Amendment_0001.pdf
PDF 2 MB Posted
- Attached to
- Sewage Lift Station Improvements
- Solicitation number
- AG-82A7-S-16-0062
About this file
Amendment 0001 with Attachments
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment_2_-_DBA_Wages.pdf | ||
| Attachment_1_Specs_and_Dwgs.pdf | ||
| AG-82A7-S-16-0062.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
AG-82A7-S-16-0062
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
82A7
GOLDEN CO 80401
740 SIMMS STREET
USDA FOREST SERVICE
JOB CORPS AQM
07/11/20160001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
07/11/2016
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
TITLE: Replace Sewage Lagoon Lift Station, Anaconda Job Corps, Deer Lodge County, Montana
This amendment is hereby issued to provide for the following revsions:
a. Provide for the following pen and ink change to the SF-1442.
1. Block 13.b. Check the box to reflect a offer guarantee "is" required.
2. Block 13.d. insert "60" calendar days for acceptance
b. The following Clauses are hereby incorporated into Section I - Contract Clauses
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
GINGER R. DOMINGOS
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 2
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
AG-82A7-S-16-0062/0001
1. 52.228-1, Bid Guarantee (Sep 2996) The amount of the bid guarantee shall be 20 percent of the bid price.
2. 52.228-14, Irrevocable Letter of Credit
(Nov 2014)
3. 52.228-15, Performance and Payment
Bonds - Construction (Oct 2010)
c. The following paragraph (5) s hereby added to
Section L, Clause 452.215-71 paragraph (a)
General Instruction.
(5) Proposals may be submitted via email to gingerdomingos@fs.fed.us, however an original bid guarantee must be submitted via mail (postal service), shipped (UPS/FEDEX/etc.) or hand delivered by the date and time provided for in the solicitation. If technical proposal is not submitted via email, an electronic copy shall be provided.
d. The Drawing Sheets 1 thru 12 provided within
Attachment 1 are hereby replaced in their entirety.
e. The list of attendees and responses to questions received is attached.
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
Replace Sewage Lagoon Lift Station Pre-bid Site Visit, Thursday, July 21, 2016, 10:00 AM
Anaconda Job Corps Center
Attendees:
Shawn Boelman, USFS, Bitterroot National Forest, 406-363-7107, sboelman@fs.fed.us Lan Hertz, Hertz Contracting LLC., 406-880-1889, lhertz@montana.com Joe Dolan, Central Excavation, 406-388-1000, joe@centralexcavation.com Brett Hackman, USFS, Anaconda JCC, 406-563-8736 Ray Bennett, Mungas CO, 406-439-9034 Marty Logan, Diamond Construction, 406-461-2342 Chance Ellis, ICS, 406-781-6467 Ron Morgan, USFS, Anaconda JCC, 406-563-8758 Jim Maes, USFS, Anaconda JCC, Notes:
Shawn Boelman, who will be the Contracting Officer’s Representative, initially discussed that the drawings posted were an older set. That they have been updated. Mr. Boelman handed out hardcopies. The solicitation will be updated with the new drawings. When going over the drawings at the site, it was pointed out that the new wet well was located on the lagoon side of the force main and that the COR has been talking about it being on the opposite side of the force main. When new drawings are posted on the solicitation, it will reflect the new wet well located on the opposite side.
It was discussed that the Anaconda JCC will be installing a new potable water line to the lift station building this summer. The water line will be going around the proposed construction area and into the north side of the structure. It should not interfere with the proposed work.
Mr. Boelman discussed proposal requirements. Spoke of pages 21 and 22 of solicitation, section 452.215-71. In addition to business proposal (ie., price), the best value determination will include a technical component including Specialized Experience, Plan of Operations, Key Personnel, Bio-Based Product Utilization, and Past Performance.
Question: What is the volume that the bypass will have to handle? Jim Maes stated approximately 10,500 gal/day.
Question: Does the existing wet well have to be cleaned. Shawn responded yes. Section 02020, Demolition and Salvage, states to remove and dispose of all remaining sewage and solids from the wet well offsite at an approved location.
Question: Do we need to water proof the interior and exterior of the new wet well. Shawn indicated that it is covered in section 07121 and 07160. Section 07121 covers exterior waterproofing of the new wet well. No interior water proofing of the new wet well is required.
Question: Performance Bond – Yes, Bid Bond – Yes (At the pre-bid site visit Mr. Boelman stated no bid bond was required, however, the CO is amending the SF 1442 to require a bid bond)
Question: Can the proposal be submitted online? Yes the proposal can be submitted online, see the CO instructions, with the bid bond being sent postmarked no later than the August 11, 2016 bid date.
mailto:sboelman@fs.fed.us mailto:lhertz@montana.com mailto:joe@centralexcavation.com
Question: Clarifying what are the work hours. The solicitation states 7:30 – 4:00. The specifications state 7:00 to 5:00. The contractors are allowed to work between 7:00 AM to 5:00 PM MDT.
Question: Electricity on-site. Whose is it? The electricity is provided by NW Energy. Power for the lift station comes from a transformer shared with another building. The Anaconda JCC will coordinate any Contractor’s requests of NW Energy. It is 3 Phase.
Question: What is the Contractor required to plant and reclaim? The Contractor will be required to plant and reclaim only the areas that they disturbed in meeting the requirements of the contract.
Question: What is the lagoon elevation? Lagoon elevation is 6059.5 as depicted on Sheet 4 of 12, Section A detail.
Question: Existing 4” force main, what is it made of? Specific type of existing iron pipe is not identified.
Contractor shall expose the existing pipe or structure to verify its exact location, size, materials, and invert elevations.
Question: Are there any intermediate valves on the existing force main from the existing lift station building and the top of the line. No, there are no intermediate valves on the 4” force main between the existing lift station and the manhole #7 (see sheet 3 for the manhole location).
OTHER QUESTIONS RECEIVED VIA EMAL:
Question: The Manual transfer switch to be installed is shown on the print as a 200 amp fused transfer switch. This is redundant for the load center has a main breaker. Therefore can a non fused transfer switch be used? Yes a non-fused SE rated transfer switch is acceptable as the load panel does include a main CB.
Question: The procurement of the Aerator control panel is who’s responsibility? If it is Division 16 / do you have a manufacture or is this field made? It is the Contractor’s responsibility to provide the aerator control panel. Yes, it is Division 16 and field made to match existing aerator control panels per detail in drawings.