Bid_Results_for_Posting_6-10-13.xlsx
XLSX spreadsheet 12 KB Posted
- Attached to
- Trenton Wetland Reserve Program (WRP) Wetland Restoration Project, Trenton Township, Dodge County, WI
- Solicitation number
- AG-5F48-S-13-0006
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Signed_Amendment_1.pdf | ||
| Solicitation _Offer _and_Award-Standard_Form_1442 _Section_A.pdf | ||
| Att_3_WI15_dvb.mht | MHT file | |
| Att_6_SAM_Guide.doc | DOC document | |
| Solicitation_Sections_B_through_M.docx | DOCX document | |
| Att_4_WRP_SPECS_TRENTON2013.pdf | ||
| Att_2_Trenton_WRP_location_map2.jpg | JPG image | |
| Att_5_TRENTON_WRP_2013_Plans.pdf | ||
| Att_1_Trenton_WRP_location_map.jpg | JPG image |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Savoy
| Bid Results for Trenton WRP Restoration Project - Dodge County |
| AG-5F48-S-13-0006, due 6/10/13 at 2pm CST |
| The work consists of the following: Approximately 1600’ of ditch fill; Excavation of 5 shallow water scrape (borrow) areas; Approximately 7530 cubic yards of spoil placement and shaping 2695’ of tile exploration (tile search); 5750’ of tile line removal; Seeding of all areas disturbed during construction; Approximately 0.4 acres of brush removal; 100’ of silt fence installation; and Providing post-construction seeding of disturbed areas. |
| Line Item | Town & Country Underground Utility Construction Inc | Solutions 101 LLC | Kinas Excavating Inc | Wondra Construction Inc | Curtis Excavating Inc | Dunneisen Excavating LLC | ||||||
| Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | Unit Price | Amount | |
| 1 - Mobilization/ Demobilization | $4,320.00 | $5,790.25 | $7,600 | $3,800.00 | $2,500 | $2,100 | ||||||
| 2 - Clearing | $1.30 | $3,000.00 | $2,711.25 | $3,000 | $2.50 | $800.00 | $1.50 | $1,200 | $1,800 | |||
| 3 - Tile Search | $1.30 | $3,503.50 | $4,392.85 | $6,750 | $2.50 | $6,737.50 | $1.50 | $4,042 | $2,156 | |||
| 4 - Tile Removal | $7,527.00 | $14,243.40 | $14,375 | $14,475.00 | $8,685 | $4,632 | ||||||
| 5 - Excavation/ Earthfill | $39,500.00 | $84,300.00 | $41,500 | $30,800.00 | $37,290 | $37,100 | ||||||
| 6 - Construction Site Pollution Control | $1,000.00 | $1,361.35 | $200 | $500.00 | $300 | $150 | ||||||
| 7 - Seeding | $12,000.00 | $17,811.20 | $4,000 | $6,700.00 | $12,000 | $5,500 |
Total $70,850.50 $130,610.30 $77,425 $63,812.50 $66,017 $53,438