Bid Schedule Revised Amend 1.pdf
PDF 9 KB Posted
- Attached to
- McPherson County, Kansas, WRP Project
- Solicitation number
- AG-6215-S-11-0019
About this file
Amendment No. 1 Revised Bid Schedule
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Signed Abstract of Offers.pdf | ||
| Question Responses 2.pdf | ||
| Schmidt WRP Mowing Plan 1.pdf | ||
| SF30.pdf | ||
| Bid Schedule Dale Schmidt WRP Revised.pdf | ||
| Revised_Location_Quantities.pdf | ||
| Schmidt WRP Mowing Plan 2.pdf | ||
| Question Response.pdf | ||
| cs250 Mobilization and Demobilization Revised Amend 1.pdf | ||
| SF30 Amend 1.pdf | ||
| Standard Form | — | |
| Wage Rates.mht | MHT file | |
| SF1199A_with_instructions.pdf | ||
| Construction Drawings.pdf | ||
| Construction Specs.pdf | ||
| Schmidt Solicitation Packet 1.doc | DOC document |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
8/15/2011
McPherson County
Item Spec. Unit No. Work or Material No. Quantity Unit Price Amount
1 Mobilization and Demobilization 250 LUMP SUM xxxxx
2 Seeding and Mulching 253 22.0 Ac
3 Earthfill, Dike and Ramp Spillways 254 67,800 Cu.Yd.
4 Excavation, Existing Dike 255 4,110 Cu.Yd.
5 Plastic Pipe, 12-Inch Diameter 256 195 Lin.Ft.
6 Water Level Control Structure, 12-Inch 256 LUMP SUM xxxxx
7 Chemical Weed Control 267 22.0 Ac
8 Site Preparation (Mowing) 250 LUMP SUM xxxxx
Total
Dale Schmidt WRP
BID SCHEDULE