliminate the white sheet requirements on the project? Do you have any suggestions?
ANSWER: The Government will not amend the solicitation to remove project requirements. That said, offerors in this type of situation may consider two alternatives:
1) Offerors may propose an alternative method of completing the required work. That is, if there is some other way you could meet the requirement, but it would require a change to drawings and/or specifications, propose it and price for the alternative method.
2) If there is no alternative, submit a proposal for the rest of the project.
For either alternative, such proposals shall clearly identify why the acceptance of the proposal would be advantageous to the Government. Any deviations from the terms and conditions of the solicitation, as well as any advantage to the Government, shall be clearly identified and explicitly defined. The Government reserves the right to amend the solicitation after the closing date to allow all offerors who submitted proposals an opportunity to submit revised proposals based on any revised requirements.
QUESTIONS RECEIVED AS OF 11/14/2016:
2. Regarding the Instrumentation and Control for HVAC section (spec section 23 09 00) under the products section of this specification, it reads basis of design by Honeywell Spyder LonWorks with a note that comparable products may be provided. Are we allowed to submit a proposal using a different manufacturer’s controls?
ANSWER: Yes, as long as the proposed equipment performs the sequence of operations specified and meets all specification requirements.