DEMOLITION/REMOVAL OF STRUCTURES
MIDEWIN NATIONAL TALLGRASS PRAIRIE
AG-56A1-S-16-0010
SCOPE OF WORK
BACKGROUND:
The Midewin National Tallgrass Prairie (MNTP) is made up of approximately 19,000 acres of land that previously belonged to the US Army Arsenal, Joliet, IL. The Army constructed buildings and structures to support their activities. Most structures were constructed between 1940 and 1960. Over time, virtually all army structures will be removed to facilitate the prairie restoration of the MNTP. Many of the structures are currently in place and not currently in use.
The Forest Service (FS) has a requirement for a Performance Based Service Blanket Purchase Agreement (BPA) for Prairie Wide Demolition/Removal of GROUP 811 BUNKERS in preparation for the restoration of the MNTP. Contractors shall provide all expertise, labor, supervision, services, equipment, tools, supplies, materials, permits, licenses, transportation, and incidentals necessary to perform the required work, for which the desired outcome is in strict accordance with the standards incorporated into each BPA and each BPA Call (the actual order placed against a BPA). There will be no work guaranteed on a BPA and the FS may accomplish work by other methods at their discretion.
BPA calls will require work that includes removal and disposal of structures, structural components and structure contents. This work shall also include minor restoration/stabilization of the site where structures are removed (i.e., seeding/mulching to mitigate short term soil erosion). Structures include storage bunkers (igloo style), railroad grades, railroad ties, road surface, road base, culverts, and miscellaneous debris. Some work will require removal and disposal of hazardous materials that require special handling/disposal. Contractors will be required to dismantle, remove and dispose off-site the structural debris in accordance with requirements and standards established in this BPA, existing laws, regulations, and industry standards applicable to any materials removed and disposed.
SCHEDULE OF WORK ITEMS
| 1. Bunker (including foundation) removal in Group 811 on the west side of Midewin. |
| Remove and dispose/recycle off site bunker and foundation two (2) feet below grade; final grade the work area. Unit cost below shall also include obliteration and re-grading of approximately 500 linear feet by 80 foot width of road/railbed associated with each bunker. (250’ linear feet north and south of the bunker centerline) Existing Bunker numbers are listed below: |
| 811001 |
| BUNKER | |
| 811070 | |
| BUNKER | |
| 811107 | |
| BUNKER | |
| 811005 |
| BUNKER |
| 811071 |
| BUNKER |
| 811108 |
| BUNKER |
| 811006 |
| BUNKER |
| 811072 |
| BUNKER |
| 811109 |
| BUNKER |
| 811007 |
| BUNKER |
| 811073 |
| BUNKER |
| 811110 |
| BUNKER |
| 811008 |
| BUNKER |
| 811074 |
| BUNKER |
| 811111 |
| BUNKER |
| 811009 |
| BUNKER |
| 811079 |
| BUNKER |
| 811112 |
| BUNKER |
| 811010 |
| BUNKER |
| 811080 |
| BUNKER |
| 811113 |
| BUNKER |
| 811016 |
| BUNKER |
| 811081 |
| BUNKER |
| 811114 |
| BUNKER |
| 811020 |
| BUNKER |
| 811082 |
| BUNKER |
| 811115 |
| BUNKER |
| 811021 |
| BUNKER |
| 811083 |
| BUNKER |
| 811116 |
| BUNKER |
| 811022 |
| BUNKER |
| 811084 |
| BUNKER |
| 811117 |
| BUNKER |
| 811023 |
| BUNKER |
| 811085 |
| BUNKER |
| 811118 |
| BUNKER |
| 811024 |
| BUNKER |
| 811086 |
| BUNKER |
| 811119 |
| BUNKER |
| 811030 |
| BUNKER |
| 811087 |
| BUNKER |
| 811120 |
| BUNKER |
| 811036 |
| BUNKER |
| 811088 |
| BUNKER |
| 811121 |
| BUNKER |
| 811037 |
| BUNKER |
| 811089 |
| BUNKER |
| 811122 |
| BUNKER |
| 811038 |
| BUNKER |
| 811090 |
| BUNKER |
| 811123 |
| BUNKER |
| 811039 |
| BUNKER |
| 811091 |
| BUNKER |
| 811124 |
| BUNKER |
| 811043 |
| BUNKER |
| 811092 |
| BUNKER |
| 811125 |
| BUNKER |
| 811044 |
| BUNKER |
| 811093 |
| BUNKER |
| 811126 |
| BUNKER |
| 811045 |
| BUNKER |
| 811094 |
| BUNKER |
| 811127 |
| BUNKER |
| 811050 |
| BUNKER |
| 811095 |
| BUNKER |
| 811128 |
| BUNKER |
| 811051 |
| BUNKER |
| 811096 |
| BUNKER |
| 811129 |
| BUNKER |
| 811052 |
| BUNKER |
| 811097 |
| BUNKER |
| 811130 |
| BUNKER |
| 811053 |
| BUNKER |
| 811098 |
| BUNKER |
| 811131 |
| BUNKER |
| 811057 |
| BUNKER |
| 811099 |
| BUNKER |
| 811132 |
| BUNKER |
| 811058 |
| BUNKER |
| 811100 |
| BUNKER |
| 811059 |
| BUNKER |
| 811101 |
| BUNKER |
| 811065 |
| BUNKER |
| 811102 |
| BUNKER |
| 811066 |
| BUNKER |
| 811103 |
| BUNKER |
| 811067 |
| BUNKER |
| 811104 |
| BUNKER |
| 811068 |
| BUNKER |
| 811105 |
| BUNKER |
| 811069 |
| BUNKER |
| 811106 |
| BUNKER |
| 2. Seed & Mulch work area (contractor shall supply seed and mulch) |
| Apply pasture grass mix to disturbed areas in item 1 above at the minimal of 50 lbs./acre and mulch with straw or other Midewin NTP approved mulch. Seed mix is as follows: |
spring oats - 25 lbs/acre perennial ryegrass - 10 lbs acre redtop - 5 lbs acre bluegrass - 5 lbs acre Hungarian (smooth) brome grass - 5 lbs acre No fertilizer.
Sq. Yard
The contractor shall recycle all applicable demolition waste including but not limited to brick, steel and concrete, unless otherwise approved by the USDA Forest Service Contracting Officer’s Representative (COR). The contractor shall submit to the COR in a timely manner all available weight tickets for the removed materials, recycled and landfilled. Contractors shall also provide a copy of hazardous material handling certificates, location of the waste site and destination locations for reusable and recyclable materials.
| Material Type |
| Material Examples |
| Disposition |
| Comments |
1. Land clearing debris
| Landscape material |
| Contractor to Shred/chip and |
Stockpile on Midewin Stockpile location to be provided on each BPA Call
2. Ferrous Metal
| Structural steel |
| Contractor re-use or recycle as scrap |
| Remove from Midewin |
| Piping/conduit/culverts and appurtenances |
| Contractor to re-use or recycle as scrap |
| Remove from Midewin |
| Sheet metal, decking and piling |
| Contractor to re-use or recycle as scrap |
| Remove from Midewin |
| Recovered concrete reinforcing |
| Contractor to re-use or recycle as scrap |
| Remove from Midewin |
| Non-structural framing |
| Contractor to re-use or recycle as scrap |
| Remove from Midewin |
| Doors window and hardware |
| Contractor to re-use or recycle as scrap |
| Remove from Midewin |
| HVAC |
| Contractor to re-use or recycle as scrap |
| Remove from Midewin |
| Light poles or mounts |
| Contractor to re-use or recycle as scrap |
| Remove from Midewin |
3. Non-ferrous Metal
| Structural aluminum |
| Contractor to re-use or recycle as scrap |
| Remove from Midewin |
| Other aluminum |
| Contractor to re-use or recycle as scrap |
| Remove from Midewin |
| Copper, brass, bronze |
| Contractor to re-use or recycle as scrap |
| Remove from Midewin |
| HVAC |
| Contractor to re-use or recycle as scrap |
| Remove from Midewin |
| Other |
| Contractor to re-use or recycle as scrap |
| Remove from Midewin |
4. Asbestos
| Friable |
| Contractor to properly remove, handle and landfill |
| Remove from Midewin |
| Transite, non-friable |
| Contractor to properly remove, handle and landfill |
| Remove from Midewin |
| Asbestos-containing items such as doors, boilers, window glazing, ceiling tiles |
| Contractor to properly remove, handle and landfill |
| Remove from Midewin |
Asbestos-containing Floor tile
| Contractor to properly remove, handle and landfill |
| Remove from Midewin |
Asbestos-containing siding
| Contractor to properly remove, handle and landfill |
| Remove from Midewin |
Asbestos-containing Refractory/fire brick
| Contractor to properly remove, handle and landfill |
| Remove from Midewin |
5. Concrete
| Paving/masonry |
| Contractor to re-use, recycle as aggregate |
| Remove from Midewin |
| Drainage structures |
| Contractor to re-use, recycle as aggregate |
| Remove from Midewin |
| Structural |
| Contractor to re-use, recycle as aggregate |
| Remove from Midewin |
| Other reinforced |
| Contractor to re-use, recycle as aggregate |
| Remove from Midewin |
6. Asphalt
| Bituminous paving |
| Contractor to recycle at asphalt plant. Prairie View |
Landfill may accept as road material.
Remove from Midewin
7. Brick
| Pavers/flooring |
| Contractor to re-use, recycle as aggregate |
| Remove from Midewin or stockpiled as specified on each BPA Call |
| Masonry |
| Contractor to re-use, recycle as aggregate. Prairie View Landfill may accept for roads. |
| Remove from Midewin |
| Clay, ceramic, concrete, slate roofing |
| Contractor to re-use, recycle as aggregate |
| Remove from Midewin |
| Brick/refractory |
| Contractor to re-use, recycle as aggregate |
| Remove from Midewin |
8. Stone
| Pavers/flooring |
| Contractor to re-use, recycle as aggregate |
| Remove from Midewin or stockpiled as specified on each BPA Call |
| masonry |
| Contractor to re-use, recycle as aggregate |
| Remove from Midewin or stockpiled as specified on each BPA Call |
| aggregate |
| Contractor to re-use, recycle as aggregate |
| Remove from Midewin or stockpiled as specified on each BPA Call |
9. Wood
| Poles - any |
| Contractor to re-use or recycle, shred/chip |
| Landfill may accept shredded/chipped for roads use. Wilmington Park District may accept for reuse. |
| Structural members |
| Contractor to re-use or recycle, shred/chip |
| Landfill may accept shredded/chipped for roads use |
| Sheathing, flooring |
| Contractor to re-use or recycle, shred/chip |
| Landfill may accept shredded/chipped for roads use |
| windows |
| Contractor to re-use or recycle, shred/chip |
| Landfill may accept shredded/chipped for roads use |
10. Light fixtures
| Lighting fixtures |
| Contractor to re-use or recycle |
| Remove from Midewin |
| PCB ballast in fluorescent lights |
| See “Capacitors” in “Other” below |
| Lamps |
| Contractor to re-use or recycle |
| Remove from Midewin |
11. Other
| Capacitors – PCB or other |
| Contractor to recycle, if PCB then dispose |
| Remove from Midewin |
| Motor/hydraulic Oil |
| Contractor to recycle |
| Remove from Midewin |
| Mercury Switches |
| Contractor to recycle |
| Remove from Midewin |
| Glass, including reinforced glass |
| Contractor to recycle |
| Remove from Midewin |
| Vinyl siding |
| Contractor to recycle |
| Remove from Midewin |
| Rigid insulation board |
| Landfill or other arrangement |
| Remove from Midewin. There may be ways to recycle these materials or re-use them, but the quantity and condition of these materials may be limiting factors. |
| Insulation batting |
| Landfill or arrange for recycle |
| Asphalt roofing |
| Landfill or arrange for recycle |
| Specialty doors |
| Landfill or arrange for recycle |
| Carpet and padding |
| Landfill or arrange for recycle |
| Non-ACM ceiling tile |
| Landfill or arrange for recycle |
| Equipment and furnishings |
| Contractor to recycle, scrap |
| Remove from Midewin |
END
Contractors shall provide ACM inspection performed and signed by an Illinois Licensed ACM inspector to satisfy State of Illinois requirements prior to demolition. The contractor will be responsible for submitting the proper notification to the Illinois EPA, including asbestos testing results, as required for any demolition within the state. A copy of the inspection report and state notification shall be submitted to the COR before any payment will be made for demolition.
Burning of materials is not permitted. Many of the materials originating from MNTP will be accepted at the adjacent Prairie View Landfill (PVL) however it is the contractor’s responsibility to make all disposal arrangements.
Contractor shall work in such a manner so as to minimize the release of dust into the air. When excessive dust is being generated, as determined by the Contracting Officer’s Representative (C.O.R.), the contractor shall be required to use water from a source designated by the USDA Forest Service to suppress dust release.
The contractor shall recycle all applicable demolition waste including but not limited to brick, steel and concrete, unless otherwise approved by the USDA Forest Service Contracting Officer’s Representative (C.O.R.). The contractor shall submit in a timely manner to a designated representative of the USDA Forest Service all available weight tickets for the removed materials, recycled and landfilled.
The Contractor will ensure spill cleanup materials will be available on each project at all times on the Prairie. Any spill greater than one (1) pint must be immediately reported to the COR or PM. Contractor personnel must have training to ensure they are qualified to identify such releases and are competent to provide proper cleanup and reporting. All spilled materials and impacted soils will be removed and properly disposed as necessary.
Contractors must avoid remaining contaminated Army land in or near the work area, and must be aware of the potential for discovery of CERCLA wastes, TSCA (PCB) equipment, or remnant ordnance materials (Munitions and Explosives of Concern (MEC)). Contractors shall notify the COR of any discovered suspicious material, equipment or items encountered during work.
Equipment will be inspected at the time it is delivered to the job. Equipment that is not free of soil and debris that could carry invasive plant species from prior worksites or equipment that does not meet contract specifications may be rejected. Rejected equipment will be replaced or the deficiencies corrected. If the equipment cannot perform on site it may also be removed or replaced.
Contractor shall avoid heavy equipment in sensitive areas during times when the soil is soft. Contractor may enter when ground is dry or frozen or with vehicles that have a low ground pounds-per-square-inch loading (not to exceed 4). Work is to halt if thawing or heavy precipitation occurs. Any soil or other resource damage (rutting deeper than two inches, tracking, etc.) shall be mitigated by the contractor using conservation techniques such as baffling, erosion netting, siltation fence, seeding and mulching.
Soil or other resource damage (rutting deeper than two inches, tracking, etc.) shall be mitigated by the contractor using conservation techniques. Soil from the any excavation required to complete a task order shall be stockpiled and surrounded by siltation fencing. USDA Forest Service Contracting Officer’s Representative (C.O.R.) will approve the layout of the siltation fencing.
Contractor is responsible for complying with “call before you dig” regulations before performing surface disturbing activities.
DEFINITIONS
| 1 | BPA: Blanket Purchase Agreement: A non-binding simplified method of filling anticipated repetitive needs for supplies or services by establishing an agreement with qualified sources of supply. |
| 2 | BPA Call: An award on Form OF-347 for work covered by a BPA. |
| 3 | Acceptable Quality Level (AQL): The maximum percent defective work that may occur before the FS will employ price deducts in accordance with the Inspection clause of the contract. |
| 4 | Defective Service: A unit of service which contains one or more defects, or nonconformance with specified requirements. |
| 5 | Quality Control: Those actions taken by a contractor to control the performance of services so that they meet the specified requirements. |
| 6 | Quality Assurance: Those actions taken by the FS to assure services meet the specified requirements. |
| 7 | COR: Contracting Officer’s Representative -A FS employee that is appointed and officially designated by the Contracting Officer to assist the Contracting Officer with technical matters related to contract administration. The COR will assist the Contracting Officer with surveillance of contractor performance. |
| 8 | FS Inspector: A FS employee designated by the Contracting Officer or COR to perform surveillance of contractor performance. |
| 9 | CSI: Construction Specifications Institute |
FS FURNISHED PROPERTY, MATERIALS AND SERVICES
General: The FS shall provide, without cost, the facilities, equipment, materials, and/or services listed below.
FS Furnished Materials:
1. Key for contractor gate access (cost of replacement for key not returned after work is completed will be paid by the contractor at the actual cost for changing the affected locks)
FS Furnished Facilities:
1. Overnight/weekend parking for Contractor equipment (unsecured)
2. Storage areas for materials (unsecured)
CONTRACTOR FURNISHED ITEMS AND SERVICES
General: Except for those items or services specifically stated to be furnished by the FS, the contractor shall furnish everything required to perform the work of this contract, task order, and/or attachment(s) to the Acceptable Quality Level indicated in said contract, task order, and/or attachment(s).
QUALITY ASSURANCE PLAN
| REQUIREMENT |
| TASKS/CRITICAL |
SUB-TASKS
QUALITY
STDS
1.
Demolition
1.a. Superstructure
| Take down superstructure in a safe, environmentally compliant, and efficient manner. |
| Superstructure is completely dismantled or disconnected from any foundation in accordance w/CSI and any other applicable State, local or industry standards. |
| 100% |
| Visual 100% |
1.b. Foundation (no basement)
| Break up top 2 feet of foundation materials and remove as needed. Use native fill materials from site surrounding the work site as approved by the FS. |
| All foundation materials will be removed to a level of 2’ below finished grade and covered with fill. No foundation material, including broken pieces, shall remain within the top two feet of finish grade. |
| 100% |
| Visual 100% |
Removal:
Gather Segregate Load/haul Staging/stockpiling
Gather all materials from demolition unless otherwise noted; properly segregate waste; load and haul materials to the staging/stockpiling area (if necessary)
Demolition materials are completely removed from the demo site and properly staged in an orderly manner at the designated staging areas only. Materials shall not exist outside their staging areas.
100%
Visual 100%
Disposal On-site Off-site Special treatment Documentation
| Demolition materials designated by the USFS to be disposed on-site shall be disposed at their designated location in a timely, safe and compliant manner. Demo materials designated by the USFS for off-site disposition shall be completely removed from the USFS property and disposed in compliance with all local, state, and federal regulations. The contractor shall acquire all necessary documentation and any special waste treatments. |
| Materials to be disposed shall be completely vacant from the demolition and staging areas. |
On-site disposal areas shall be safe and in compliance with all applicable local, state and federal rules.Demo materials to be disposed off-site shall be disposed in a manner that complies with all local, state, and federal regulations regarding the material and will be accompanied with all necessary documents and treatments.
Document Review 100%
Reuse/Recycling Segregate Load/haul Documentation
| Demo material designated to be reused or recycled shall be segregated from material to be disposed. Recycled material shall be loaded and hauled to designated staging or recycling area. The contractor shall obtain applicable documentation. |
| Recyclable or reusable material is completely removed from the demolition site, staged in the designated area and in the best condition possible from the demolition. |
All applicable local, state, and federal documents are acquired.
90 – 100% Visual 90 – 100%
Document Review 100%
Site Restoration Backfill compaction contouring seed/mulch erosion control
| Area to be restored shall be backfilled and compacted with existing on-site soil material. Final grading shall blend in the demo site with the surrounding topography with allowance for further settling. The area shall be seeded and mulched with the designated seed mix by the USFS (contractor shall supply seed and mulch). Any additional erosion control measures shall be taken as needed. |
| The demo site shall blend in with the surrounding topography and absent of any erosion. No signs of soil migration into waterways shall be present. |
| 100% |
| Visual 100% |
| Mitigation/Restoration of any environmental damage |
| Repair all rutting, erosion or other environmental damage |
| Final area will be free of any ruts, erosion or any other signs of obtrusions |
| 100% |
| Visual 100% |