Attachment 1 - Specifications Summary

View the file

Other files for this federal contract opportunity

Other files attached to HIA - Rapid River District Office Compound Electrical Upgrades, newest first.
File Type Posted
Attachment__3_-_USFS_Rapid_River_Electrical_Plans_FINAL_10-12-16.pdf PDF
Attachment__2_-_USFS_Rapid_River_Electrical_Technical_Specifications_-_FINAL_10-12-16.pdf PDF
Attachment__6_-_Site_Sketch_-_UPPCO_form.pdf PDF
Attachment__4_-_Wage_Determination_MI116.txt TXT text file
AG-569R-S-17-0002_Solicitation_Document.docx DOCX document
Attachment__7_-_UPPCO_load_form.pdf PDF
Attachment__5_-_Experience_Questionnaire_.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

U.S. DEPARTMENT OF AGRICULTURE

U.S. FOREST SERVICE

HIAWATHA NATIONAL FOREST

RANGER DISTRICT OFFICE COMPOUND

ELECTRICAL UPGRADES

RAPID RIVER, MI

Copyright 2010 by The American Institute of Architects (AIA)

Exclusively published and distributed by Architectural Computer Services, Inc. (ARCOM) for the AIA

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 PROJECT INFORMATION

A. Project Identification: Ranger District Office Compound Electrical Upgrades.

1. Project Location: 8181 US Hwy 2, Rapid River, MI, 49878.

B. Owner: USDA Forest Service, Hiawatha National Forest, 820 Rains Drive, Gladstone, MI 49837.

Retain "Architect's Consultants" Paragraph below if providing contact information for Architect's consultants for Project use.

Retain "Design-Builder" Paragraph below for design-build projects.

Retain "Project Web Site" Paragraph below if Project uses a project Web site, project extranet, or FTP site for information and document management.

C. The Work consists of electrical repairs, renovations, and upgrades to a number of structures at the Rapid River Ranger District compound as indicated in the project plans including: light fixtures, electric panels, branch circuits, receptacles, grounding and bonding, building and site electrical service, labeling, miscellaneous incidental work, and demolition and removal of outdated and/or un-needed items. The contractor shall be responsible for all coordination between the utility provider (UPPCO), contractor, and owner while upgrading the compound electrical service; scheduling for outages shall be approved by the Contracting Officer. The utility provider has provided a “no cost” letter for the UPPCO portion of the work; if a fee increase occurs in 2017 the Forest Service shall be responsible for payment. The Contractor shall also be responsible for locating all utilities prior to beginning any excavation work.

1.2 WORK RESTRICTIONS

A. Contractor's Use of Premises: During construction, Contractor will have limited use of site indicated. Contractor's use of premises is limited only by Owner's right to perform work or employ other contractors on portions of Project and as follows:

First subparagraph below contains an example of limitations on Contractor's use of premises; delete if not applicable. Insert other descriptions of areas or types of limited use, requirements for cooperation with Owner's personnel, noninterference with Owner's or public use, and other necessary restrictions if required.

1. Owner will occupy premises during construction. Perform construction only during normal working hours (7 AM to 5 PM Monday thru Friday, other than holidays), unless otherwise approved in writing by the Contracting Officer. Clean up work areas and return to usable condition at the end of each work period.

"Limits" Subparagraph below is based on requirements of LEED-NC Credit SS 5.1. See Evaluations.

"Driveways, Walkways, and Entrances" Subparagraph below is an example of a special requirement appropriate to many projects. Revise to suit Project or delete.

2. Driveways, Walkways, and Entrances: Keep driveways, garage doors, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

B. Contract Time: The contract time shall be 45 calendar days from the start work date noted on the Notice to Proceed.

1. Submittals: Submit a proposed progress schedule to the Contracting Officer detailing expected timelines in different buildings and proposed outages for individual buildings and the compound when the main service is switched over. The progress schedule is due the earlier of 5 days after starting work or 3 days prior to any proposed outage.

C. Outages: The maximum scheduled electrical outage for any individual (non-office) building shall be 24 hours and the maximum scheduled outage for the site service change-over shall be 72 hours. If an outage is required for the labeling/marking of the office conductors; the maximum outage shall be 1 hour between 17:00 and 18:00 on the date requested and approved in the progress schedule.

D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor-air intakes.

E. Permits: The Contractor shall be responsible for obtaining any required permits and inspections of the work at no additional cost to the government.

F. All work shall be performed in accordance with the current edition of the following codes and standards.

1. ASA

American Standards Association

2. ASTM

American Society of Testing Materials

3. ANSI

C2, American National Standards Institute

4. CFR

Code of Federal Regulations

5. NECA

Standards for Installation

6. NEMA

Standards for Materials and Products

7. NFPA

National Fire Protection Association

8. OSHA

Occupational Safety and Health Act

9. UL

Underwriters Laboratories

10. IBC

International Building Code

11. IMC

International Mechanical Code

12. IPC

International Plumbing Code

13. IFGA

International Fuel Gas Code

14. AWWA

American Water Works Association

15. NSF

National Sanitation Foundation

16. NEC

National Electric Code

17. NEMA

National Electrical Manufacturer’s Association

18. ABA

Architectural Barriers Act PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

SUMMARY
011000 - 1