Attachment_1_Specs_and_Dwgs.pdf

PDF 9 MB Posted

Attached to
Sewage Lift Station Improvements
Solicitation number
AG-82A7-S-16-0062
Issued by

About this file

Attachment 1 Plans and Specs

View the file

Other files

File Type Posted
Amendment_0001.pdf PDF
Attachment_2_-_DBA_Wages.pdf PDF
AG-82A7-S-16-0062.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TABLE OF CONTENTS

ANACONDA JOB CORPS CENTER

SEWAGE LIFT STATION IMPROVEMENTS

Table of Contents – Page 1 of 2 M:\0916\071 - USFS 5 Year Contract\20 - AJCC Lift Station\Documents\Design\Specs\TOC.docx April 19, 2016

All front end documentation provided by the USFS

DIVISION 1 - GENERAL REQUIREMENTS

SECTION 01010 Summary of Work SECTION 01040 Coordination and Site Conditions SECTION 01092 Abbreviations and Reference Standards SECTION 01300 Submittals SECTION 01400 Quality Control SECTION 01500 Construction Facilities and Temporary Controls SECTION 01560 Environmental Quality Control SECTION 01600 Product Shipment, Handling, Storage, and Protection SECTION 01640 Manufacturers’ Services SECTION 01700 Contract Closeout SECTION 01720 Record Drawings

DIVISION 2 - SITEWORK

SECTION 02015 Move in and Site Preparation SECTION 02020 Demolition and Salvage SECTION 02220 Earthwork for Structures SECTION 02221 Trench Excavation & Backfill For Pipelines & Appurtenant

Structures* SECTION 02235 Crushed Base Course* SECTION 02480 Finish Grading, Seeding, and Landscaping SECTION 02500 Precast Concrete Structures

DIVISION 3 – CONCRETE

SECTION 03210 Reinforcing Steel* SECTION 03310 Structural Concrete*

DIVISION 5 - METALS

SECTION 05500 Miscellaneous Metal Items

DIVISION 7 – THERMAL AND MOISTURE PROTECTION

SECTION 07121 Cold Fluid Applied Waterproofing

DIVISION 10 – SPECIALTIES

SECTION 10400 Identifying Devices

DIVISION 11 – EQUIPMENT

SECTION 11005 Miscellaneous Equipment SECTION 11300 Submersible Grinder Pumps and Accessories

TABLE OF CONTENTS

ANACONDA JOB CORPS CENTER

Table of Contents – Page 2 of 2 M:\0916\071 - USFS 5 Year Contract\20 - AJCC Lift Station\Documents\Design\Specs\TOC.docx April 19, 2016

DIVISION 15 – MECHANICAL

SECTION 15000 Piping Schedule SECTION 15001 Piping - General SECTION 15001A DPS: Cement Lined Ductile Iron Pipe and Fittings SECTION 15001H DPS: Polyvinyl Chloride (PVC) Pipe and Fittings SECTION 15080 Manual Valves

DIVISION 16 - ELECTRICAL

SECTION 16045 Basic Electrical Requirements SECTION 16050 Basic Material and Methods SECTION 16051 Common Work Results for Electrical SECTION 16060 Grounding and Bonding SECTION 16073 Hangers and Supports for Electrical Systems SECTION 16075 Electrical Identification SECTION 16120 Conductors and Cables SECTION 16130 Raceways, Boxes, and Underground Utility Structures SECTION 16410 Enclosed Switches and Circuit Breakers SECTION 16442 Panelboards SECTION 16491 Fuses

* Montana Public Works Standard Specifications incorporated by reference and modified in these specifications.

DRAWINGS

12 SHEET DRAWING SET

END OF TABLE OF CONTENTS

SECTION 01010

DIVISION 1 – GENERAL REQUIREMENTS SUMMARY OF WORK

01010 – Page 1 of 4 M:\0916\071 - USFS 5 Year Contract\20 - AJCC Lift Station\Documents\Design\Specs\Technical\01010.doc April 19, 2016

PART 1 GENERAL

1.01 GENERAL

A. This section describes the project and the work to be performed under this Contract in a general summary. Detailed requirements and extent of work are stated in applicable Specification sections and are shown on the Drawings.

1.02 ORGANIZATION AND INTERPRETATION OF CONTRACT DOCUMENTS

A. Specifications and Drawings included in these Contract Documents establish the performance, quality requirements, location and general arrangement of materials and equipment, and establish the minimum standards for quality of workmanship and appearance.

B. Specification sections have not been divided into groups for work of subcontractors or various trades. Should there be questions concerning the applicability or interpretation of a particular section or part of a section or Drawing, direct questions to the Contracting Officer.

C. Piping shown on the Drawings is intended to be depictive and may not be an exact and complete representation of the actual finished work. Include fittings, joints, supports, nuts, bolts, and other accessories required to provide complete and satisfactory piping systems, as specified even though some items may not be specifically shown on the Drawings.

D. Any part of the work that is necessary or required to make each installation satisfactory and operable for its intended purpose, even though it is not specifically included in the Specifications or on the Drawings, shall be performed as incidental work as if it were described in the Specifications and shown on the Drawings.

1.03 STANDARD SPECIFICATIONS

A. The Montana Public Works Standard Specifications, Sixth Edition, April 2010, are referred to elsewhere in this document as the MPW Standard Specifications or MPWSS. Copies of the MPW Standard Specifications are available from:

Associated General Contractors of America Montana Contractors Association, Inc.

1717 11th Avenue P.O. Box 4519 Helena, Montana 59604

B. Where a specification section from the MPW Standard Specifications is referenced, it shall be understood that the section is thereby made a part

01010 – Page 2 of 4

April 19, 2016 of these Contract Documents even though the section is not printed in this Project Manual. Special provisions that supplement or supercede referenced MPW Standard Specifications sections are included within this Project Manual and take precedence over any conflicts with the MPW Standard Specifications.

1.04 WORK BY OTHERS

A. Normal wastewater system operations by Owner’s personnel. Also see Section 01040, COORDINATION AND SITE CONDITIONS.

1.05 DESCRIPTION OF PROJECT

A The Contractor shall, except as otherwise specifically stated in applicable parts of these Contract Documents, provide and pay for all labor, materials, equipment, tools, equipment, facilities, and services necessary for proper execution, testing, and completion of the work.

B. This project consists of the following items of work:

1. Anaconda Job Corp Center – Sewage Lift Station Improvements:

The work generally consists of, but is not necessarily limited to, the following major items:

• Installation of a new lift station and accessories including a

5-foot diameter wet well, submersible grinder pumps, valves, piping, a flow meter, ancillary controls equipment, and appurtences;

• Tie in to existing force main and influent line;

• Replacement of electrical disconnects and panels;

• Demolition and removal of the existing equipment within the wet well and lift station building, the wet well penetrations, and ancillary control equipment;

• Construction and modification of HVAC equipment for electrical room suitability.

1.06 LOCATION AND INSPECTION OF SITE

A. The work shall occur in the areas as shown on the Drawings which are within the Anaconda Job Corp Center.

B. Inquiries concerning the Specifications and Drawings may be made to the Contracting Officer.

1.07 TIME FOR COMPLETION AND LIQUIDATED DAMAGES

A. Following the notice to proceed, the contractor shall have 30 calendar

01010 – Page 3 of 4

April 19, 2016 days to complete the project.

1.08 ENGINEERING SERVICES

A. Benchmarks for horizontal and vertical control have not been established.

Existing facilities are located with respect to record drawing information.

The Contractor shall be responsible to provide all other horizontal and vertical control to complete the work.

C. The Contracting Officer may perform independent and separate compaction density tests, concrete sampling and testing, or other testing as the Contracting Officer may decide.

1.09 BOUNDARIES OF WORK

A. The Owner shall make suitable provisions for ingress and egress, and the Owner shall not cause the Contractor to enter or occupy with workers, tools, equipment or material, any ground outside the property of the Owner without the written consent of the owner of such ground. The final location and extent of the areas to be used shall be coordinated with the Contracting Officer. Other contractors and employees or agents of the Owner may for all necessary purposes enter upon the premise used by the Contractor, providing the operations of other contractors do not interfere with the actual scheduled operations. The Contractor shall conduct his work so as not to impede unnecessarily any work being done by others on or adjacent to the site.

B. It shall be understood that the responsibility for protection and safekeeping of equipment and materials on or near the site will be entirely that of the Contractor and that no claim shall be made against the Owner or the Contracting Officer by reason of any act of an employee or trespasser. It shall be further understood that should any occasion arise necessitating access by the Owner to the sites occupied by these stored materials and equipment, the Contractor owning or responsible for the stored materials or equipment shall immediately remove same. No materials or equipment may be placed upon the property of the Owner until the Contracting Officer has agreed to the location contemplated by the Contractor to be used for storage.

C. The Contractor shall be solely responsible for obtaining and shall pay all costs in connection with any additional work area, storage sites, access to the site, or temporary right-of-way, which may be required for proper completion of the work.

1.10 PROTECTION OF SITE

A. Excepting as otherwise provided herein, the Contractor shall take all necessary precautions and provide all material and equipment to protect, 01010 – Page 4 of 4

April 19, 2016 shore, brace, support and maintain all public and private property in the proximity or otherwise affected by the construction work performed by him.

The Contractor shall remove from the site all unused materials.

B. Also see Section 01040, COORDINATION AND SITE CONDITIONS.

1.11 TEMPORARY FACILITIES

A. The Contractor shall be responsible for supplying his own office and storage facilities at the site, if necessary. The Contractor shall supply a port-o-potty and potable water for it’s employees. Requests for water needed for construction and testing purposes must be coordinated with the Contracting Officer. The Contractor shall remove all traces of these facilities prior to completion of the project.

B. Also see Section 01500, CONSTRUCTION FACILITIES AND

TEMPORARY CONTROLS.

1.12 SITE ACCESS

A. The Contractor shall be responsible for determining the adequacy of all roads and bridges used in moving equipment and materials to the construction site. The Contractor shall provide alternative methods of access, such as temporary crossings, for any equipment that exceeds the capacity of existing access facilities.

1.13 SAFETY

A. The Contractor shall be solely responsible for all project personnel on the jobsite. No acts or comments by the Contracting Officer or Owner shall be interpreted as a transfer of responsibility for safety.

PART 2 PRODUCTS (Not Used)

END OF SECTION 01010

SECTION 01040

COORDINATION AND

DIVISION 1 - GENERAL REQUIREMENTS SITE CONDITIONS

01040 – Page 1 of 17 M:\0916\071 - USFS 5 Year Contract\20 - AJCC Lift Station\Documents\Design\Specs\Technical\01040.doc April 19, 2016

PART 1 GENERAL

1.01 1.01 SECTION INCLUDES

A. Requirements for coordinating and sequencing the work under the Contract, and requirements regarding existing site conditions.

B. Requirements for cutting and patching of new and existing work.

1.02 JOBSITE COORDINATION

A. Project Coordination: All project coordination (i.e. equipment staging, traffic control, wastewater collection system operation) should be discussed with the Contracting Officer.

B. Owner may perform additional work related to this project himself, or he may let other direct contracts therefore, which shall contain General Conditions and General Requirements similar to these. Contractor shall afford the other Contractors who are parties to such direct contracts, (or Owner if he is performing the additional work himself), reasonable opportunity for the introduction and storage of materials and equipment and execution of work, and shall properly coordinate his work with theirs.

C. If any part of Contractor's work depends on proper execution or results from the work of any such other Contractor (or Owner), Contractor shall inspect and promptly report to the Contracting Officer in writing any defects or deficiencies in such work that renders it unsuitable for such proper execution or results. His failure to so report shall constitute an acceptance of the other work as fit and proper for the execution of his work except as to defects and deficiencies, which may appear in the other work after the execution of his work.

D. Contractor shall do all cutting, fitting, and patching of his work that may be required to make its several parts come together properly and fit it to receive or be received by such other work. Contractor shall not endanger any work of others by cutting, excavating, or otherwise altering their work and will only cut or alter their work with the written consent of the Contracting Officer and of the other Contractors whose work will be affected.

E. If the performance of additional work by other contractors or Owner is not noted in the Contract Documents prior to the execution of the Contract, written notice thereof shall be given to Contractor prior to starting any such additional work. If Contractor believes that the performance of such additional work by Owner or others involves him in additional expense or entitles him to an extension of the contract time, he may make a claim therefore.

01040 – Page 2 of 17

April 19, 2016

F. Contractor shall be responsible for all areas of the site used by him and all Subcontractors in performance of the work. He shall exert full control over the actions of all employees and other persons with respect to the use and preservation of property and existing facilities, except such controls as may be specifically reserved to Owner or others.

G. Contractor and all Subcontractors shall cooperate in the coordination of their separate activities in a manner that will provide the least interference with the Owner's operations and utility companies working in the area, and in the interfacing and connection of the separate elements of the overall project work. If any difficulty or dispute should arise in the accomplishment of the above, the problem shall be brought immediately to the attention of the Contracting Officer. All Contractors working on this site are subject to this requirement for cooperation, and all shall abide by the Contracting Officer's decision in resolving project coordination problems without additional cost to the Owner.

1.03 SUBMITTALS

A. In accordance with provisions of SECTION 01300 – SUBMITTALS, Contractor shall submit the following information as applicable to coordination activities:

1. Subsurface Information and Utilities

a. Records or logs of borings or test holes made by Contractor, if any.

b. Results of exploratory excavations made to verify locations and nature, shape, dimensions, etc., of existing utilities and facilities; where possible, indicate this information on a clean copy of Contract Drawings.

2. Field Relocation: Clearly show proposed relocations of new or existing facilities, or related work affected by the relocation, on a clean copy of the Contract Drawings and submitted prior to performing the relocation.

3. Easements: Copy of easements and other agreements obtained from utilities and property owners as required to carry out the work.

4. Connecting Work: Proposed methods of connecting new work to existing facilities, where not shown or specified.

5. Cutting and Patching

a. Written notice requesting consent to perform cutting, which

01040 – Page 3 of 17

April 19, 2016 may affect structural safety or normal functioning of existing facilities.

b. Recommendations indicating changed conditions, alternative materials or methods, time when uncovered work may be observed, and other information necessary to evaluate substitutions when work conditions necessitate change of materials or methods.

6. Leases: Copy of leases and other agreements obtained from public agencies or private owners as required for Contractor’s staging and material storage areas.

1.04 SITE CONDITIONS

A. Information on Site Conditions:

1. General: Information obtained by the Owner regarding site conditions, topography, subsurface information, groundwater elevations, existing construction of site facilities as applicable, and similar data is included in the Contract Documents or will be available for inspection at the office of the Engineer or Owner upon request. Such information is offered as supplementary information only. Neither the Engineer nor the Owner assumes any responsibility for its accuracy or completeness or for the Contractor's interpretation of such information.

2. Control Points: Contractor shall check existing vertical and horizontal survey control points on structures and improvements located in the vicinity of the work prior to beginning work. The Contractor may establish new vertical and horizontal survey control points, if desired. Contractor shall check the points for movements when directed by the Contracting Officer. Furnish Contracting Officer with copies of survey notes for each survey and a copy of the layout of survey control points.

B. Existing Utilities:

1. Location

a. Known utilities and facilities adjacent to or within the work area are shown on the Drawings. The locations shown are taken from existing records and the best information available from existing utility plans; however, it is expected that there may be some discrepancies and omissions in the locations and quantities shown. Contractor's request for additional compensation or Contract time resulting from

01040 – Page 4 of 17

April 19, 2016 encountering utilities not shown will not be considered as this work is considered incidental to the overall project work.

The Contractor is solely responsible for locating and avoiding conflicts with all existing utilities.

b. Contractor shall verify locations of utilities and facilities shown on the Drawings and to determine the presence of those not shown. Immediate and adjacent areas where excavations are to be made shall be thoroughly checked by visual examination for indications of underground facilities and also checked with electronic metal and pipe detection equipment. Where there is reasonable cause to verify the presence or absence of an underground facility, make exploratory excavations prior to proceeding with major excavation in the area. Where information on buried facilities is required to verify their nature, shape, configuration, dimensions, materials, or other properties, make exploratory excavations as required to ensure avoidance of conflicts and as acceptable to the Contracting Officer.

c. The Contractor is advised that there is a one call utility locate number in use for utility location requests within the State of Montana for buried gas and electrical lines and buried telecommunication lines. The one call number is 811. It is mandatory to use this system before any excavation work in Montana.

2. Contractor's Responsibilities

a. Where Contractor's operations could cause damage or inconvenience to telephone, television, power, oil, gas, water, sewer, or irrigation systems, the Contractor shall make arrangements necessary for the protection of these utilities and services. Replace existing utilities removed or damaged during construction with equal or better materials, unless otherwise provided for in these Contract Documents.

b. Notify utility offices that are affected by construction operations at least 48 hours in advance. Under no circumstances expose any utility without first obtaining permission from the appropriate agency. Once permission has been granted, locate, expose, and provide temporary support for the utilities.

c. Protect all utility poles from damage. If interfering utility poles will be encountered, notify the utility company at least 48 hours in advance of construction operations to permit

01040 – Page 5 of 17

April 19, 2016 necessary arrangements with the utility company for protection or relocation of the interfering poles.

d. Contractor shall be solely and directly responsible to owner and operator of such properties for damage, injury, expense, loss, inconvenience, delay, suits, actions, or claims of any character brought because of injuries or damage which may result from construction operations under this Contract.

e. Neither Owner nor its officers or agents shall be responsible to Contractor for damages as a result of Contractor's failure to protect utilities encountered in the work.

f. In event of interruption to domestic water, sewer, storm drain, or other utility services (public and private) as a result of accidental damage due to construction operations, promptly notify the Contracting Officer and/or proper authority. Cooperate with the Contracting Officer and said authority in restoration as promptly as possible and pay for repair. Prevent interruption of utility service unless granted by the utility owner.

g. Maintain a legible log of all utility crossings showing type, depth, date of crossing, location referenced to project stationing, and a notation if the utility was damaged, type of repair, and who made the repair. The Contractor will work with the Contracting Officer to maintain an accurate and complete log, which will become part of the as-constructed contract drawings.

3. Names of Known Utilities: Notify the following applicable utilities if conflicts or emergencies arise during the work: (This list is not all inclusive. The Contractor is responsible for determining all of the utilities within the project work area).

a. Electric and Natural Gas Company: Northwestern Energy

Telephone: 1-888-467-2669

b. Water and Sewer Utilities: USFS (Contracting Officer)

C. Interfering Structures

1. Take necessary precautions to prevent damage to existing structures whether on the surface, above ground, or underground.

01040 – Page 6 of 17

April 19, 2016

2. Protect existing structures from damage, whether or not they lie within limits of easements obtained by the Owner. Where existing fences, gates, sheds, buildings, or other structures must be removed to properly carry out work, or are damaged during work, restore them to original condition and to the satisfaction of property owner.

3. Contractor may remove and replace in equal or better than original condition, small structures such as fences, mailboxes, and signposts that interfere with Contractor's operations. Replacement of these small structures will be incidental to the work. Contractor to obtain permission from the small structure owner prior to removal and replacement. Comply with all regulatory requirements.

D. Field Relocation:

1. During construction, it is not expected that relocations of proposed facilities will be necessary. However, in the event such relocations become necessary, make such relocations only by direction of the Contracting Officer. If existing structures are encountered that prevent construction as shown, notify the Contracting Officer before continuing with work so Contracting Officer may make necessary field revisions.

2. Where shown or directed by and acceptable to the Contracting Officer, provide relocation of existing facilities to include piping, utilities, equipment, structures, electrical conduit wiring, electrical duct bank, and other miscellaneous items. Use only new materials for relocation of existing facilities. Match materials of existing facilities unless otherwise shown or specified. Perform relocations to minimize downtime of existing facilities. Install new portions of existing facilities in their relocated position prior to removing existing facilities, unless otherwise accepted by the Contracting Officer.

E. Monuments and Markers:

1. Preserve and protect survey monuments and markers throughout construction. If damage occurs or removal becomes necessary, immediately notify Contracting Officer and restore monument or marker to original condition. Restoration to be at the Contractor’s sole expense.

2. Preserve private and public monuments that are found. If monument must be removed, replace at original locations using registered land surveyor. Notify Engineer when monuments are encountered. If government monuments are encountered, 01040 – Page 7 of 17

April 19, 2016 reference the monument for later replacement and provide 10-day advance notification to Engineer who will notify the proper authority.

F. Connecting to Existing Facilities: Unless otherwise shown or specified, determine methods of connecting new work to existing facilities, and obtain Engineer's review and acceptance of connections.

1. Determine location, elevation, nature, materials, dimensions, and configurations of existing facilities where necessary for connecting new work.

2. Inspect existing record drawings and shop drawings, conduct exploratory excavations and field inspections, and conduct similar activities as needed.

G. Erosion and Dust Control On-Site:

1. The Contractor shall be responsible for reducing soil erosion and dust due to wind or water to a level meeting federal, state, and local regulations at the construction site. Control measures that may be required include, but may not be necessarily limited to, the following:

a. Suspending excavation during high winds or rain.

b. Minimizing land exposure in area and time.

c. Covering erodible areas as quickly as possible with gravel or by compaction.

d. Stabilizing construction site soils.

e. Controlling dust during construction by use of water spray.

1.05 PROJECT MEETINGS OR REPORTS

A. Preconstruction Conference: A preconstruction conference will be scheduled after the Notice of Award.

B. Progress Meetings: The Contracting Officer may schedule regular progress meetings if necessary, approximately every two weeks to review work progress, schedules, and other matters needing discussion and resolution.

C. Progress Reports: A monthly progress report may be required with an updated schedule by the Contractor prior to the submission of the application for progress payment. If the work falls behind schedule, Contractor shall submit progress reports at such intervals as the Contracting Officer may request. Each progress report shall include sufficient narrative to describe

01040 – Page 8 of 17

April 19, 2016 current and anticipated delaying factors, their effect on the construction schedule, and proposed corrective actions. Any work reported complete, but which is not readily apparent to the Contracting Officer must be substantiated with satisfactory evidence.

D. Purpose of Meetings and Reports: The purpose of the meetings or reports will be to review the progress of work, maintain coordination of efforts, discuss changes in scheduling, and resolve other problems which develop. At a minimum, each meeting must be attended by the Contractor's project manager or field superintendent.

1.06 SEQUENCE OF WORK

A. Operation and Shutdown of Existing Facilities:

1. Continuous operation of Owner’s facilities is of critical importance.

Schedule and conduct activities to enable existing facilities to operate continuously, unless otherwise specified. Conduct work outside normal working hours as may be necessary to meet project schedule and avoid undesirable conditions within limits specified in the General and Supplementary Conditions.

2. Provide at least 14 days advance notice to Contracting Officer of need to shut down a pump, pipeline, or facility unless specified otherwise hereinafter. Do not proceed with work affecting a facility’s operation without obtaining Contracting Officer’s advance approval of the need for, and duration of, such work.

3. At no time shall the Contractor be permitted to take actions that may result in discharge of untreated or inadequately treated wastewater. The Contractor will be afforded the opportunity to select the appropriate means and methods of construction to accomplish the construction and continue providing treatment, within the specific constraints specified hereinafter.

4. Provide temporary devices, pumps, piping, equipment, electric service, and other similar items as may be required to accomplish the work and maintain continuous and efficient operation.

B. Modifications to Existing Facilities:

1. Where existing facilities are to be modified during the course of work, obtain Contracting Officer's review and acceptance of submittals for temporary shutdown, demolition, modification, connections between new and existing work, and other related work. Conform to other sections as applicable.

01040 – Page 9 of 17

April 19, 2016

2. Connections to existing services or utilities, or other work that requires the temporary shutdown of any existing operations of utilities shall be planned in detail with appropriate scheduling of the work and coordinated with the Contracting Officer. The schedule for shutdown or restart shall be given by written advance notice in order that the Contracting Officer may witness the shutdown, tie-in, and startup. All equipment, materials, and labor that the Contractor plans to have available shall be coordinated in order to ensure the work is done in the minimum amount of time.

3. All materials and equipment (including emergency equipment) necessary to expedite the tie-in shall be on hand prior to the shutdown of existing services or utilities. Where bypass pumping is required, the Contractor shall have equipment of adequate capacity to meet maximum anticipated flowrates with one “unit” in standby mode as specified in Paragraph 1.07 below.

4. Unless otherwise specified or indicated, Contractor shall make all necessary connections to existing facilities including structures, pipelines, and utilities such as water, gas, and electric. In each case, Contractor shall obtain permission from the Owner or the owning utility prior to undertaking connections. Contractor shall protect facilities against deleterious substances and damage.

5. Existing valves or gates used to isolate certain structures may not be watertight and some leakage may occur. The Contractor shall provide the necessary temporary plugs and/or pumping facilities to handle any leakage.

6. Temporary dams, stop logs, stop gates, valves, or other devices shall be designed and installed by the Contractor as needed for installation of the work.

7. The Contractor shall design and install shoring and support of existing and new structures and piping to prevent damage during the work and to maintain functional use of the Owner’s facilities.

C. The following major existing facilities will need to be modified as part of the work, as shown on the Drawings and as necessary to accomplish the work.

This work must be carefully planned and coordinated with the Contracting Officer as specified herein. This work shall also be performed as specified in Section 02020, DEMOLITION AND SALVAGE and in other appropriate detail specifications.

1. The existing wet well and lift station will be replaced with a new wet well and submersible grinder pumps as generally shown on the Drawings. This requires the Contractor to demo the existing pumps

01040 – Page 10 of 17

April 19, 2016 and accessories, re-route the influent and discharge lines, and replace the electrical and controls.

2. All miscellaneous connections to existing piping and structures are shown on the Drawings.

D. Sequence of Major Activities: In order to meet the overall objectives of the project, certain elements of work must be completed or substantially completed within the following sequence constraints. The following sequence of construction is meant to be a guideline for the Contractor presenting one method of accomplishing desired results and includes only major items of work. It is the responsibility of the Contractor to review these items and the work to be done, and determine the methods that will be used to accomplish the tasks. The Contractor shall also submit proposed methods to the Contracting Officer for review prior to commencing work. The Contractor is still responsible for the methods used to accomplish the project objectives and all safety requirements.

1. Temporarily Relocate Existing Pump Station Controls: The following items of work are included:

a. Field verify that adequate freebord is available in the aerated lagoon for adequate transition time required to temporarily move power.

b. Close influent gate valve in existing wet well and pump down wet well.

c. Temporarily relocate the pump and aerator panels to a location out of the way of new panel installation and provide a temporary power feed.

d. Re-open influent valve in existing wet well and restart the existing aerators and pump station.

2. Construct New Lift Station: A possible sequence of construction is listed below and is meant to be a guideline for the Contractor and includes only major items of work:

a. The groundwater level under the site is unknown but is expected to range from 3 to 4 feet below grade depending on the time of year. Contractor to field verify. In order to complete work at the site, the groundwater level will have to be lowered using localized dewatering methods designed and installed by the Contractor. Refer to Section 02220, EARTHWORK FOR STRUCTURES for additional information and requirements.

01040 – Page 11 of 17

April 19, 2016

b. Install Precast Wet Well as shown on the Drawings. Vacuum test structure as described in section 02500 – PRECAST

CONCRETE STRUCTURES.

c. Install all Manufacturer supplied equipment as shown on the Drawings including the pumps, floats, level transducer, flow meter, piping, and valves. Also, complete associated electrical and control installation at the wet well as required on the Drawings for this equipment.

d. Installation of fiberglass enclosure: Install manufactured enclosure as detailed on the Drawings. Install electrical, insulation, heating, and ventilation equipment associated with the enclosure.

e. Coordinate installation of all process/plumbing piping and electrical/controls conduit in this area and between the wet well and existing building prior to backfilling.

f. Perform commissioning, clean water functional testing, and start-up on new lift station according to individual equipment specifications prior to placing facility into service.

3. Connection of the new lift station to the existing influent line & force main piping: Tie-in of the piping must be closely coordinated and must occur simultaneously to switch wastewater pumping from the existing lift station to the new lift station. The following items of work are included:

a. Using a plug at the lagoon side of the influent line or a transfer pump into the existing wet well to pump down the lagoon. Stop flow into the influent line. Transfer pumping will require at a minimum that a pump by supplied to pump from the lagoon into the wet well for the existing pumps to pump through the volume through force main. Attention should be given to existing pumps during transfer to ensure that they remain functional while running longer, more frequent cycles and no wet well backing up occurs. See below for detail on transfer pumping requirements.

b. Temporary power must be remain in service to keep both existing pumps in service until the new facilities are operational.

c. Modify the existing lift station and facilities required to commission the new lift station including switching over the electrical components, installation of influent piping, and

01040 – Page 12 of 17

April 19, 2016 connection of the discharge piping to the force main. Refer to Section 02020 for demolition details.

d. Plugging and abandoning the existing piping between the new connection point and the existing wet well. If fully excavated, piping may be removed and wall penetration plugged.

4. Aeration Equipment: Aeration must be provided to the lagoon at all times, with the exception of short power transfers, to ensure adequate wastewater treatment. Demolition work on the existing aeration system electrical equipment and accessories should likely begin once the existing electrical equipment in the Lift Station Building has been removed. Downtime of aeration equipment must be minimized.

5. Lift Station Building: Demolition of the existing Lift Station Building equipment and construction work on the building must be closely coordinated with the continued operation of the existing facility and startup of the new facility. A possible sequence of construction is listed below and is meant to be a guideline for the Contractor and includes only major items of work:

a. The demolition of the existing lift station equipment, existing electrical equipment, and modifications to the building may occur once the new lift station is in service. Modifications to the building include removal of pumps, piping, valves, floats, supports, and other appurtenances. Additionally, patching of holes in the concrete floor and building walls will be required in addition to cleaning out sludge, grit, debris, ect out of the existing wet well. Refer to Section 02020 for demolition details.

b. Any sludge, grit, debris, ect that is found in the bottom of the wet well will have to be removed and deposited by the Contractor into the lagoon or as instructed by the Contracting Officer.

6. All electrical, instrumentation, and control connections must be scheduled and coordinated with the Owner at least 14 days in advance and made within the minimum time possible. This work must be completed prior to placing the new/modified facilities into service. Service continuity must be maintained except for brief outages for cut-overs.

01040 – Page 13 of 17

April 19, 2016

7. All excavation and/or trenching work must be completed in such a way so as to maintain vehicular access to all portions of the plant site at all times.

E. Miscellaneous Piping Connections: All piping connection work shall be planned and coordinated with the Owner and Engineer as specified hereinbefore and shall be performed during a time of the day when influent wastewater or sludge flows are expected to be at a minimum. In general, the Contractor shall work continuously to make these connections and construct all necessary thrust blocks in the minimum time. Temporary thrust restraints shall be provided by the Contractor and high early strength concrete shall be used for all connections required by the Owner to be placed back in service immediately. The temporary thrust restraints shall be left in place until the thrust block concrete has reached its design strength.

1.07 TRANSFER PUMPING

A. Transfer pumping of wastewater from the lagoon into the existing wet well be necessary as part of the modifications to the existing facilities. The wastewater lagoon must be pumped down sufficiently (~6 feet) in order to make the tie-in to the influent line in the wet well. By transfer pumping from the lagoon into the wet well, the existing pumps can be used to pump lagoon volume up the 4-inch force main.

B. The Contractor shall supply transfer pumping equipment, piping and fittings capable of pumping no more than of 80 gpm, which is the capacity of the existing lift station pumps. The Contractor shall provide a power source for pumping operations. The Contractor is required to check on the transfer pumps and existing pumping equipment a minimum of every 45 minutes while the pumps are transferring to ensure that the existing wet well is not backing up. Transfer pumping may be stopped and restarted over multiple shifts should it be advantageous to the Contractor.

1. The influent line invert in the existing lift station wet well is similar to the water surface elevation in the aeration lagoon. Therefore, transfer pumping would only require that the water surface be brought down far enough to provide time to perform the work. It can be roughly estimated that at an 80 gpm pumping rate with a 13 gpm average influent flow, every foot of drop in the lagoon will take approximately 26 hours to pump down. At 13 gpm, it is expected that the level will rise 1 foot in approximately 133 hours.

C. The Contractor shall submit a Transfer Pumping Plan prior to beginning transfer pumping operations. Transfer pumping shall not be performed

01040 – Page 14 of 17

April 19, 2016 without approval of the Contracting Officer. The Plan shall include, at a minimum, the following information:

2. Pump manufacturer, pump type, and motor horsepower of pump to be used and generator information. Sound levels from the generator and pumping equipment shall be no more than 69 dBA at 30 feet.

3. Type of temporary piping and fittings to be used.

4. Temporary pipe routing through construction area. Include any pipe supports required.

5. Mode of inlet and outlet piping support within existing structures.

6. Anticipated number of days, hours of operation and number of personnel dedicated to pumping operations.

1.08 SCHEDULING OF WORK

A. Modifications to Existing Facilities:

1. Where existing facilities are to be modified during the course of work, obtain the Contracting Officer’s review and acceptance of submittals for temporary shutdown and temporary water supply, demolition, modification, corrections between new and existing work, and other related work. Conform to other sections as applicable.

2. Connections to existing services or utilities, or other work that requires the temporary shutdown and/or bypass pumping of any existing operations of utilities shall be planned in detail with appropriate scheduling of the work and coordinated with the Contracting Officer. The schedule for shutdown or restart shall be given by written advance notice in order that the Contracting Officer may witness the shutdown, tie-in, and startup.

3. All materials and equipment (including emergency equipment) necessary to expedite tie-ins shall be on hand prior to the shutdown of existing services or utilities.

4. Unless otherwise specified or indicated, Contractor shall make all necessary connections to existing facilities including manholes, structures, pipelines, and utilities such as gas and electric. In each case, Contractor shall obtain permission from the Contracting Officer or the owning utility prior to undertaking connections.

01040 – Page 15 of 17

April 19, 2016

Contractors shall protect facilities against deleterious substances and damage.

5. Connections to existing facilities which are in service shall be thoroughly planned in advance, and all required equipment, materials, and labor shall be on hand at the time of undertaking the connections. All equipment, materials, and labor that the Contractor plans to have available shall be coordinated with the Contracting Officer in order to ensure the work is done in the minimum amount of time.

B. Time of Work:

1. Working hours for the Contractor shall be limited to the hours between 7:00 a.m. and 5:00 p.m. and shall not exceed 10 hours per day with authorized overtime. The Contractor must obtain approval from the Contracting Officer for any alternate work schedule.

PART 3 EXECUTION

3.01 CUTTING AND PATCHING

A. General:

1. Execute cutting (including excavating), fitting, or patching of work, required to:

a. Make the several parts fit properly.

b. Uncover work to provide for installation of specified work.

c. Remove and replace defective work or work not conforming to requirements of Contract Documents.

d. Install specified work in existing construction.

2. Perform the following upon written instruction of Contracting Officer:

a. Uncover work to provide for Contracting Officer’s observation of covered work.

b. Remove work to provide for alteration of existing work.

3. Contractor shall not, without written consent of Contracting Officer:

a. Cut or alter work of another Contractor.

b. Cut structural or reinforcing steel.

01040 – Page 16 of 17

April 19, 2016

c. Endanger existing or new structures or facilities.

d. Shut down or disrupt existing operations.

4. Materials for replacement of work removed shall comply with applicable sections of these Specifications for corresponding type of work to be done.

5. Provide all tools and equipment required to accomplish cutting and patching.

B. Inspection and Preparation:

1. Inspect existing conditions of work, including elements subject to movement or damage during cutting, patching, excavating, and backfilling.

2. After uncovering work, inspect conditions affecting installation of new products.

3. Prior to cutting, provide safety protection.

C. Procedures:

1. Execute fitting and adjustment of products to provide finished installation to comply with specified tolerances and finishes.

2. Execute excavating and backfilling as specified in Section 02221, Trench Excavation & Backfill – Pipelines & Appurtenant Structures.

3. Restore work which has been cut or removed; install new products and provide completed work in accordance with specified requirements.

4. Restore structures and surfaces damaged that are to remain in the completed work including concrete embedded piping, conduit, and other utilities.

5. Make restorations with new materials and appropriate methods as specified for new work of similar nature; if not specified, use best recommended practice of manufacturer or appropriate trade association.

6. Restore damaged work so there is a secure and intimate bond or fastening between new and old work. Finish restored surfaces to such planes, shapes, and textures that no transition between new and old work is evident in finished surfaces.

01040 – Page 17 of 17

END OF SECTION 01040

SECTION 01092

ABBREVIATIONS AND

DIVISION 1 - GENERAL REQUIREMENTS REFERENCE STANDARDS

01092 – Page 1 of 4 M:\0916\071 - USFS 5 Year Contract\20 - AJCC Lift Station\Documents\Design\Specs\Technical\01092.doc April 19, 2016

PART 1 GENERAL

1.01 SUMMARY

A. This section lists many of the construction industry organizations, professional and technical associations, societies and institutes, and government agencies issuing, promoting, or enforcing standards to which references may be made in the Contract Documents along with the abbreviations commonly used for those references. Also included are certain general requirements for the use of industry standards specified, and for application of the standards in quality control.

1.02 USE OF REFERENCE STANDARDS

A. Work specified by reference to the published standard or specification of a government agency, technical association, trade association, professional society or institute, testing agency, or other organization shall conform to or surpass the minimum standards of quality for materials and workmanship established by the designated standard or specification.

B. Where so specified, products or workmanship shall also conform to the additional prescriptive or performance requirements included within the Contract Documents to establish a higher or more stringent standard of quality than that required by the referenced standard.

C. Where the specific date or issue of the standard is not included with the reference to the standard, the edition, including all amendments published and available on the first published date of the Project Manual, shall apply.

D. Where two or more standards are specified to establish quality, the product and workmanship shall conform to or surpass the requirements of both.

E. In case of conflict between referenced standards, the more stringent shall apply.

F. Where both a standard and a brand name are specified for a product in the Contract Documents the proprietary product names shall conform to or surpass the requirements of the specified reference standard. The listing of a trade name in a Contract Document shall not be construed as warranting that such product conforms to the respective reference standard.

01092 – Page 2 of 4

G. Copies of standards:

1. Copies of applicable referenced standards have not been bound in this Contract Document.

2. Where copies of standards are needed by the Contractor for superintendence and quality control of the work, obtain a copy or copies directly from the publication sources and maintain in an orderly manner at the job site, available to the Contractor personnel, Sub-Contractors, Owner, and Contracting Officer.

3. Submittals: Submit for approval the requests to use products conforming to printed standards or publications with a different publication date from that effective under the Contract. Clearly indicate the changes in product or workmanship quality involved in the proposed change, if any, and reasons for the request.

1.03 ABBREVIATIONS

A. Abbreviations for Trade Organizations and Government Agencies:

Following is a list of construction industry organizations and government agencies to which references may be made in the Contract Documents, with abbreviations used.

AA Aluminum Association AAMA Architectural Aluminum Manufacturers' Association AASHTO American Association of State Highway and

Transportation Officials ACI American Concrete Institute AFBMA Anti-Friction Bearing Manufacturers' Association AGA American Gas Association AGMA American Gear Manufacturers' Association AISC American Institute of Steel Construction AISI American Iron and Steel Institute AITC American Institute of Timber Construction ALS American Lumber Standards AMCA Air Moving and Conditioning Association ANSI American National Standards Institute APA American Plywood Association API American Petroleum Institute AREA American Railway Engineering Association ARI Air Conditioning and Refrigeration Institute ASAE American Society of Agricultural Engineers ASCE American Society of Civil Engineers ASHRAE American Society of Heating, Refrigerating and Air Conditioning Engineers, Inc.

01092 – Page 3 of 4

April 19, 2016

ASME American Society of Mechanical Engineers ASSE American Society of Sanitary Engineers ASTM American Society for Testing and Materials AWI Architectural Woodwork Institute AWPA American Wood Preservers' Association AWPB American Wood Preservers' Bureau AWPI American Wood Preservers' Institute AWS American Welding Society AWWA American Water Works Association BHMA Builders Hardware Manufacturers' Association CBMA Certified Ballast Manufacturers' Association CDA Copper Development Association CGA Compressed Gas Association CISPI Cast Iron Soil Pipe Institute CMAA Crane Manufacturers' Association of America CRSI Concrete Reinforcing Steel Institute FGMA Flat Glass Marketing Association FM Factory Mutual Fed Spec.

This is the start of the file's text. The full file is on GovTribe.