Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO.

IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14.

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this Amendment is to:

1. Change the required response date and time to August 16, 2017 by 5:00 p.m. CST.

USDA APHIS MRPBS

ASD Procurement Branch Butler Square, 5th Floor 100 N 6th Street Minneapolis, MN 55403

See Item 6

J

9A. AMENDMENT OF SOLICITATION

NO.

AG-6395-S-17-0190

09/21/2017

9B. DATED (SEE ITEM 11)

09/18/2017

The purpose of this Amendment is to:

1. Extend the required response date and time to September 26, 2017 by 5 p.m. (CST).

2. Incorporate Responses to Questions.

3. Revise the Performance Work Statement to incorporate the attachment, Operators Manual, for reference.

X

SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

RESPONSES TO QUESTIONS

1. The hydraulic oil and filter required for each kettle?

Response: 12 U.S. gallons of Tellus 32 hydraulic oil and filter Part # SE5009

2. Will the government have a shop or bench available for any service work that occur during the visit?

Response: No. There is not a shop or bench area available because the kettles are outside.

The Government can provide a cart where the service contractor can place their tools if needed.

3. Would the government have a staff member interested in training or support of the inspection during each visit?

Response: Yes. The contractor shall provide training upon request, and only if changes are made for the operator’s level.

4. Are there available parts in stock for any quick repairs that could be made on the kettles during the visit?

Response: No. Please refer to the Performance Work Statement. The contractor is responsible for furnishing all materials, equipment and labor, and for performing all work under the contract in a complete and acceptable manner.