RECOVERY, LOST CREEK WATERSHED REHABILITATION. 1008
Solicitation number
AG-6424-S-10-0004
Issued by

About this file

Amendment 3 Solicitation AG-6424-S-10-0004 - Lost Creek Rehabilitation

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

AG-6424-S-10-0004

x x

1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

NRCS-MO-126424

COLUMBIA MO 65203

SUITE 250

601 BUSINESS 70 WEST

USDA-NRCS-MISSOURI STATE OFFICE

NRCS-MO-126424

COLUMBIA MO 65203

SUITE 250

601 BUSINESS 70 WEST

USDA-NRCS-MISSOURI STATE OFFICE

PRIORITY 100802/19/2010000003

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

02/19/2010

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PURPOSE: The purpose of this amendment is to make a chage to Construction Specification 6

-- Seeding, Sprigging and Mulching.

FIRST: The current Page (6-5) of Construction Specification 6 -- Seeding, Sprigging and

Mulching, is hereby replaced by the attached Page (6-5) of Construction Specification 6 --

Seeding, Sprigging and Mulching.

SECOND: Except as provided herein, all other terms and conditions of the original

Solicitation remain in full force and effect.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

LINDA K. MCARTHUR

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

Structure B-2 Lost Creek Watershed NRCS-Missouri (6-5) 3/10

(7) PLS is pure live seed. Pure live seed percentages in bulk seed is equal to the percent of purity times the percent of germination as shown on the seed tag.

Seed shall be furnished in amounts that equal or exceed the following rates per acre:

Dam, Berms, Auxiliary Spillway, Borrow Area, Parking Area, and Haul

Road Percent Pure Live Seed Species of Mix Rate (lbs. per ac.)

Tall Fescue 100% 24.0

Seeding Dates March 1 through May 15 August 16 through October 15

(8) From May 16 through August 15, seeding can be done when the following conditions exist:

1. Soil moisture on the site is at field capacity at time of seeding;

2. Planting rates are increased by an additional 50 percent;

3. An adequate, firm and weed-free seedbed has been prepared;

4. Seed is planted at a depth of ¼ inch or less with grassland drill or similar quality seeding equipment; and

5. Mulch material is applied following the planting operation

If soil moisture requirement is not satisfied, all operations will be performed except sowing the seed. Overseeding will be done during the next seeding period as seeding dates permit. Increase seeding rates by 50% for overseeding. There will be no tillage during overseeding operation.

(9) Apply seed uniformly at a depth of ⅛ to ¼ inch with drill or cultipacker type seeder or broadcast seed uniformly and cover ⅛ to ¼ inch deep with a cultipacker, harrow, or similar tool. Seeding operation shall be performed immediately after seedbed preparation, if seeding dates permit.

(10) Mulch shall be small grain straw or grass hay relatively free of weed seed.

The mulch shall be applied uniformly over the designated area at a rate of 1.5 tons per acre. Anchor mulch with: (1) mulch tacker into the top one (1) inch of soil, or (2) wood cellulose fibertack or a water dispersible mulch tacker following manufacturer's recommendations, or (3) commercial mulch nets or excelsior blankets. Only Option (2) or (3) shall be permitted in areas that are hydro-seeded.

(11) Insofar as practical, all operations shall be performed on the contour.

(12) Payment shall be made by measuring to the nearest 0.1 acre. This payment will constitute full compensation for the completion of the work.