AG-8191-S-16-0012_Amd_000001.pdf
PDF 93 KB Posted
- Attached to
- VERDE SOLAR PANEL EXPANSION
- Solicitation number
- AG-8191-S-16-0012
View the file
Other files
| File | Type | Posted |
|---|---|---|
| amendment_0002.pdf | ||
| Verde_Energy_Audit_-_Solar_exerpt.pdf | ||
| APS_utility_bills.pdf | ||
| Verde_PV_info.pdf | ||
| site_plans.pdf | ||
| VerdeRangerStationAdminSitePlan04252015.pdf | ||
| WD_AZ35.docx | DOCX document | |
| AG-8191-S-16-0012.pdf | ||
| Photos.docx | DOCX document | |
| Prescott_Fire_Plan.doc | DOC document | |
| Past_Performance_Questionnaire.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(x)
AG-8191-S-16-0012
x x
1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT
THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
x
PRESCOTT AZ 86303
344 SOUTH CORTEZ
PRESCOTT NATIONAL FOREST
08/23/2016000001
13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
FACILITY CODE CODE
10B. DATED (SEE ITEM 13)
10A. MODIFICATION OF CONTRACT/ORDER NO.
9B. DATED (SEE ITEM 11)
9A. AMENDMENT OF SOLICITATION NO.
CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)
7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY
PAGE OF PAGES
4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)
1. CONTRACT ID CODE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
08/22/2016
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.
ORDER NO. IN ITEM 10A.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
PHOTOVOLTAIC SYSTEM - VERDE RANGER DISTRICT - PRESCOTT NATIONAL FOREST - PROJECT
The purpose of this amendment is for clarification purposes and to respond to Questions and
Answers from emails and the pre-bid site visit scheduled on August 10, 2016.
SCOPE CLARIFICATION ¿ PRE-BID SITE VISIT
During the site visit, it was discovered that the existing PV system installed at the Verde
Ranger Station was no longer functioning at its peak capacity or efficiency. It was also discovered that the existing service entrance provided by APS is an 800A service and that most of the capacity in the unit is already being used. This means that there is inadequate
Continued ...
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED
(Signature of person authorized to sign) (Signature of Contracting Officer)
JONI DUTCHER
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
NSN 7540-01-152-8070
Previous edition unusable
Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .
ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
NAME OF OFFEROR OR CONTRACTOR
2 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
AG-8191-S-16-0012/000001
capacity to add a new 45.2 kw system on top of the existing system. The Forest has elected that at this time we do not wish to puruse increasing the capacity of the 800A service provided by APS.
Instead, we would like to have solar power generation provided that either offsets 100% of the site¿s energy usage or that fully utilizes the 800A service provided by APS at the Verde
Ranger Station.
BID ITEMS:
A. For bidding purposes of this contract, all interested parties shall submit a proposal for completing the original scope of work. This includes providing an additional 45.2 kw system that could tie in with the existing system. The existing system shall be assumed to be working properly.
B. In addition to the above, vendors shall submit pricing and a narrative describing their approach in repairing and/or retrofitting the existing PV system to provide reliable and efficient solar power generation. Vendors MUST submit a narrative describing the modifications, changes, and repairs they intend to make to the existing system and the subsequent power generation that would be provided by retrofitting the existing system.
Either item A or B will be awarded, not both. The
Forest will make a determination after receiving proposals from all interested parties on what option provides the best value to the Forest
Service.
C. Submit a price proposal that expands the PV system as much as possible. This price would be to offset the power consumption at the site by
100% or until the 800A service capacity is met.
Whichever condition is met first. Depending the cost to pursue this option, the Forest may elect to award all, some, or none of this bid option.
Vendors should submit pricing as a ¿per panel¿ unit cost for this bid item as well as a total cost.
QUESTIONS & ANSWERS ¿ PRE-BID SITE VISIT
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
Sponsored by GSA
FAR (48 CFR) 53.110
3 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
AG-8191-S-16-0012/000001
1. Can utility data for the past year be provided.
a. Yes see attached utility bill statement from
APS.
2. Do we need to account for sales tax?
a. Contractors should pay any and all taxes that they are subject too. The federal government is not required to pay sales tax but we are not directly paying for the materials/equipment to be installed.
3. Has anyone talked to APS regarding the expansion?
a. No, that will be the responsibility of the awardee.
4. What exactly is meant by ¿net metering¿?
a. See the APS website for definitions on net metering.
https://www.aps.com/en/residential/accountservices
/serviceplans/Pages/renewable-energy-plans.aspx
5. Do you have warranty information for the existing system?
a. Yes, please see attached warranty information.
6. The existing PV system is not operating properly. Do you want this system to be diagnosed and repaired?
a. Yes.
7. What phase is the power?
a. Single phase.
8. Can you provide information for the current system?
a. Yes, see attached operation and maintenance manuals.
9. Have you contacted the installer of the current system?
a. Yes.
10. Can you provide a site plan?
a. Yes, see attached site plan.
11. Can you provide information from the 2015 energy audit that recommended expansion of the PV system?
Continued ...
NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)
4 4
CONTINUATION SHEET
REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF
(A) (B) (C) (D) (E) (F)
AG-8191-S-16-0012/000001
a. Yes, see attached energy audit sections.
12. Do you require the Buy American Act.
a. Yes, see attached FAR clauses.
13. Do you have any existing soils reports?
a. No.
14. What is the APS main service entrance rated at?
a. 800A.
15. Is a bid bond required?
a. No.
16. Is a project bond required?
a. Yes.
17. Can you verify where the existing underground conduits go to at the PV array and the electrical panel?
a. See attached utility plan.
Period of Performance: 09/15/2016 to 12/31/2016