Amendment 5 Solicitation AG-6424-S-10-0004 - Lost Creek Rehabilitation

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

AG-6424-S-10-0004

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

NRCS-MO-126424

COLUMBIA MO 65203

SUITE 250

601 BUSINESS 70 WEST

USDA-NRCS-MISSOURI STATE OFFICE

NRCS-MO-126424

COLUMBIA MO 65203

SUITE 250

601 BUSINESS 70 WEST

USDA-NRCS-MISSOURI STATE OFFICE

PRIORITY 100802/19/2010000005

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

02/19/2010

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PURPOSE: The purpose of this amendment is to revise the Spcification Index sheet, revise

Specification Page 92-4, and add Material Specification MS 585 for this project.

FIRST: The original Index of Construction Specification sheet is hereby replaced by the attached Index of Construction Specification sheet. This replacement shows the addition of

Material Specification 585.

SECOND: The original Specification Sheet 92-4 is hereby replaced by the attached

Specification Sheet 92-4. This replacement revises statements made in 11, Item of Work and

Construction Details.

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

MARK R. LUCKRITZ

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 5

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

AG-6424-S-10-0004/000005

THIRD: The attached Material Specification 585 is hereby added to this Solicitation.

FOURTH: Except as provided herein, all other terms and conditions of the original Solicitation remain in full force and effect.

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

Structure B-2 Lost Creek Watershed NRCS-Missouri (92-4) 09/09

11. ITEM OF WORK AND CONSTRUCTION DETAILS

Item of work to be performed in conformance with this specification and the construction details therefore are:

a. Bid Item 10, Medium Duty Fence

(1) This item shall consist of all materials and labor needed to install medium duty (Type I Barbed) fence as shown on the drawings.

(2) Minimum barbed wire size is 14 gauge.

(3) Payment shall be made as described in Section 10.

NRCS-NEH 642 585-1 2/2002

MATERIAL SPECIFICATION

585. WOOD PRESERVATIVES AND TREATMENT

1. SCOPE

This specification covers the quality of wood preservatives and methods of treatment of wood products.

2. TREATING PRACTICES

Treating practices and sampling, inspection and test procedures shall conform to the requirements of ASTM D 1760, “Standard Specification for Pressure Treatment of Timber Products”.

3. PRESERVATIVES

The wood shall be treated with the specified type of preservative. Wood preservatives shall conform to the requirements of the applicable specifications list in ASTM D 1760.

4. QUALITY OF TREATED MATERIALS

Treated lumber, timber, piles, poles, or posts shall be free from heat checks, water bursts, excessive checking, results of chafing or from any other damage or defects that would impair their usefulness or durability for the purpose intended. The use of “s” irons will not be permitted. Holes bored for tests shall be filled with tight fitting treated wood plugs.

5. MARKING

Each treated wood item delivered to the job site shall be marked as specified in ASTM D 1760, unless otherwise specified.