Guest_House_Rehab_Specifications.pdf
PDF 2 MB Posted
- Attached to
- Forest Lodge Guesthouse Rehabilitation Phase II
- Solicitation number
- AG-569R-S-17-0061
About this file
Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Guest_House_First_Floor_Rehabilitation_Plans_August_2017.pdf | ||
| Solicitation.pdf | ||
| Wage_Determination.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
000101
Specifications 2017
Forest Lodge Guest House Rehabilitation
000102 - 1
Forest Lodge Gatehouse Rehabilitation Chequamegon Nicolet National Forest Bayfield County, Wisconsin
TABLE OF CONTENTS
DIVISION 0 – PROCUREMENT AND CONTRACT REQUIREMENTS PAGES THROUGH
(Applied to all Contractors) (Addenda are to be bound in this volume in order of issuance)
000101 Project Title Page 1 000102 Table of Contents 3
DIVISION 01 – GENERAL REQUIRMENTS
011000 Summary of Work 2 012500 Substitution Procedures 2 013300 Submittal Procedures 4 015000 Temporary Facilities and Controls 3 017300 Cutting and Patching 4 017700 Closeout Procedures 2
DIVISION 02 – EXISTING CONDITIONS
024119 Selective Removals 6
DIVISION 03 – CONCRETE
033000 Concrete 5
DIVISION 04 – MASONRY
044300 Stone Masonry 3
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
061000 Rough Carpentry 2 062013 Exterior Finish Carpentry 1
DIVISION 07 – THERMAL AND MOISTURE PR0TECTION
074623 Wood Log Siding 3 079200 Joint Sealants 7
DIVISION 08 – DOORS AND WINDOWS
081400 Wood Doors 4
DIVISION 09 - FINISHES
092000 Gypsum Board 5 096400 Wood Flooring 8 099000 Paint 8 099300 Stains and Varnishes 7
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
230700 HVAC Insulation 4 230933 Electric Control Devices for HVAC 2 233100 HVAC Ducts 4 233713 Diffusers, Registers & Grills 2
000102 - 2
DIVISION 26 - ELECTRICAL
260500 Common Work for Electrical 5 260519 Wire and Cable 3 260526 Grounding and Bonding 3 260529 Hangers and Supports 2 260533 Raceway and Boxes 6 260553 Identification 2 262416 Panel Boards 2 262419 Equipment Wiring Systems 2 262726 Wiring Devices 3 265100 Interior Lighting Fixtures 5
DIVISION 31 – EARTHWORK
311100 Clearing and Grubbing 2 311413 Strip Topsoil 1 312000 Site Excavation, Filling, and Compacting 2 312333 Trenching, Backfilling, and Compacting 3 312500 Erosion Control 2
DIVISION 32 – EXTERIOR IMPROVEMENTS
320190 Site Restoration 2 321116 Granular Subbase Course 1 321123 Crushed Aggregate Base Course 1 321623 Concrete Sidewalk 3
011000 - 1
SECTION 011000
SUMMARY OF WORK
PART 1 – GENERAL
CONDITIONS OF THE CONTRACT
The conditions of the contract relating to the work specified herein also apply to this section. Applicable provisions of Division 00-Procurement and Contracting Requirements, and Division 01- General Requirements shall govern work under this section.
GENERAL REQUIREMENTS
Work in all sections is subject to the provisions of the Instructions to Bidders, General Conditions, Supplementary Conditions, and all other parts of the Contract Documents.
Reference Standards: Each section of the specifications generally includes a list of reference standards. The purpose of this list is to furnish the Contractor with a list of standards normally used for outlining the quality control desired on the project. The lists are not intended to be complete or all inclusive, but serve as a general reference of standards that are regularly referred to.
Materials: Each section of the specifications may include reference to various material types and/or products which may or may not be intended for use on the respective project. Unless otherwise stated, the Contractor will be allowed to furnish only that material listed in the bid proposal documents and/or construction plans.
The Gatehouse building is located on the National Register Listed Forest Lodge Site. This project is subject to Section 106 of the National Historic Preservation Act. All work shall conform to the Secretary of the Interior’s Standards for Rehabilitation, available online.
WORK COVERED BY THE CONTRACT
The Work covered by the Contract Documents is:
Forest Lodge Guest House 2017 Rehab USDA Forest Service Chequamegon Nicolet National Forest Bayfield County, Wisconsin
Project Location:
22230 Garmisch Road, Cable, WI 54821
DESCRIPTION OF WORK
The Work consists of furnishing all labor, materials, taxes, services, equipment, and any other incidental or collateral work or items necessary to complete the project in accordance with the design specifications. The Work shall also include all supervision, general conditions, port-a-john, and dump fees.
011000 - 2
An abbreviated description of the specified Work is as follows:
The project includes updates to the spaces such as insulation, minor carpentry and wall finishes on the first floor of the guesthouse and minor electrical work throughout, as well as provide ADA accessible walkway leading to entrance.
WORK SEQUENCE
Construct work in stages; assure building and adjoining roof areas remain watertight.
CONTRACTOR USE OF PREMISES
Owner will occupy site during construction. Perform construction only during normal working hours 8 am to 5 pm Monday thru Friday, other than holidays, unless otherwise agreed to in advance by Owner. Clean up work areas and return to usable condition at the end of each work period.
Confine operations at site to areas as shown on the drawings.
Assume full responsibility for protection and safekeeping of material and products stored on or off premises.
Move any stored material or products which interfere with operations of Owner or other Contractors.
Obtain and pay for use of additional storage or work areas needed for operation.
Keep driveways and entrances serving premises clear and available to Owner, Owner’s employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
Nonsmoking Buildings: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor-air intakes.
TIME OF COMPLETION
Work shall be totally completed within 5 months of the Notice to Proceed date.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
- END OF SECTION -
012500 - 1
SECTION 012500
SUBSTITUTION PROCEDURES
PART 1 - GENERAL
GENERAL REQUIREMENTS
The conditions of the contract relating to the work specified herein also apply to this section. Applicable provisions of Division 00-Procurement and Contracting Requirements, and Division 01- General Requirements shall govern work under this section.
CONTRACTOR’S OPTIONS
For products specified by naming products or manufacturer’s followed by other words:
Select any product and manufacturer names
Submit request, as required for substitution, for any product not specifically named.
SUBSTITUTION REQUESTS
Owner’s Representative will consider written requests for substitutions, received at least seven (7) days prior to Bid Date (at 5:00 PM); requests received after that time will not be considered.
If proposed substitution is approved, such approvals will be set forth in an Addendum. Bidders shall not rely upon approvals made in any other manner.
After date of contract, the Owner may consider formal requests from Contractor for substitution of products in place of those specified when submitted in accordance with the requirements of this Section. One or more of the following conditions must also be documented:
The substitution must be required for compliance with final interpretation of code requirements or insurance requirements.
The substitution must be due to the unavailability of the specified products, through no fault of the Contractor. The Contractor’s inability to obtain licensing agreements or related manufacturer’s approvals for the specified products does NOT render the specified products unavailable.
The substitution may be requested when subsequent information discloses the inability of the specified products to perform properly or fit in the designated space.
The substitution may be requested when it is clearly seen, in the judgment of the Owner’s Representative that a substitution would be in the Owner’s best interests in terms of cost, time, or other considerations.
Submit two copies of request for substitution. Include in request:
Product identification, including manufacturer’s name and address.
Manufacturer’s literature, including product description, performance and test date, and reference standards.
Name and address of similar projects where product was used and date of installation.
012500 - 2
Itemized comparison of proposed substitution with product or method specified.
Data relating to changes in construction schedule.
For request submitted after bids are received, accurate cost data on proposed substitution in comparison with product or method specified.
In making request for substitution, manufacturer (or contractor where contractor is initiating request) makes the following representations:
They have personally investigated proposed product, and determined that function, appearance, and quality are equal or superior in all respects to that specified.
They will provide the same guarantee for substitution as for product specified.
They will coordinate installation of accepted substitution into Work, making such changes as may be required for Work to be complete in all respects.
The proposed substitution does not affect dimensions shown on the drawings.
The undersigned will pay for changes to the building design, including engineering and detailed costs caused by the requested substitution.
The proposed substitution has no effect on other trades, the construction schedule, or specified warranty requirements.
Maintenance and service parts are available locally for the proposed substitution.
They waive all claims for additional costs related to substitution that subsequently becomes apparent.
Cost data is complete and includes all related costs under this contract, but excludes:
Cost under separate contracts.
Design consultants redesign.
Substitutions will not be considered if:
They are indicated or implied on these shop drawings or product data submittals without request submitted in accordance with this section.
Acceptance will require substantial revision of contract documents.
PART 2 – PRODUCTS (Not used)
PART 3 - EXECUTION (Not used)
013300 - 1
SECTION 013300 – SUBMITTAL PROCEDURES
The conditions of the contract relating to the work specified herein also apply to this section. Applicable provisions of Division 00-Procurement and Contracting Requirements, and Division 01- General Requirements shall govern
WORK INCLUDED
This section specifies administrative and procedural requirements for handling submittals.
GENERAL PROCEDURES
Coordinate submittal preparation with performance of construction activities, and with purchasing or fabrication, delivery, other submittals and related activities. Transmit in advance of performance of related activities to avoid delay.
Coordinate transmittal of different submittals for related elements so processing will not be delayed by the need to review concurrently for coordination. The Owner’s Representative reserves the right to withhold action on a submittal requiring coordination until related submittals are received.
PROCESSING
Allow two weeks for initial review. Allow more time if processing must be delayed for coordination with other submittals. The Owner’s Representative will advise the Contractor when a submittal must be delayed for coordination. Allow two weeks for reprocessing each submittal.
No extension of time will be authorized because of failure to transmit submittals in sufficient advance of the Work to permit processing.
CONTRACTOR'S CONSTRUCTION SCHEDULE
Submit a fully developed, bar-chart type construction schedule, within 30 days of the date established for Commencement of the Work. Provide a separate bar for each construction activity and a vertical line to identify the first working day of each week. Use the breakdown of units of Work as indicated in the "Schedule of Values."
Secure commitments for performing critical construction operations from parties involved. Coordinate each activity with other activities and show proper sequence; include minor elements involved in the construction sequence.
Indicate sequences necessary for completion of related portions.
Coordinate the Construction Schedule with the Schedule of Values, list of subcontracts, Submittal Schedule, progress reports, payment requests and other schedules.
Indicate completion in advance of the date established for Substantial Completion. Indicate Substantial Completion on the Schedule to allow time for the Owner’s Representative's procedures necessary for certification of Substantial Completion.
Distribution of Schedules: Distribute copies of the Construction Schedule to the Owner’s Representative, Owner, subcontractors, and other parties required to comply with scheduled dates. Post copies in the temporary field office.
When revisions are made, distribute to the same parties and post in the same locations.
Updating: Revise each Schedule after each meeting or activity, where revisions have been made. Issue the updated Schedules concurrently with report of each meeting.
013300 - 2
SHOP DRAWINGS
Submit new information, drawn to accurate scale. Indicate deviations from Contract Documents. Do not reproduce Contract Documents or copy standard information as the basis of Shop Drawings. Include the following information:
Dimensions.
Identification of products and materials included.
Notation of coordination requirements.
Notation of dimensions established by field measurement.
Identify shop drawings with:
Title of project and locations.
Owner’s Representative and project name.
Name and address of contractor.
Drawings shall be presented in a clear and thorough manner. Recommended sheet sizes: 8-1/2”x11”, 11”x17”, or 24”x36”. Submit in both hard copy and PDF formats.
FINAL SUBMITTAL
The Contractor shall deliver one copy of all final shop drawings to Owner at completion of project, including, but not limited to:
As built shop drawings.
Written warranties.
Operation/Training Manuals.
Notify the Owner’s Representative in writing, at the time of submission, of any deviations in the submittals from requirements of the contract documents.
Product Data
Collect Product Data into a single submittal for each element or system. Mark each copy to show applicable choices and options. Where Product Data includes information on several products, some of which are not required, mark copies to indicate the applicable information. Include the following information:
Manufacturer's printed recommendations.
Compliance with recognized trade association standards.
Compliance with recognized testing agency standards.
Application of testing agency labels and seals.
Notation of dimensions verified by field measurement.
013300 - 3
Notation of coordination requirements.
Submittals:
Submit a minimum of 3 copies of each required submittal. The Owner’s Representative will retain two, and will return the other marked with action taken and corrections or modifications required.
Unless noncompliance with Contract Document provisions is observed, the submittal may serve as the final submittal.
Distribution:
Furnish copies of final submittal to installers, and others required for performance of construction activities.
Show distribution on transmittal forms. Do not proceed with installation until an applicable copy of Product Data is in the installer's possession.
Do not permit use of unmarked copies of Product Data in connection with construction.
SAMPLES
Submit full-size samples cured and finished as specified and identical to the product proposed. Mount, display, or package samples to facilitate review. Prepare samples to match the Owner’s Representative's sample. Include the following:
Generic description.
Source.
Product name or name of manufacturer.
Compliance with recognized standards.
Availability and delivery time.
Submit samples for review of kind, color, pattern, and texture, for a final check of these characteristics, and a comparison of these characteristics between the final submittal and the component as delivered and installed. Where variations are inherent in the product, submit multiple units that show limits of the variations.
PRELIMINARY SUBMITTALS
Where samples are for selection of characteristics from a range of choices, submit a full set of choices for the product. Preliminary submittals will be reviewed and returned indicating selection and other action.
Submittals:
Except for samples illustrating assembly details, workmanship, fabrication techniques, connections, operation and similar characteristics, submit 3 sets; one will be returned marked with the action taken. Maintain sample sets at the Project site, for quality comparisons.
Unless noncompliance with Contract Document provisions is observed, the submittal may serve as the final submittal.
Sample sets may be used to obtain final acceptance of the construction associated with each set.
013300 - 4
Distribution: Prepare additional sets for subcontractors, manufacturers, fabricators, installers, and others as required for performance. Show distribution on transmittal forms.
Owner’s Representative's Action:
Except for submittals for record, information or similar purposes, where action and return is required, the Owner’s Representative will review each submittal, mark to indicate action taken, and return. Compliance with specified characteristics is the Contractor's responsibility.
Action Stamp: The Owner’s Representative will stamp each submittal with a self-explanatory action stamp. The stamp will be appropriately marked to indicate action taken.
PART 3 – EXECUTION (Not used)
015000 - 1
SECTION 015000
TEMPORARY FACILITIES AND CONTROLS
The conditions of the contract relating to the work specified herein also apply to this section. Applicable provisions of Division 00-Procurement and Contracting Requirements, and Division 01 – General Requirements shall govern
TEMPORARY UTILITIES
The Contractor shall arrange for, obtain, and pay for all temporary utilities necessary to complete the work except as stated otherwise in these Specifications.
Water: The Contractor shall provide whatever water quantities, valves, fittings, and lines as necessary to provide necessary water to the project.
Sewerage: The Contractor shall provide temporary, portable, toilet facilities at the site. Facilities shall be well maintained and shall be removed at the time of substantial completion.
Electrical and lighting: The Contractor shall provide all temporary electric power necessary for his operations. The Owner shall provide the existing lighting. Supplementary lighting, if necessary, shall be provided by the Contractor.
The Contractor shall provide temporary first-aid facilities on the site. Contractor shall coordinate first aid areas with owner’s security service. In the event of an emergency, owner’s building emergency will expedite the necessary emergency response. Owner’s security will direct emergency responders to the exact location necessary.
The Contractor shall provide temporary fire protection as required by federal, state, and local laws and ordinances.
The Contractor shall provide temporary ventilation as required to control dust and fumes in work areas.
The Contractor shall provide adequate heat in the work areas as required to properly conduct the work.
TRAFFIC MAINTENANCE AND CONTROLS
Owner will continue to use the site during the repair work. The Contractor must schedule and arrange his work so as to maintain access to undisturbed parking areas and to the garage and building entrances, exits and ramps.
Interruptions in traffic flow may be permitted but must be scheduled and written approval given by the Owner’s Representative.
Contractor to make provisions for safe exit through work-in-progress areas during an emergency requiring building evacuation.
SECURITY
The Contractor shall provide for the security of materials, supplies and equipment stored at the site. Material and equipment shall not be stored in areas which continue to be used for parking. The Contractor may store equipment and materials in areas in which he is working; otherwise they shall be removed from the site.
015000 - 2
All shipments shall be addressed to the Contractor and he shall be responsible for their receipt, unloading, handling and storage at the site. The Owner’s Agent will not accept deliveries on behalf of the Contractor or his subcontractors or assume any responsibility for security of materials, equipment, or supplies delivered to the site.
SPECIAL CONTROLS
Dust control: The Contractor shall erect, as required, hard-surface enclosures to protect against dust inhalation. The Contractor shall provide for protection for his employees from dust according to OSHA and other environmental agencies having jurisdiction.
Water control: The Contractor shall not permit water to run uncontrolled off of his work or be carried airborne off the site or onto vehicles and persons occupying part of the site. To prevent this, suitable enclosures shall be provided if water or moisture exceed levels acceptable to the Owner’s Representative. Water / moisture shall not be permitted to enter finished spaces below excavation areas.
The Contractor shall institute the necessary measures to prevent/minimize dust, fumes, odors, debris or liquids from this project from entering non-construction areas of the building. This shall include but not be limited to:
Installation of partitions and filter media over all openings and air intakes as necessary.
Prohibited use of open flames, highly volatile solvents, or noxious chemicals without the expressed approval of the Owner’s Representative.
The Contractor shall be responsible for damage to vehicles in or near the building resulting from his operations.
Damage includes excessive dust as well as any damage to vehicles.
The Contractor shall be responsible for maintaining any means of egress required by governing codes for the continued use of the facility. Enclosures which limit the means of egress from the structure shall have provisions for emergency egress through the partition.
The Contractor shall restrict the use of and vent all objectionable or noxious vapors produced. The Contractor shall assume full responsibility for any and all health damage claims caused by noxious vapors produced during work operations.
Hazards control:
Store propane, fuel oil, kerosene and other volatile or flammable materials in covered metal containers and at locations as required by Federal, State, County and City legal requirements, and as approved by the Owner’s Representative.
Prevent the accumulation of wastes which create hazardous conditions.
Provide adequate ventilation during the use of volatile or noxious substances.
Storage location for construction materials and debris shall be arranged with the Owner’s Representative. Prior to any removal, the Contractor shall submit to the Owner’s Representative his plan for confining, collecting and disposal of broken concrete and other waste material as a result of his operations.
The contractor shall temporarily support or remove and replace any plumbing lines, storm sewers, electrical conduit or mechanical ducts that may interfere with the work.
Smoking shall be prohibited during operations where there are combustible/flammable materials present. “NO SMOKING” signs shall be clearly posted in these areas
01 73 00 - 1
SECTION 01 73 00
CUTTING AND PATCHING
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes procedural requirements for cutting and patching.
B. Related Sections include the following:
1. Division 1 Section 01 73 20 "Selective Removals" for demolition of selected portions of the building.
1.3 DEFINITIONS
A. Cutting: Removal of in-place construction necessary to permit installation or performance of other Work.
B. Patching: Fitting and repair work required to restore surfaces to original conditions after installation of other Work.
1.4 SUBMITTALS
A. Cutting and Patching Proposal: Submit a proposal describing procedures at least 5 working days before the time cutting and patching will be performed, requesting approval to proceed.
1.5 QUALITY ASSURANCE
A. Structural Elements: Do not cut and patch structural elements in a manner that could change their load-carrying capacity or load-deflection ratio.
B. Operational Elements: Do not cut and patch operating elements and related components in a manner that results in reducing their capacity to perform as intended or that results in increased maintenance or decreased operational life or safety. Operating elements include the following:
1. Primary operational systems and equipment.
2. Air or smoke barriers.
3. Mechanical systems piping and ducts.
01 73 00 - 2
4. Control systems.
5. Communication systems.
6. Electrical wiring systems.
C. Miscellaneous Elements: Do not cut and patch miscellaneous elements or related components in a manner that could change their load-carrying capacity, that results in reducing their capacity to perform as intended, or that results in increased maintenance or decreased operational life or safety. Miscellaneous elements include the following:
1. Water, moisture, or vapor barriers.
2. Membranes and flashings.
3. Piping, ductwork, vessels, and equipment.
D. Visual Requirements: Do not cut and patch construction in a manner that results in visual evidence of cutting and patching. Do not cut and patch construction exposed on the exterior or in occupied spaces in a manner that would, in Architect's opinion, reduce the building's aesthetic qualities. Remove and replace construction that has been cut and patched in a visually unsatisfactory manner.
E. Cutting and Patching Conference: Before proceeding, meet at Project site with parties involved in cutting and patching, including mechanical and electrical trades. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding.
1.6 WARRANTY
A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during cutting and patching operations, by methods and with materials so as not to void existing warranties.
PART 2 - PRODUCTS
2.1 MATERIALS
A. General: Comply with requirements specified in other Sections.
B. In-Place Materials: Use materials identical to in-place materials. For exposed surfaces, use materials that visually match in-place adjacent surfaces to the fullest extent possible.
1. If identical materials are unavailable or cannot be used, use materials that, when installed, will match the visual and functional performance of in-place materials.
01 73 00 - 3
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine surfaces to be cut and patched and conditions under which cutting and patching are to be performed.
1. Compatibility: Before patching, verify compatibility with and suitability of substrates, including compatibility with in-place finishes or primers.
2. Proceed with installation only after unsafe or unsatisfactory conditions have been corrected.
3.2 PREPARATION
A. Temporary Support: Provide temporary support of Work to be cut.
B. Protection: Protect in-place construction during cutting and patching to prevent damage.
Provide protection from adverse weather conditions for portions of Project that might be exposed during cutting and patching operations.
C. Adjoining Areas: Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.
3.3 PERFORMANCE
A. General: Employ skilled workers to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time, and complete without delay.
1. Cut in-place construction to provide for installation of other components or performance of other construction, and subsequently patch as required to restore surfaces to their original condition.
B. Cutting: Cut in-place construction by sawing, drilling, breaking, chipping, grinding, and similar operations, including excavation, using methods least likely to damage elements retained or adjoining construction. If possible, review proposed procedures with original Installer; comply with original Installer's written recommendations.
1. In general, use hand or small power tools designed for sawing and grinding, not hammering and chopping. Cut holes and slots as small as possible, neatly to size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.
2. Finished Surfaces: Cut or drill from the exposed or finished side into concealed surfaces.
3. Concrete & Masonry: Cut using a cutting machine, such as an abrasive saw or a diamond-core drill.
4. Mechanical and Electrical Services: Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after cutting.
5. Proceed with patching after construction operations requiring cutting are complete.
01 73 00 - 4
C. Patching: Patch construction by filling, repairing, refinishing, closing up, and similar operations following performance of other Work. Patch with durable seams that are as invisible as possible. Provide materials and comply with installation requirements specified in other Sections.
1. Inspection: Where feasible, test and inspect patched areas after completion to demonstrate integrity of installation.
2. Exposed Finishes: Restore exposed finishes of patched areas and extend finish restoration into retained adjoining construction in a manner that will eliminate evidence of patching and refinishing.
a. Clean piping, conduit, and similar features before applying paint or other finishing materials.
b. Restore damaged pipe covering to its original condition.
3. Floors and Walls: Where walls or partitions that are removed extend one finished area into another, patch and repair floor and wall surfaces in the new space. Provide an even surface of uniform finish, color, texture, and appearance. Remove in-place floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.
a. Where patching occurs in a painted surface, apply primer and intermediate paint coats over the patch and apply final paint coat over entire unbroken surface containing the patch. Provide additional coats until patch blends with adjacent surfaces.
4. Ceilings: Patch and repair ceilings as necessary to provide an even-plane surface of uniform appearance.
5. Exterior Building Enclosure: Patch components in a manner that restores enclosure to a weathertight condition.
D. Cleaning: Clean areas and spaces where cutting and patching are performed. Completely remove paint, mortar, oils, putty, and similar materials.
END OF SECTION
017700- 1
SECTION 017700
CLOSEOUT PROCEDURES
The conditions of the contract relating to the work specified herein also apply to this section. Applicable provisions of Division 00-Procurement and Contracting Requirements, and Division 01- General Requirements shall govern work under this section.
THIS SECTION CONTAINS THE FOLLOWING:
Conformance Statement - 1 page
Contractor’s Affidavit of Payment of Debts and Claims (Sample) – AIA Document G706 – 1994 Edition - 1 page
Contractor’s Affidavit of Release of Liens (Sample) – AIA Document G706A – 1994 Edition – 1 page
Consent Of Surety to Final Payment (Sample) - AIA Document G707 - 1994 Edition - 1 page
Architect/Owner may request additional documentation from subcontractors or suppliers.
FINAL WAIVERS OF LIEN FROM:
Prime Contractor
Sub Contractors
Product Supplier
Others as requested by Owner’s Representative
PART 3 – EXECUTION (Not used)
017700- 2
Conformance Statement
Contractor:
Address:
Phone:
Fax:
The above-titled project has been completed in accordance with the requirements of the Contract.
Signature Date
Printed name Title
02 41 19 - 1
SECTION 02 41 19
SELECTIVE REMOVALS
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes the following:
1. Demolition and removal of selected portions of building or structure.
2. Demolition and removal of selected site elements.
3. Salvage of existing items to be reused or recycled.
4. Protection of Materials & Surfaces to remain
1.3 DEFINITIONS
A. Remove: Detach items from existing construction and legally dispose of them off-site, unless indicated to be removed and salvaged or removed and reinstalled.
B. Remove and Salvage: Detach items from existing construction and store in designated area.
C. Remove and Reinstall: Detach items from existing construction, prepare them for reuse, and reinstall them where indicated.
D. Existing to Remain: Existing items of construction that are not to be removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.
1.4 MATERIALS OWNERSHIP
A. Historic items, relics, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, doors, windows, hardware, woodwork, antiques, and other items of interest or value to Owner that may be encountered during selective demolition remain Owner's property. Carefully remove and salvage each item or object in a manner to prevent damage and deliver promptly to Owner.
1.5 SUBMITTALS
A. Inventory: After selective removal is complete, submit a list of items that have been removed and salvaged.
02 41 19 - 2
B. Pre Selective removal photographs: Show existing conditions of adjoining construction and site improvements, including finish surfaces, that might be misconstrued as damage caused by selective demolition operations.
1.6 QUALITY ASSURANCE
A. Selective Removal Firm Qualifications: An experienced firm that has specialized in demolition work similar in material and extent to that indicated for this Project.
B. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective removal. Comply with hauling and disposal regulations of authorities having jurisdiction.
C. Standards: Comply with ANSI A10.6 and NFPA 241.
1.7 WARRANTY
A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials so as not to void existing warranties.
PART 2 - EXECUTION
2.1 EXAMINATION
A. Verify that utilities have been disconnected and capped.
B. Survey existing conditions and correlate with requirements indicated to determine extent of selective demolition required.
C. Inventory and record the condition of items to be removed and reinstalled and items to be removed and salvaged.
D. Protect all items to remain in place during selective demolition work. Provide materials and barriers to prevent damage to existing building elements. Protection materials shall remain in place at all times and shall be removed only when work to that specific area is being performed
E. Protect all items to be removed, stored, refinished and re-used from further damage during construction. Provide and maintain protection materials and barriers that prevent damage.
F. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict.
Promptly submit a written report to Architect.
G. Engage a professional engineer to survey condition of building to determine whether removing any element might result in structural deficiency or unplanned collapse of any portion of structure or adjacent structures during selective demolition operations.
02 41 19 - 3
H. Survey of Existing Conditions: Record existing conditions by use of preconstruction photographs.
1. Before selective removal or removal of existing building elements that will be reproduced or duplicated in final Work, make permanent record of measurements, materials, and construction details required to make exact reproduction. If removal does not require complete destruction, salvage items to be reproduced to use as templates for new fabrications
I. Perform surveys as the Work progresses to detect hazards resulting from selective demolition activities.
2.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS
A. Existing Services/Systems: Maintain services/systems indicated to remain and protect them against damage during selective demolition operations.
1. Comply with requirements for existing services/systems interruptions specified in Division 1 Section "Summary."
B. Service/System Requirements: Locate, identify, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished.
1. Owner will arrange to shut off indicated services/systems when requested by Contractor.
2. Arrange to shut off indicated utilities with utility companies.
3. If services/systems are required to be removed, relocated, or abandoned, before proceeding with selective demolition provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.
4. Cut off pipe or conduit in walls or partitions to be removed. Cap, valve, or plug and seal remaining portion of pipe or conduit after bypassing.
a. Where entire wall is to be removed, existing services/systems may be removed with removal of the wall.
2.3 PREPARATION
A. Site Access and Temporary Controls: Conduct selective removals and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
1. Comply with requirements for access and protection specified in Division 1 Section "Temporary Facilities and Controls."
B. Protection of materials to Remain: Protect all items to remain in place during selective removal work. Provide materials and barriers to prevent damage to existing building elements, components and finishes. Protection materials shall remain in place at all times and shall be removed only when work to that specific area is being performed or at Substantial Completion.
02 41 19 - 4
C. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
1. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building.
2. Provide temporary weather protection, during interval between selective demolition of existing construction on exterior surfaces and new construction, to prevent water leakage and damage to structure and interior areas.
3. Protect walls, ceilings, floors, and other existing finish work that are to remain or that are exposed during selective demolition operations.
4. Cover and protect furniture, furnishings, and equipment that have not been removed.
5. Comply with requirements for temporary enclosures, dust control, heating, and cooling specified in Division 1 Section "Temporary Facilities and Controls."
D. Temporary Shoring: Provide and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished.
1. Strengthen or add new supports when required during progress of selective demolition.
2.4 SELECTIVE REMOVAL, GENERAL
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:
1. Proceed with selective removal systematically, from higher to lower level. Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level.
2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.
Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping, to minimize disturbance of adjacent surfaces. Temporarily cover openings to remain.
3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.
4. Protect all adjacent items to remain during removal of items to be demolished
5. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.
6. Maintain adequate ventilation when using cutting torches.
7. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable materials and promptly dispose of off-site.
8. Remove structural framing members and lower to ground by method suitable to avoid free fall and to prevent ground impact or dust generation.
9. All interior items removed from ceilings shall not free fall from ceiling to the existing historic floor. If a free fall of items is unavoidable, construct protective barriers on the floor to withstand the impact of falling objects.
02 41 19 - 5
10. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.
11. Dispose of demolished items and materials promptly.
B. Reuse of Building Elements: Project has been designed to result in end-of-Project reuse of building elements as follows. Do not demolish building elements beyond what is indicated on Drawings without Architect's approval.
C. Removed and Salvaged Items:
1. Clean salvaged items.
2. Pack or crate items after cleaning. Identify contents of containers.
3. Store items in a secure area defined in drawings.
4. Transport items to storage area.
5. Protect items from damage during transport and storage.
D. Removed and Reinstalled Items:
1. Clean and repair items to functional condition adequate for intended reuse. Paint equipment to match new equipment.
2. Pack or crate items after cleaning and repairing. Identify contents of containers.
3. Protect items from damage during transport and storage.
4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.
E. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Architect, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.
2.5 DISPOSAL OF DEMOLISHED MATERIALS
A. General: Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Owner's property, remove demolished materials from Project site and legally dispose of them in an EPA-approved landfill.
1. Do not allow demolished materials to accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
3. Remove debris from elevated portions of building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.
4. Comply with requirements specified in Division 1 Section "Construction Waste
Management."
B. Burning: Do not burn demolished materials.
C. Disposal: Transport demolished materials off Owner's property and legally dispose of them.
02 41 19 - 6
2.6 CLEANING
A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.
033000 - 1
SECTION 033000
Cast-In-Place Concrete
PART 1 – GENERAL
SUMMARY:
Section includes formwork, reinforcing, and concrete for cast-in-place concrete and installation and of items furnished by other. Provide cast-in-place concrete for general building construction, including but not limited to footings, piers, foundation walls and flatwork.
Provide concrete for walks and ramps.
Requirements of this section apply to concrete work specified in other sections, such as sidewalk paving.
1.01 DEFINITIONS:
A. Exposed concrete surfaces are defined as interior and exterior surfaces exposed to view in the finished work.
B. Shores are defined as vertical or inclined support members that carry the weight of formwork, concrete and construction loads above.
C. Backshores are defined as shores placed immediately after removal of small increments of formwork, thus carrying essentially the same load after completion of the back-shoring operation as before the original shores were removed.
1.02 COORDINATION:
A. The Contractor shall coordinate all the formwork with any and all trades that might be affected by the placement of concrete. These trades shall be notified in ample time so that provisions for the placement of their work within the formwork can be accomplished in a timely and proper manner.
1.03 REFERENCES:
A. American Concrete Institute ACI 301– Specifications for Structural Concrete for Buildings, except ACI 117 – Standard Tolerances for Concrete Construction and Materials for tolerances: Maximum variation from plumb per article 2.1.1.1 shall be 1-1/2 inch.
B. American Concrete Institute ACI 303R– Guide to Cast-in-Place Architectural Concrete Practice.
C. U.S. Product Standard PA 1-74 for Construction and Industrial Plywood with American Plywood Association (APA) grade trademark.
D. National Forest Products Association Regulations.
E. American Concrete Institute ACI 315-80 – Details and Detailing of Concrete
Reinforcement.
F. American Concrete Institute ACI 315R-80 – Manual of Engineering and Placing
Drawings for Reinforced Concrete Structures.
G. American Concrete Institute ACI 318 – Building Code Requirements for Reinforced
Concrete.
H. Concrete Reinforcing Steel Institute (CRSI) Manual of Standard Practice and Placing
Reinforcing Bars.
033000 - 2
I. ACI 211.1 – Standard Practice for Selecting Proportions of Normal, Heavyweight and Mass Concrete.
J. ACI 301 – Specifications for Structural Concrete for Buildings.
K. ACI 303 – Guide to Cast-in-Place Architectural Concrete Practice.
L. ACI 304 – Recommended Practice for Measuring, Mixing, Transporting and Placing
Concrete.
M. ACI 318 – Building Code Requirements for Reinforced Concrete.
N. CRSI Manual of Standard Practice.
QUALITY ASSURANCE: Comply with governing codes and regulations. Provide products of acceptable manufacturers that have been in satisfactory use in similar service for three years. Use experienced installers. Deliver, handle and store materials in accordance with manufacturer’s instructions.
A. Raise temperature above of concrete materials, reinforcement, forms, and ground with which concrete is to come in contact, above 50 degrees F.
B. Place concrete with minimum temperature of between 50 and 70 degrees F when surrounding air is below 40 degrees F, and maintain a temperature of not less than 70 degrees F for 3 days or 50 degrees F for 5 days and as required by formwork removal analysis and in-situ verification.
COORDINATION: Full cooperation shall be given to any and all trades affected by the timely and proper installation of embedded items, including but not limited to sleeves, anchor bolts, wedge inserts, plates, sockets for the support of conduit and piping.
A. Suitable templates shall be provided for setting any and all items not placed in the formwork. The Contractor shall provide these templates.
B. The Contractor shall ascertain that the embedded items have been placed by the respective tradespersons, or the Contractor shall place them, as required, prior to the placement of any concrete.
C. The Contractor shall ascertain that all embedded items have been properly placed and do not interfere with the concrete reinforcement or placement.
DESIGN CRITERIA AND CONCRETE MIX:
Class Name Maximum Aggregate Size
Maximum Slump
Minimum Cement Lbs./Cu.
Yd.
Minimum Compressive Strength (psi/20 days)
Maximum Water/ Cement Ratio
1 Footings 1 ½” 4” 423 3,000 3 Piers* ¾” 5” 564 4,000 0.50 8 Exterior
Walks, Curbs & Equipment Pads*
¾” 3” 517 3,500 0.48
* All exterior concrete shall be air-entrained to six (6) percent, plus or minus one (1) percent.
033000 - 3
TOLERANCES: Subfloors under materials such as vinyl tile and carpet, and plain sealed floors shall have a floor flatness (Ff) of 20 and floor levelness (Fl) of 17, per ACI 302.1R and ASTM E 1155.
PART 2 – PRODUCTS
2.01 MATERIALS:
A. Reinforcement Bars: ASTM A 615 steel, Grade 60.
B. Steel Tie Wire: Black annealed, 16-gauge soft wire.
C. Conform to ACI 301 and ACI 347 except as specified herein.
D. Portland Cement: ASTM C-150, Type 1.
E. Fine Aggregate: Natural sand or manmade sands or combinations thereof conforming to
ASTM C-33.
F. Coarse Aggregate: Well graded pea gravel or crushed stone ranging between 1/8 inch and
3/8 inch in size and graded sieve size to percent passing: ½ inch – 100 percent, 1/8 inch – 95 to 100 percent, No. 4 – 40 to 60 percent, and No. 8 – 0 to 5 percent.
G. Water: Fresh, clean, free from sediment and suitable for drinking.
H. Air-Entraining Admixture: MB-VR by Master Builders, Sair by Concrete Supplies and
Service Co., AES by Protex Industries, Darex AEA or Daravair by W. R. Grace & Co., Sika AER by Sika Chemical Corporation, Air Entraining Agent by W. R. Meadows, Air Mix by EUDO, or approved equal.
I. Curing-Sealing Compound: Plasticized chlorinated resin which complies with ASTM C309, Type 1 compound, Kure-N-Seal by Sonneborn, Clear Seal by W. R. Grace & Co., Sealcure by Tech/Carboline, Floor Treet by Spray-o-Bond, CS-309 Cure and Seal by W.
R. Meadows, Eucocure by EUCO, Dress and Seal 18 by L & M, or approved equal.
2.02 EXPOSED FINISH CONCRETE FORMS: Cylindrical cardboard type forms for deck piers.
2.03 STORAGE OF MATERIALS: Store reinforcement at project site clear of the ground and protected from the weather.
PART 3 – EXECUTION
3.01 CONCRETE FORM ERECTION: Comply with ACI 301 and ACI 341. Erect forms full height of footings, walls and other forms. Earth forms are not allowed.
3.02 PREPARATION OF FORM SURFACES:
A. All surfaces of forms and embedded materials shall be cleaned of all accumulated mortar or grout from previous concrete placement and of all other…