NFSR 43, Whetstone Slide Repair on the London Ranger District of the Daniel Boone National Forest
Solicitation number
AG-531A-S-16-0015
Issued by

About this file

Amendment No. 1 Pages 2 through 4

View the file

Other files

File Type Posted
Amendment_No._1_AG-531A-S-16-0015.rtf RTF text file
Attachment_No._1 _Wage_Determination.txt TXT text file
AG-531A-S-16-0015.rtf RTF text file
Attachment_No._4_Questionnaire.docx DOCX document
Attachment_No._3 _Drawings_Plans.pdf PDF
Attachment_No._2 _Specifications.pdf PDF
INSTRUCTIONAL_COVER_SHEET.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ AG-531A-S-16-0015

AMENDMENT NO. 1

SOLICITATION NUMBER RFQ AG-531A-S-16-0015

NFSR 43, WHETSTONE SLIDE REPAIR

ON THE LONDON RANGER DISTRICT

DANIEL BOONE NATIONAL FOREST

Pre-Bid Site Visit Notes The pre-bid site visit meeting was held as scheduled on September 7, 2016 at the project site. The Forest Service Representatives in attendance were Andrew Christensen and Chris Phelps. The following contractors were represented at the meeting:

1. Ground Solution

2. Jigsaw Enterprises

3. Siler Excavating

4. Grimes Construction Co., Inc.

5. E & J Construction Co., Inc.

6. Advanced Enterprises, Inc.

7. Diaz Construction, Inc.

Pre-Bid Meeting Agenda:

Andrew Christensen went through the pre-bid meeting agenda shown on Page 4 with those in attendance.

Questions and Answers:

The following questions were asked and recorded. The answers to the questions are addressed below:

(1) What are the disposal requirements for the fallen trees within the excavation?

a. It was stated that the trees could be decked alongside the road (outside of travelled way) and/or scattered on the fill slopes adjacent to the constructed reinforced slope.

b. Note #7 on Sheet 12 of the drawings clarifies disposal requirements.

(2) Will the contractor be required to gate or block the road during construction?

a. It was stated that yes, traffic control would be the responsibility of the contractor. A follow up question was would barricades be the minimum requirement, and it was stated that barricades and “road closed” signs would be the minimum.

b. Note #3 on Sheet 12 of the drawings specifies that the contractor is responsible for traffic control, and requires a traffic control plan prior to construction.

(3) What would be the proposed start date?

a. It was stated that we would like to start as soon as possible, to take advantage of the typically drier weather present during the fall. It was clarified that ideally, work would start by mid-October.

b. Page 10 of the solicitation (FAR 52.211-10) requires work to commence within 10 calendar days after issuance of Notice to Proceed.

(4) Clarification was requested regarding “construction limits,” “clearing limits,” “excavation limits,” and the “slide perimeter” that is shown on Sheets 3-4 of the drawings.

a. It was stated that the construction and clearing limits were the road template from Station 0+00 to Station 4+00 for road/ditch reconditioning, reconstruction, and culvert installation, in addition to the excavation limits for the reinforced soil slope.

b. It was stated that if additional trees needed to be cut, they would have to be identified and cleared by the COR prior to cutting.

c. It was stated that clearing and excavation was not required within the “slide perimeter” north of the road and reinforced soil slope limits. However, ditch reconstruction will be required through the slide perimeter. Any stabilization needed on the cut slope north of the road would be a changed or differing site condition.

d. The slide perimeter was displayed in the drawings to visually illustrate the slide location in reference to the roadway and reinforced soil slope. Portions of the slide perimeter are likely outside the excavation limits both above and below the reinforced soil slope.

e. Excavation limits are described in Note #3 on Sheets 5-6 of the drawings.

Pre-Bid Meeting Agenda

Project Name: NSFR 43, Whetstone Slide Repair

9/7/2016 - 1000

A. INTRODUCTIONS

B. SIGN-IN SHEET

C. PROJECT DESCRIPTION & SCOPE OF WORK

D. BID OPENING

Bids due September 20, 2016 COB.

E. COMPLETION TIME & PROJECT SCHEDULE

Contract time is 30 calendar days from notice to proceed.

NOTE: This amendment increases the contract time from 30 calendar days to 45 calendar days.

F. OBTAINING PLANS AND SPECIFICATIONS

1. Plans and Supplemental Specifications on FedBizOpps at www.fbo.gov

2. FP-14 Standard Specifications available on line.

G. Schedule

1. Estimated 30 days contract time.

2. Unsure of lead time for RSS materials.

H. REQUIRED BID SUBMITTALS

1. See Page 30 of 32

2. Requirement to be registered in “SAM” (System for Award Management)

I. Project Submittals

1. Safety Plan

2. Erosion Control

3. Materials

J. Project Specifics

1. Bond Requirement

2. Erosion Control Plan

3. Aggregate

4. Riprap

5. RSS Materials/Construction

6. Davis Bacon Wage Rates and certified payrolls

K. Questions: