This amendment contains questions and answers from the prebid meeting and a revised Davis Bacon Wage Determination.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment Two.pdf | ||
| Final Drawings.pdf | ||
| Return Bid Package.pdf | ||
| Final Specifications.pdf | ||
| Final Solicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or
(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
PREVIOUS EDITION UNUSABLE STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
This form was electronically produced by USDA/ARS/OCIO/ADB.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date,etc.)
SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
J 1 1
Amendment 1 07/06/2010
USDA-ARS-MWA
1815 N. University Street Peoria, IL 61604
Same as Block 6
AG-5114-S-10-AA15
06/14/2010
N/A
RECOVERY-Repair Mechanical Systems and Install Emergency Generator, National Soil Erosion Research Laboratory (NSERL), W.
Lafayette, IN.
Pages two through seventeen of the amendment contains questions and answers from the pre-bid meeting.
Pages eighteen through forty-eight of the amendment replaces Davis Bacon Wage Determination IN20100002 dated 06/04/2010 with Davis Bacon Wage Determination IN20100002 dated 07/02/2010.
This amendment becomes part of the contract documents.
Midwest Area Engineer, 1815 North University Street, Peoria, IL 61604
Phone 309-681-6124 Fax: 309-681-6683 email:wayne.myers@.ars.usda.gov
Research, Education and Economics Agricultural Research Service
DATE: June 30, 2010
United States Department of Agriculture Agricultural Research Service
TO: PROSPECTIVE BIDDERS
SUBJECT: AMENDMENT TO THE BIDDING DOCUMENTS FOR:
RECOVERY – REPAIR MECHANICAL SYSTEMS AND INSTALL EMERGENCY
ELECTRICAL SYSTEM
USDA-ARS-NATIONAL SOIL EROSION LABORATORY (NSERL)
WEST LAFAYETTE, IN
RFI QUESTIONS:
1. This is a re-bid of this project. Is there any information available on previous bid, previous bidder, etc.?
Response: The Bid Abstract of Offers, OF 1419, contains procurement sensitive information regarding this procurement and will not be released at this time.
2. Was this project a SDVOSB set aside for the previous bid?
Response: No, the previous bid was set aside for HUB Zone.
3. What modifications to the plans and specifications will be made if Option #2 is selected and Option #1 is not selected?
Response: No modification to the plans and specifications is anticipated if Option #2 is awarded and Option #1 is not awarded.
4. Please provide copies of ARS 371 and 372 or link to them.
Response: The Government will not be issuing ARS 371 and 372 as part of the bidding documents. Copies of these documents will be made available to the Awarded Contractor.
Prospective bidders may review the forms by conducting an on line search.
5. May we assume this is a sales tax exempt project?
Response: Yes.
6. The Drawing E1.1 calls for the MDPH to be completed in off hours and on non-working weekend.
What Owner presence and owner inspection costs will be borne by the contractor for this?
Response: All work completed during Owner’s off hours including weekends and holidays shall be coordinated with the Government and shall be scheduled so the Government can have on site attendance. When requested during construction, Government shall notify the Contractor the
Midwest Area Engineer, 1815 North University Street, Peoria, IL 61604
Phone 309-681-6124 Fax: 309-681-6683 email:wayne.myers@.ars.usda.gov selected days that “off hour” on site attendance is available. Contractor shall not include any costs in their bid for off hour attendance by Government representation.
7. Option #2 requires more than 25 circuits to be run in occupied spaces, what owner presence and owner inspection costs will be borne by the Contractor if this is completed in off hours and non-working weekends?
Response: All work completed during Owner’s off hours including weekends and holidays shall be coordinated with the Government and shall be scheduled so the Government can have on site attendance. When requested during construction, Government shall notify the Contractor the selected days that “off hour” on site attendance is available. Contractor shall not include any costs in their bid for off hour attendance by Government representation.
8. Will “plastic reproducibles” be provided for mark-up as record documents?
Response: The Government will not be issuing any hard copy sets of the Drawings, Specifications and Amendments to the Contractor. Contractor shall be responsible for obtaining sets of Drawings, Specifications and Amendments for bidding, construction and project close out purposes. The Contractor shall provide the Government one clean, red-lined record document set of Drawings and Specifications as part of project closeout.
9. Can the base contract be turned over before the options?
Response: Prospective bidders shall review Clause 52.236-11 (Use and Possession Prior to Completion). See Section I – Clauses Included by Reference.
10. Is there anything else salvaged for re-use or turned over to the Owner other than the possibility of conduit?
Response: The Government retains the right to retain any removed items. After award, the Contractor shall coordinate and review with the Government to confirm all items to be retained. The reuse of existing materials shall be in accordance with the Drawings and Specifications.
Submitted: Wayne K. Myers, USDA-ARS-AOE
USDA–ARS-NSERL
West Lafayette, Indiana
Recovery – Repair Mechanical Systems and Install Emergency Electrical System Pre-Bid Questions Response
1. This is a rebid of the project, what was the value or dollar amount of the previous bid?
Response: See USDA response
2. We heard there was only one bidder, who was the previous bidder?
3. Was this project a SDVOSB set aside for the previous bid?
4. What modifications to the plans and specifications will be made if option 2 is selected and option 1 is not?
5. Please provide copies of ARS 371 and 372 or a link to them.
6. Will there be a modification to the Centrifugal Roof Ventilator (PRE) and when will that be available?
Response: Yes, refer to MAD-1, MAD-2, MAD-3 attached
7. If there is not a modification to the PRE, could the roof penetration, curb and flashing be added to the roofing contract?
Response: This contract stands alone, the roof penetration shall be the contractors responsibility
8. May we assume this is a sales tax exempt project?
9. The drawing E1.1 calls for the MDPH to be completed in off hours and on one non-working weekend.
What owner presence and owner inspection costs will be borne by the contractor for this?
10. Option 2 requires more than 25 circuits to be run in occupied spaces, what owner presence and owner inspection costs will be borne by the contractor if this is completed in off hours and non-working weekends?
11. What other items will be painted other than those specified in 09 91 00-1 and -2?
Response: Refer to schedule on drawing M1.1
4949 Harrison Avenue Suite 100 PO Box 5207 Rockford, Illinois 61125-0207 Tel. (815) 484.0739 Fax (815) 229.9867 E-Mail ldg@larsondarby.com
12. What type of refrigerant is in the two existing chiller systems?
Response: R-22, it is to be recovered and recycled
13. We understand there will be air balance on the PRE; hydronic balance on the boilers, chillers, and associated pumps. Are there any other balancing requirements? Are there any other balancing requirements on existing equipment?
Response: See addendum Item #1, and NOTE added to drawing MD1.1
14. Can McQuay chiller be used with a McQuay condenser?
Response: See addendum Item #2
15. Is the existing steam boiler operational?
Response: Yes, the existing steam boiler is the building back-up emergency heat source and it works.
16. Will the existing hot water boiler carry the entire building?
Response: Yes, the existing hot water boiler is the primary source of heat for the building
17. Will one existing chiller carry the entire building?
Response: Yes
18. Will ‘plastic reproducibles’ be provided for mark-up as record documents?
Response: See USDA response
19. Can the base contract be turned over before the options?
Response: See USDA response
20. Is there anything else salvaged for re-use or turned over to the owner other than the possibility of conduit?
Response: See USDA response
21. The concrete slabs around the existing air cooled condensing units: How thick is the existing slabs?
Response: According to construction records from 1979 the walkways are 4”. Actual thickness is unknown.
22. How thick are the existing pads under the existing air handling units?
Response: According to construction records from 1979 the Equipment Pads are 6” thick with 12” deep tapered edges.
23. How thick are the existing sidewalks?
Response: According to construction records from 1979 the walkways are 4”. Actual thickness is unknown
24. For the new pads: The pad foundation for the Gen Set is 6 inch “Plus” the existing slab. What is the thickness of the existing pad at the Gen Set?
Response: The existing walkway is to be removed. Refer to drawing EAD-2.
25. For the new pads: What would be the total depth of the new concrete pad?
Response: For the Gen Set provide 10” thick pad on compacted soil per Specification 03 30 00, top of pad located 6” above walkway and 4” larger than the Equipment footprint. Refer to drawing EAD-2 for Gen Set pad detail.
26. Same question for the new ACCU-1 pad? What would be the total depth of concrete pad?
Response: Provide 8” thick pad on compacted soil per Specification 03 30 00, top of pad located 4” above walkway and 4” larger than the Equipment footprint.
27. Is there any requirement for preparing for future ACCU-2 Pad? A block out? Pour it to match ACCU –
1?
Response: No pad is to be provided for the future ACCU
28. Is there a thickness specification for the replacement sidewalk?
Response: 4” thick for walkway area per Specification Section 32 13 13. New walkways shall be level with existing blacktop and adjacent concrete walkways. Pitch the walkway area to drain onto driveway
29. Fencing? What is the height of the proposed fence?
Response: Provide a 6’ fence. Refer to drawing EAD-1.
30. What size and quantity of access gates are required?
Response: Provide two 3’ access gates for maintenance. Refer to drawing EAD-1 for position of access gates.
31. Is the fence to be grounded to the Gen Set “Grounding Plan” E1.1-3?
Response: Provide grounding to security fence. Tie fence into grounding of Gen Set. Refer to drawing EAD-1 for fence grounding locations.
32. Spec 32 13 13-1 calls for concrete pavement of 4000 psi; Drawing E5.2 calls for 3000 psi on pads.
Which governs what?
Response: Provide 4000 psi concrete for Gen Set pad. Refer to drawing EAD-2.
33. Drawing 5.5-3 is for a guard rail. Does this apply to this project? Where?
Response: Guard Rail Detail has been altered, there are no guard rails in this project, refer to drawing EAD-2 for new detail of Security Fence Post Detail.
7-5-10
LARSON & DARBY GROUP ARCHITECTS-ENGINEERS-PLANNERS
4949 Harrison Avenue, Suite 100 P. O. Box 5207, Rockford, IL 61125-0207
815/484-0739 FAX 815.229.9867
TO: ALL BIDDERS
RE: Pre-Bid addendums
Bidding Documents Dated June 10, 2010
PROJECT: Repair Mechanical Systems and Install Emergency Electrical System
USDA-ARS, NSERL, West Lafayette, Indiana
PROJECT NO.: 19074
DATE: July 1, 2010
Specification Sections
Item # 1: Reference Specification 23 05 93: Add Section 3.0 as follows:
“3.0 Contractor to provide a Pre-Demolition Flow Test performed on each of the existing Chilled Water and Hot Water Heating Pumps. Testing shall provide the existing pump Flow (GPM), Head (Feet of Water), and Amp draw. Data shall be submitted to the USDA and Engineer in writing prior to demolition of systems.”
Item # 2: Reference Specification 23 64 26, 2.1, B, WATER CHILLERS : Add “McQuay International” to the list of approved manufacturers
Item # 3: Reference Specification 26 32 13, subsection 2.1, A, 1, add Kohler Power Systems; Generator Division to approved manufacturers list.
Drawing MD1.1:
Add NOTE to drawing as follows:
“NOTE: Prior to demolition of Chilled Water and Hot Water heating Systems a Flow Test shall be performed on each pump. Testing shall provide the existing pump Flow (GPM), Head (Feet of Water), and Amp draw with system at full flow (valves open). Data shall be submitted to the USDA and Engineer in writing prior to demolition of systems.”
Drawing M1.1:
See Revision MAD-1 Roof penetration for exhaust fan See Revision MAD-2 Ducting for exhaust fan See Revision MAD-4 Clarification of equipment pad and walkway location
Drawing M3.1:
See Revision MAD-3 PRE Exhaust Fan Schedule
Drawing E1.1:
See Revision EAD-1, EAD-3, EAD-4 Added grounding for Security Fence.
Added dimensions to security fence, 6ft high fence with two 3ft access gates.
Revised position of Motor #10, removed (ON ROOF) note.
Removed spare conduit to new ACCU-2.
Deleted KEYED NOTES 1 and 5 that referenced ACCU spare conduit.
Drawing E5.1 See Revision EAD-2, EAD-5 Revised Equipment pad detail, specified 4000lb concrete for gen set pad, revised names of slabs for clarity.
Revised Guard Rail Detail, it is now called Security Fence Detail.
Revised Typical Wiring in Trench Detail, removed spare conduit for future ACCU.
GENERAL DECISION: IN20100002 07/02/2010 IN2
Date: July 2, 2010 General Decision Number: IN20100002 07/02/2010
Superseded General Decision Number: IN20080002
State: Indiana
Construction Type: Building
Counties: Adams, Allen, Bartholomew, Benton, Blackford, Boone, Carroll, Cass, Clinton, DeKalb, Delaware, Fountain, Fulton, Grant, Hamilton, Hancock, Hendricks, Howard, Huntington, Jay, Johnson, Madison, Marion, Miami, Monroe, Montgomery, Morgan, Noble, Shelby, Steuben, Tippecanoe, Tipton, Wabash, Warren, Wells, White and Whitley Counties in Indiana.
CASS, FULTON AND WHITE COUNTIES:
BUILDING CONSTRUCTION(does not include single family homes and apartments up to and including 4 stories)
Modification Number Publication Date 0 03/12/2010 1 03/19/2010 2 04/02/2010 3 04/09/2010 4 04/16/2010 5 04/23/2010 6 04/30/2010 7 05/07/2010 8 05/14/2010 9 06/04/2010 10 06/18/2010 11 07/02/2010
ASBE0018-004 06/01/2009
BARTHOLOMEW, BENTON, BOONE, CARROLL, CLINTON, DELAWARE,
FOUNTAIN, HAMILTON, HANCOCK, HENDRICKS, HOWARD, JOHNSON,
MADISON, MARION, MONROE, MONTGOMERY, MORGAN, SHELBY,
TIPPECANOE, TIPTON, AND WARREN COUNTIES:
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR (includes application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems)..............$ 31.14 12.84
HAZARDOUS MATERIAL HANDLER
7/6/2010http://frwebgate.access.gpo.gov/cgi-bin/getdoc.cgi?dbname=Davis-Bacon&docid=IN2010...
(includes preparation, wettings, stripping, removal, scrapping, vacuuming, bagging & disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems).........$ 18.75 9.70
ASBE0041-002 07/05/2009
ADAMS, ALLEN, BLACKFORD, DE KALB, GRANT, HUNTINGTON, JAY,
MIAMI, NOBLE, STEUBEN, WABASH, WELLS AND WHITLEY COUNTIES:
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR (includes application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems)..............$ 29.04 12.36
HAZARDOUS MATERIAL HANDLER
(includes preparation, wettings, stripping, removal, scrapping, vaccuming, bagging & disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems)..............$ 18.70 9.70
ASBE0075-003 06/01/2009
CASS, FULTON AND WHITE COUNTIES:
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR (includes application of all insulating materials, protective coverings, coatings and finishings to all types of mechanical systems)..............$ 31.40 13.09
HAZARDOUS MATERIAL HANDLER
(includes preparation, wetting, stripping, removal, scrapping, vaccuming, bagging & disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems)..............$ 19.35 10.35
BOIL0374-002 07/01/2007
Rates Fringes
BOILERMAKER......................$ 32.00 17.72
BRIN0003-001 06/01/2009
INDIANAPOLIS
BOONE, HANCOCK, HENDRICKS, JOHNSON, MARION, MONTGOMERY, MORGAN,
and SHELBY COUNTIES
Rates Fringes
Bricklayer, Stone Mason, Pointer, Caulking................$ 29.85 10.13
TERRAZZO FINISHER................$ 18.92 5.70
TERRAZZO WORKER/SETTER...........$ 29.50 9.33
Tile & Marble Finisher...........$ 19.80 5.72 Tile, Marble Setter..............$ 28.90 9.23
BRIN0004-004 06/01/2009
FORT WAYNE
ADAMS, ALLEN, DEKALB, HUNTINGTON, NOBLE, STEUBEN, WELLS AND
WHITLEY COUNTIES:
Rates Fringes
BRICKLAYER (STONE MASON,
MARBLE MASONS, POINTER,
CLEANER, AND CAULKER)............$ 27.72 11.05
Terrazzo Grinder Finisher........$ 22.26 8.45 Terrazzo Worker Mechanic.........$ 26.77 10.10 Tile Setter & Marble Mason Mechanic.........................$ 24.11 10.10 Tile, Marble & Terrazzo Finisher.........................$ 19.09 8.45
BRIN0004-021 06/01/2009
BLOOMINGTON
BARTHOLOMEW AND MONROE COUNTIES
Rates Fringes
Bricklayer, Stonemason...........$ 27.45 9.51
TERRAZZO FINISHER................$ 18.00 4.10
TERRAZZO WORKER/SETTER...........$ 27.80 7.07
Tile & Marble Finisher...........$ 18.82 4.10 Tile & Marble Setter; Mosaic Worker...........................$ 27.27 6.97
BRIN0011-001 06/01/2009
LAFAYETTE
BENTON, CARROLL, CLINTON, FOUNTAIN, TIPPECANOE, WARREN, and
WHITE COUNTIES
Bricklayer, Stonemason, Pointer, Caulker & Cleaner.......$ 27.00 12.79
TERRAZZO FINISHER................$ 18.92 5.70
TERRAZZO WORKER/SETTER...........$ 29.50 9.33
Tile & Marble Finisher...........$ 19.80 5.72 Tile & Marble Setter; Mosaic Worker...........................$ 28.90 9.23
BRIN0018-001 06/01/2009
SOUTH BEND CHAPTER
CASS, FULTON, GRANT, HOWARD, MIAMI AND WABASH COUNTIES:
Rates Fringes
Bricklayer, Stonemason, Pointer, Caulker & Cleaner.......$ 27.00 11.19 Terrazzo Worker Finisher.........$ 26.05 9.59
TERRAZZO WORKER/SETTER...........$ 28.08 10.63
Tile & Marble Finisher...........$ 25.05 9.59 Tile, Marble Setter..............$ 27.08 10.63
BRIN0019-001 06/01/2009
MUNCIE CHAPTER
BLACKFORD, DELAWARE, HAMILTON, JAY, MADISON AND TIPTON COUNTIES:
Rates Fringes
Bricklayer, Stonemason, Pointer, Caulker & Cleaner.......$ 28.05 12.14
TERRAZZO FINISHER................$ 18.48 4.40
TERRAZZO WORKER/SETTER...........$ 28.53 7.54
Tile & Marble Finisher...........$ 19.33 4.40 Tile & Marble Setter; Mosaic Worker...........................$ 27.98 7.44
CARP0107-001 06/01/2009
ADAMS, CASS, FULTON, GRANT, HOWARD, HUNTINGTON, MIAMI, TIPTON,
WABASH, AND WELLS COUNTIES:
Rates Fringes
CARPENTER........................$ 24.15 11.49
MILLWRIGHT.......................$ 23.45 14.68
Piledriver.......................$ 20.83 6.21
CARP0110-002 06/01/2008
ALLEN, DEKALB, NOBLE, STEUBEN AND WHITLEY COUNTIES:
CARPENTER........................$ 23.46 11.16
MILLWRIGHT.......................$ 23.40 14.28
Piledriver.......................$ 20.77 6.21
CARP0111-001 06/01/2009
BARTHOLOMEW, JOHNSON (Townships of Union, Hensley, Franklin, Nineva, Needham and Blue River), SHELBY COUNTIES
Rates Fringes
Carpenters:
Carpenters, Drywall Insallers, Piledrivers......$ 25.10 11.82 Millwrights.................$ 25.91 14.00 Soft Floor Layers...........$ 25.12 9.88
CARP0215-001 06/01/2009
BENTON, CARROLL, CLINTON, TIPPECANOE, WARREN AND WHITE
COUNTIES:
Rates Fringes
CARPENTER........................$ 25.32 13.59
MILLWRIGHT.......................$ 25.34 14.15
CARP0912-001 06/01/2009
Rates Fringes
Carpenters:
BLACKFORD, DELAWARE, JAY
AND MADISON COUNTIES
Carpenters, Drywall, Installers, Piledrivers....$ 26.29 11.82 Millwrights................$ 25.91 14.00 Soft Floor Layers..........$ 25.12 9.88
BOONE, FOUNTAIN,
HENDRICKS, MONROE,
MONTGOMERY AND MORGAN
COUNTIES
Carpenters, Drywall........$ 26.58 11.82 Millwrights................$ 25.91 14.00 Soft Floor Layers..........$ 25.12 9.88
CARP0912-002 06/01/2009
HAMILTON, HANCOCK, JOHNSON (Townships of White River, Pleasant and Clark), MARION
Rates Fringes
Carpenters:
Carpenters, Drywall Installers, Piledrivers.....$ 28.09 11.82 Millwrights.................$ 25.91 14.00 Soft Floor Layers...........$ 25.12 9.88
ELEC0305-003 10/01/2009
ADAMS, ALLEN, DE KALB, HUNTINGTON, NOBLE, STEUBEN, WELLS, and
WHITLEY COUNTIES
Rates Fringes
ELECTRICIAN......................$ 28.98 10.67
ELEC0481-005 01/01/2009
BARTHOLOMEW, BOONE, HAMILTON, HANCOCK, HENDRICKS, JOHNSON,
MADISON, MARION, MONTGOMERY, MORGAN AND SHELBY COUNTIES
Rates Fringes
ELECTRICIAN......................$ 31.45 14.74
ELEC0538-006 06/01/2010
FOUNTAIN AND WARREN COUNTIES:
Rates Fringes
ELECTRICIAN......................$ 32.14 14.61
ELEC0668-002 12/01/2009
BENTON, CARROLL, CASS, FULTON, TIPPECANOE AND WHITE COUNTIES:
Rates Fringes
ELECTRICIAN......................$ 31.16 13.12
FOOTNOTE:
a. PAID HOLIDAYS: New Years Day, Memorial Day, July 4th, Labor Day, Veterans Day Thanksgiving Day and Christmas Day
ELEC0725-006 09/01/1999
MONROE COUNTY
Rates Fringes
Communication Technician.........$ 18.70 3.80+3%
Includes the installation, operation, inspection, maintenance, repair and service of radio, television, recording, voice sound and vision production and reproduction apparatus, equipment and appliances used for domestic, commercial, education, entertainment and private telephone systems.
ELEC0725-011 12/01/2009
MONROE COUNTY:
Rates Fringes
ELECTRICIAN......................$ 33.04 22%+5.54
ELEC0855-003 06/01/2010
BLACKFORD, DELAWARE, AND JAY COUNTIES
Rates Fringes
ELECTRICIAN......................$ 31.71 5.70+17.5%
ELEC0873-002 06/01/2009
CLINTON, GRANT, HOWARD, MIAMI, TIPTON AND WABASH COUNTIES:
Rates Fringes
ELECTRICIAN......................$ 30.60 10.77
ELEV0034-003 01/01/2010
BARTHOLOMEW, BENTON, BLACKFORD, BOONE, CARROLL, CLINTON,
DELAWARE, FOUNTAIN, GRANT, HAMILTON, HANCOCK, HENDRICKS,
HOWARD, JAY, JOHNSON, MADISON, MARION, MIAMI, MONROE,
MONTGOMERY, MORGAN, SHELBY, TIPPECANOE, TIPTON, WABASH, and
WARREN COUNTIES
Rates Fringes
Elevator Constructor Mechanic....................$ 39.275 20.035+a+b
PAID HOLIDAYS:
a. New Year's Day, Memorial Day, Independence Day, Labor Day, Vetern's Day, Thanksgiving Day, the Friday after Thanksgiving, and Christmas Day.
b. Employer contributes 8% of regular hourly rate to vacation pay credit for employee who has worked in business more than 5 years; 6% for less than 5 years' service.
ELEV0044-002 01/01/2010
ADAMS, ALLEN, DEKALB, HUNTINGTON, NOBLE, STEUBEN, WELLS, and
WHITLEY COUNTIES
ELEVATOR MECHANIC................$ 40.66 20.035+a+b
PAID HOLIDAYS:
a. New Year's Day, Memorial Day, Independence Day, Labor Day, Vetern's Day, Thanksgiving Day, the Friday after Thanksgiving, and Christmas Day.
b. Employer contributes 8% of regular hourly rate to vacation pay credit for employee who has worked in business more than 5 years; 6% for less than 5 years' service.
ELEV0057-002 01/01/2005
CASS, FULTON AND WHITE COUNTIES:
Rates Fringes
ELEVATOR MECHANIC................$ 31.77 12.015
FOOTNOTES:
a. Employer contributes 8% basic hourly rate for 5 years or more of service or 6% basic hourly rate for 6 months to 5 years of service as vacation pay credit.
b. Eight Paid Holidays: New Year's Day; Memorial Day;
Independence Day; Labor Day; Veteran's Day, Thanksgiving Day; the Friday after Thanksgiving Day and Christmas Day.
ENGI0103-001 06/01/2010
BENTON, CARROLL, CASS, CLINTON, GRANT, HOWARD, MIAMI,
TIPPECANOE, TIPTON, WABASH, and WHITE COUNTIES
Rates Fringes
Power equipment operators:
GROUP 1.....................$ 31.26 11.64
GROUP 2.....................$ 28.26 11.64
GROUP 3.....................$ 26.69 11.64
GROUP 4.....................$ 22.99 11.64
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: A-Frame Winch Truck, Air Compressors over 600 cu.ft., Air Tugger, Autograde (CMI), Auto Patrol, Backhoe, Ballast Regulator (RR), Batcher Plant (electricial control concrete), Bending Machine (pipe), Bituminous Plant (engineer), Bituminous Plant, Bituminous Mixer Travel Plant, Bituminous Paver, Bituminous Roller, Buck Hoist, Bull Dozer, Cable Way, Chicago Boom, Clamshell, Concrete Mixer (21 cu. ft. or over), Concrete Paver, Concrete Pump(crete), Crane, Craneman, Crusher Plant, Derrick, Derrick Boat, Dinkey, Dope Pots (pipeline), Dragline, Dredge Operator, Dredge Engineer, Drill Operator,, Elevating Grader, Elevator, Ford Hoe (or similar type equipment), Forklift, Formless Paver, Gantry Crane, Gradall, Grademan, Grout Pump, Helicopter Crew, Heterington Paver, High-Lift, Hoist, Hopto, Hough Loader (or similar type), Hydro Crane, Hydro Hammer, Locomotive Crane, Locomotive, Mechanic, Mobile Mixer, Motor Crane, Mucking Machine, Multiple Tamping Machine (rr), Overhead Crane, Pile Driver, Pulls, Push Dozer, Push Boats, Roller (sheep foot), Ross Carrier, Scoop, Shovel, Side Boom, Swing Crane, Tail Boom, Tar Machine (pipeline), Throttle Valve, Tower Crane, Trench Machine, Welder (heavy duty), Truck Mounted Concrete Pump, Truck-Mounted Drill, Well Point, Whirleys
GROUP 2: Air Compressor (up to 600 cu. ft.), Brakeman, Bull Float, Concrete Mixer (over 10s and under 21s), Concrete Spreader or Puddler, Deck Engine, Drill Helper, Electic Vibrator Kompactor (earth or rock), Finishing Machine, Gireman, Greaser (on grease facilities servicing heavy equipment), Material Pump, Motor Boats, Motor Crane Oiler, Portable Loader, Post Hole Digger, Power Broom, Rock Roller, Roller-Wobble Whell (earth or rock), Spike Machine (RR) Seamen Tiller, Spreader Rock, Sub Grader, Tamping Machine, Truck Mounted Drill Oiler, Welding Machine, Widener (apsco or similar type)
GROUP 3: Air Compressor 210 cu ft & over, Bituminous Distributor, Chair Cart, Concrete Curing Machine, Concrete Saw, Dope Pot Power Agitated, Flex Plane, Form Grader, Hydrohammer, Jacks Hydraulic Power Driven, Paving Joint Machine, Post Hole Digger, Roller Earth, Throttle Valve, Track Jack Power Driven, Tractor Farm Type, Truck Crane Driver
GROUP 4: Air Compressor (under 200 cu. fr. per min), Bituminous Distributor, Cement Gun, Concrete Saw, Conveyor, Deck Hand Oiler, Earth Roller, Form Grader, Generator, Guardrail Driver, Heater, Oiler, Paving Joint Machine, Power Traffic Signals, Steam Jenny, Vibrator, Water Pump, "JLG" Lifts and "Scissor" Lift or similar machine
ENGI0103-002 06/01/2010
BLACKFORD, DELAWARE, HAMILTON, HANCOCK, JAY, JOHNSON, MADISON,
MARION, and SHELBY COUNTIES
Rates Fringes
Power equipment operators:
GROUP 1.....................$ 32.60 10.58
GROUP 2.....................$ 31.65 10.58
GROUP 3.....................$ 27.60 10.58
GROUP 4.....................$ 23.90 10.58
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Air Compressor (pressurizing shafts, tunnels & drivers); Air Tugger; Auto Patrol; Back Filler; Back Hoe;
Boom Cat; Boring Machine; Bull Dozer; Caisson Drilling Machine; Cherry Picker; Compactor (with dozer blade);
Concrete Mixer (dual drum); Concrete plant; Concrete Pump;
Crane with all attachments; Crane- Electric overhead;
Derrick; Ditching Machine (18' and over); Dredge; Elevators (when hoisting material or tools); Fork Lift (machinery);
Formless Paver; Generator (power for welders of compressor); Gradall; Helicopter; Helicopter Winch Operator; High Lift-Front End Loader; Hoist-Material and/or Personnel over 3 Floors; Locomotive; Mechanic on job site;
Mucking Machine; Panel Board Concrete Plant; Pile Driver;
Push Cat; Scoop & Tractor; Scraper-Rubber Tired;
Spreader-Tractor Mounted; Straddle Carrier-Ross Type; Sub Base Finish Machine (C.M.I. or smiliar); Tower Crane;
Tractor with Backhoe (over 1/2 yard); Welder (craft)
GROUP 2: A Frame Truck; Batcher Plant (automatic dry batch);
Bending Machine-Power Driven; Bituminous Mixer; Bituminous Paver; Bituminous Plant Engineer; Boatman; Bull Float;
Compactor or Tamper-Self Propelled; Concrete Mixer (21 cu.
ft. or over); Concrete Spreader-Power Driven; Dinkey Engine; Ditching Machine; Ditching Machine (less than 18");
Drilling Machine; Finish Machine & Bull Float; Finishing Machine; Fireman-Pile Driving and Boilers; Fork Lift-Masonry & Material; Gunite Machine; Head Greaser;
Hoist-Material and/or personnel 3 floors and under;
Mechanic in shop; Mesh Depresser-Mesh Placer; P.C.C.
Concrete Belt Placer; Ruller-Asphalt, stone & sub base;
Sheepsfoot Roller- Self Propelled; Shop Mule; Spreader or Base Paver-Self Propelled; Sub Grader; Throttle valve with air compressor or boiler; Tractor with Backhoe (1/2 yard & under); Tractor-high lift-farm type; Tractor-Industrial Type; Tractor with Winch; Well Points; Winch Trick
GROUP 3: Air Compressor (210 cu. ft. & over); bituminous Distributor; Chair Cart; Concrete Curing Machine; Concrete Saw; Dope Pot Power Agitated; Flex Plane; Form Grader;
Hydrohammer; Jacks-Hydraulic-Power Driven; Minor Equipment opr. 3,4, or 5; Paving Joint Machine; Post Hole Digger;
Roller-Earth; Throttle Valve; Track Jack-Power Driven;
Tractor-Farm Type; Truck Crane Driver
GROUP 4: Air Compressor (less than 210 cu. ft.); Concrete Mixer (under 21cu. ft.); Conveyor; Generator; Mechanical Heater; Oiler; Operator-2 pieces of miner equipment; Power Broom; Pump; Welding Machine
ENGI0103-007 04/01/2009
ADAMS, ALLEN, DEKALB, HUNTINGTON, STEUBEN, WELLS, and WHITLEY
COUNTIES
Rates Fringes
Power equipment operators:
GROUP 1.....................$ 29.53 11.02
GROUP 2.....................$ 28.58 11.02
GROUP 3.....................$ 25.58 11.02
GROUP 4.....................$ 22.08 11.02
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Air Tugger; Auto Patrol, Back Filler; Back Hoe;
Boom Cat; Boring Machine; Bull Dozer; Caisson Drilling Machine; Cherry Picker; Compactor (with dozer blade);
Concrete Mixer (dual drum); Concrete Plant; Concrete Pump;
Crane with all attachments; Crane Electric overhead;
Derrick; Ditching Machine (18" and over); Dredge; Fork Lift (machinery); Formless Paver; Gradall; Helicopter;
Helicopter Winch Operator; High Lift Front End Loader;
Hoist Material and/or personnel over 3 floors; Locomotive;
Mechanic on Job Site; Mucking Machine; Panel Board Concrete Plant; Pile Driver; Push Cat; Scoop & Tractor; Scraper Tubber Tired; Skid Steer Machine (grading and back hoe);
Spreader Tractor Mounted; Straddle Carrier Ross Type; Sub Base Finish Machine (C.M.I.or similar); Tower Crane;
Tractor with backhoe (over 1/2 yard); Welder for Craft Work.
GROUP 2: A-Frame Truck; Batcher Plant (automatic dry batch);
Bending Machine Power Driven; Bituminous Mixer; Bituminous Paver; Bituminous Plant Engineer; Boatman; Bull Float;
Compactor or Tamper Riding Only; Concrete Mixer (21 cu. ft.
or over); Concrete Spreader Power Driven; Dinkey Engine;
Ditching Machine (less than 18" riding only); Drilling Machine; Elevators (when hoisting material or tools);
Finish Machine and bull Float (excluding trowelling machine); Fireman Pile Driving and Boilers; Gunite Machine;
Head Greaser; Hoist Material and/or personnel 3 floors and under; Mesh Depressor Mesh Placer; P.C.C. Concrete Belt Placer; Roller Asphalt, Stone & Sub Base; Sheepsfoot Roller Self Propelled; Shop Mule; Spreader or Base Paver Self Propelled; Sub Grader; Throttle Valve with Air Compressor or Boiler; Tractor with Backhoe (1/2 yard & under); Tractor High Lift Farm Type; Tractor Industrial Type; Tractor with Winch; Winch Truck.
GROUP 3: Bituminous Distributor; Chair Cart; Concrete Cuting Machine; Dewatering Sytems; Dope Pot Power Agitated; Flex Plane; Fork Lift (masonry and material); Form Grader;
Hydrohammer; Jacks Hydraulic Power Driven; Paving Joint Machine; Post Hole Digger (machine Mounted); Roller Earth;
Skid Steer Machine (fork lift and trasporting); Throttle Valve; Track Jack Power Driven; Tractor Farm Type.
GROUP 4: Air Compressor (pressurizing shafts, tunnels and divers); Air Compressor (over 210 cu. ft.); Concrete Saw;
Conveyor; Generators; Oiler; Operating minor equipment;
Power Broom; Truck Crane Driver; Welding Machines over 300 amps (2 or more).
ENGI0150-017 06/01/2010
FULTON and NOBLE COUNTIES
Rates Fringes
Power equipment operators:
GROUP 1.....................$ 27.60 18.85+a GROUP 2.....................$ 26.25 18.85+a GROUP 3.....................$ 25.45 18.85+a GROUP 4.....................$ 24.65 18.85+a GROUP 5.....................$ 22.05 18.85+a
FOOTNOTE: a. PAID HOLIDAYS: New Years Day, Memorial Day, Fourth of July, Labor Day, Thanksgivng Day, Day After Thanksgiving, and Christmas Day.
POWER EQUIPMENT OPERATOR CLASSIFICATIONS:
GROUP 1: Mechanic, Asphalt Plant, Asphalt Spreader, Auto Grader; Batch Plant, Benoto (requires 2 Engineers), Boiler and Throttle Valve, Boring Machine (road), Bulldozers (with engines of 140 net horse power or more) Caisson Rigs, Central Redi-mix Plant, Concrete Conveyor Systems, Concrete Power (over 27E cu. ft.), Concrete Paver (27E cu. ft. and under), Concrete Pumps/Grout cncrete placer (Truck Mounted), Concrete Tower, Cranes and backhoes (all), Cranes, Hammerhead Tower, Creter Crane, Derricks (all), Forklift (capble of hoisting and mechanically moving forks horizontally), Grader, Elevating, Highlift Shovels or Front End Loaders (over 3 yd bucket), Hoists (2 or more drums), Locomotives (all), Laser screed, Motor Patrol, Pile Drivers and Skid Rig, Pre-Stress Machines, Pump Cretes & Similar Types, Rock Drill (Self-Propelled), Rock Drill (self propelled Truck Mounted), Scoops (tractor drawn), Slip-Form Paver, Tournapull, Tractor with Boom & Side Boom, Trenching Machine (12 or more inches in width), Combination Backhoe Front End Loader Machine with backhoe 1/2 yd bucket or attachments.
GROUP 2: Air Compressor (600 cu. ft. and over), Bob Cat (over 3/4 cu. yd.), Boilers, Broom (all powered propelled), Bull Dozers with engines of less than 140 net horsepower, combination backhoe front end loader 1/2 yf bskhhoe or under, Compressor and Throttle Valve, Concrete Breaker (truck mounted), Concrete Mixer (of moore than 21 cu. ft.
capacity), Forklift (with fixed or tilt mast), Greaser Engineer, Highlift shovel or front endloader 3 yd bucket and under, Hoists (1 drum), Hydrulic Boom Truck, Post Hole Digger (vehicle mounted), Pump Cretes (squeze crete type pumps, Gypsum, bulker , Rollers(all), Steam Generators, Stone Crushers, Stradddle Buggies, Tractors, Winch Trucks (with "a" frame.
GROUP 3: Buck Hoist, Combination (small equipment operator), .Conveyor (portable), Grouting Machine, Hoist Elevators (material and personnel), Hydraulic Power Units, Grouting and Pile Driving, Stud Welder, Trenching Machines less than 12 inches in width, Welding Machines (8 through 15).
GROUP 4: Bobcat (up to and including 3/4 cu. yd.).
Compressor (over 210 cu. ft. and less than 600 cu. ft.), Generator (over 50 kw.), Heaters, Mechanical, Hoists (all elevator, permanent installation), Hoist (automatic), Hoist (tugger single drum), Oilers, Pumps, Well Points and electric submersible, Small Rubber Tired End Loaders (1/4
cu. yd. and under), Tractors (farm type) Welding Machines (2 through 8).
GROUP 5: Bobcats and forklifts (commercial or residential).
ENGI0181-004 04/01/2010
BARTHOLOMEW COUNTY
Rates Fringes
Power equipment operators:
GROUP A.....................$ 27.18 13.00
GROUP B.....................$ 19.30 13.00
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP A: A-frame winch truck, articulating dump, autograde (CMI), auto patrol, ballast regulator (RR), batcher plant (electrical control concrete), bending machine (pipe), bituminous plant (engineer), bituminous plant, bituminous mixer travel plant, bituminous paver, bituminous roller, boring machine, buck hoist, bull dozer, cable way, Chicago boom, chimney hoist, clamshell, concrete mixer (21 cu.ft.
or over), concrete paver, concrete pump (crete), construction elevator (Allmac or similar) creane, creaneman, crawler backhoe, bcreawler high-lift, crusher plant, derrick, derrick boat, dinkey, directional/boring machine, dope pots (pipeline), double drum tugger (electric or air), dragline, dredge operator, dredge engineer, drill operator, elevating grader, extendable boom forklift, formless paver, gantry crane, gator (or similar type tiller), gradeall, grader, grademan, greaser (on grease facility servicing heavy equipment), G.P.S. System (on equipment within the classificaitons), grout pump, head greaser, helicopter crew, Hetherington paver, hoist (motorized, gas or disel), hydraulic crane, ghdro blaster, Industrial type forklift (over 9,000 lbs.), laser concrete screed, laser or remote controlled equipment (within the classifications), locomotive crane, locomotive, mechanic, mobile mixer, botor creane, mucking machine, multiple tamping machine (RR) overhead crane, pile driver, pulls, push dozer, push boats, roller (sheep foot), rough terrain crain, R.T. backhoe, R.T. endloader, Ross carrier, scoop, shovel, side boom, skidsteer loader (bobcat or similar type), swing crane, tail boom, tar machine (pipeline), tower crane, trench machine, welder (heavy duty), truck mounted concrete pump, truck-mounted drill, vacuum truck, well point, whirleys
GROUP B: Air compressor (1 or more, 600 cfm and over), air compressor with throttle valve, bituminous distributor, brakeman, bullfloat, cement gun, concret mixer, concrete say, soncrete spreader or puddlers, conveyor, deck hand oiler, deck engine, drill helper, earth roller electric vibrator compactor (earth or rock), elevator (in-plant, automatic), finishing machine fireman, form grader, generator, guard-rail driver, heater, oiler, Industrial type forklift (9,000 lbs and under), aterail pump, motor boats, paving joint machine, post hole digger, power broom, power traffic signals, rock roller, rock spreader, Roller (earth or rock), spike machine (RR), steam jenny, sub grader, taping machine, gruck crane oiler, truck mounted drill oiler Tugger (one-drum, air or electric)vibrator, vibro-piling hammer- hydraulic hammer or auger, water pump, widener (apsco or similar type) welding machine, JLG lifts and scissor lifts or similar machine.
ENGI0841-008 04/01/2010
BOONE, FOUNTAIN, HENDRICKS, MONROE, MONGOMERY, MORGAN, and
WARREN COUNTIES
Rates Fringes
Power equipment operators:
GROUP 1.....................$ 29.00 13.95
GROUP 2.....................$ 21.85 13.95
POWER EQUIPMENT OPERATOR CLASSIFICATIONS
GROUP 1: Power Cranes, Draglines, Derricks, Shovels, Gradalls, Mechanics, Tractor Highlift, Tournadozer.
Concret Mixers with Skip Tournamixer, Two-Drum Machine, One-Drum Hoist with Tower or Boom, Cableways, Tower Machines, Motor Patrol, Boo Tractor, Boom or Winch Truck, Winch or Hydraulic Boom Truck, Truck Crane, Tournapull, Tractor Operating Scoops, Bulldozer, Push Tractor, Asphalt Planer, Finishing Machine on Asphalt, Large Rollers on Earth, Rollers on Asphalt Mix, Ross Carrier or Similar Machine, Gravel Processing Machine, Asphalt Plant Engineer, Paver Operator, Farm Tractor with Half Yard Bucket and/or
Backhoe Attachments, Dredge Engineer, or Dredge Operator, Central Mix Plant Engineer, CMI or Similar Type Machine, Truck or Skid Mounted Concrete Pump, Tower Crane, Engine or Rock Crusher Plant, Concrete Plant Engineer, Ditching Machine with Dual Attachment, Tractor Mounted Loaders, Cherry Picker, Hydro Crane, Standard or Dinkey Locomotives, Scoopmobiles, Euclid Loader, Soil Cement Machine, Back Filler, Elevating Machine, Power Blade, Drilling Machines including Well Testing, Caissons, Shaft or any similartype Drilling Machines, Motor Driven Paint Machine, Pipe Cleaning Machine, Pipe Wrapping Machine, Pipe Bending Machine, Apsco Paver, Boring Machine, (Equipment Greased), Barber-Greene Loaders, Formless Paver, (Well Point System), Concrete Spreader, Hydra Ax, Span Saw and Similar Types, Marine Scoops, Brush Mulcher, Brush Burner, Mesh Placer, Tree Mover, Helicopter Crew (3), Piledriver-Skid or Crawler, Stump Remover, Root Rake, Tug Boat Operator, Refrigerating Machine, Freezing Operator, Chair Cart-Self Propelled, Hydra Seeder, Straw Blower Power Sub Grader, Bull Float, Finishing Machine, Self-Propelled Pavement Breaker (Backhoe Attached), Lull (or Similar Type Machine), Two Air Compressors, Compressors Hooked in Manifold, Overhead Crane, Chip Spreader, Mud Cat, Sull-Air Fork Lifts (Except when used for Landscaping Work), Soil Stablilizer (Seaman Tiller, Bo Mag, Rago Gator and Similar types or Equipment), Tube Float, Spray Machine, Curing Machine, Concrete or Asphalt Milling Machine, Snooper Truck Operator.
GROUP 2: Concrete Mixers without Skips, Rock Crusher, Ditching Machine Under 6', Curbing Machine, One Drum Machines without Tower or Boom, Air Tugger, Self-Propelled Concrete Saw, Machin- Mounted Post Hole Digger, Two to Four Generators, Water Pumps, or Welding Machines, with 400 ft., Air Compressor 600 cu. ft. and Under, Rollers on Aggregate and Seal Coat Surfaces, Fork Lifts (When used for Landscaping Work), Concrete and Blacktop Curb Machine, Farm Tractor with less than Half Yard Bucket, One Water Pump, Iolers, Air Valves or Steam Valves, One Welding Machine, Truck Jack, Mud Jack, Gunnite Machine, House Elevators when used for Hoisting Material, Engine Tenders, Wagon Drill, Flex Plane, Conveyor, Siphons nad Pulsometer, Switchman, Fireman on Paint Pots, Fireman on Asphalt Plants, Distributor Operators on Trucks, Tampers, Self-Propelled Power Broom, Striping Machine (motor driven), Form Tamper, Bulk Cement Plan Equipment Greaser, Deck Hands, Truck Crane Oiler Driver, Cement Blimps, Form Grader, Temporary Heat, Throttle Valve, Farm Tractor, Super Sucker (and similar type of equipment). FOOTNOTE: Employees operating booms from 149 ft. to 199 ft. including jib, shall receive an additional seventy five cents (.75)per hour above the rate.
Employees operating booms over 199 ft. including jib, shall receive an additional one dollar and twenty-five cents ($1.25) per hour above the regular rate.
IRON0022-004 06/01/2009
BARTHOLOMEW; BENTON, BOONE; CARROLL; CASS; CLINTON; DELAWARE (S
2/3); FOUNTAIN; FULTON (SW 1/4 OF COUNTY); GRANT (SW PORTION);
HAMILTON; HANCOCK; HENDRICKS; HOWARD; JOHNSON; MADISON; MARION;
MIAMI; MONROE; MONTGOMERY; MORGAN; SHELBY; TIPPECANOE; TIPTON;
WARREN AND WHITE COUNTIES
Rates Fringes
IRONWORKER.......................$ 26.20 16.80
IRON0147-004 06/01/2010
ADAMS, ALLEN, BLACKFORD, DEKALB, DELAWARE (NORTHEAST THIRD OF
COUNTY), FULTON (EASTERN PART), GRANT (EXCLUDING SOUTHWEST
PORTION), HUNTINGTON, JAY, MIAMI (NORTHEAST HALF), NOBLE
(EXCLUDING NORTHEAST TIP), STEUBEN, WABASH, WELLS, and WHITLEY
COUNTIES
Rates Fringes
IRONWORKER.......................$ 24.47 17.57
IRON0292-006 06/01/2010
FULTON (Remainder of County) and NOBLE (Northeastern Tip)
COUNTIES
Rates Fringes
IRONWORKER.......................$ 25.05 17.21
LABO0120-001 06/01/2010
MARION and SHELBY COUNTIES
Rates Fringes
Laborers:
GROUP 1.....................$ 22.38 10.65
GROUP 2.....................$ 23.13 10.65
GROUP 3.....................$ 23.38 10.65
LABORER CLASSIFICATIONS
GROUP 1: Building and Construction Laborers; Scaffold Builders (other than for Masons and Plasterers); Mechanic Tenders; Window Washers and cleaners; Railroad Workers;
Masonry Wall Washers; Portable Water pumps with discharge up to (3) inches; Flag & Signal Person; Waterproofing;
Handling of Creosot Lumber or like treated material (excluding railroad material); Asphalt Rakers and Lutemen;
Kettlemen; Air Tool Operators; Pneumatic Tool Operators;
Air and Electric Vibrators and Chipping Hammer Operators;
Earth Compactors Jackmen and Sheetmen working Ditches deeper than (6) ft.in depth; Laborers working in ditches
(6) ft.in depth or deeper; Assembly of Unicrete Pump; Chain Saw and Demolition Saw; Tile Layers (sewer or field) and Sewer Pipe Layer (metallic or non-metallic); Motor driven Wheelbarrows and Concrete Buggies; Hyster Operators; Pump Crete Assemblers; Concrete Conveyor Assemblers; Core Drill Operators; Cement, Lime or Silica Clay Handlers (bulk or bag); Handling of Toxic Materials damaging to clothing;
Pneumatic Spikers; Deck Engine and Winch Operators; Water Main and Cable Ducking (metallic and non-metallic); Screed Man or Screw Operator on Asphalt Paver; Asbestos Removal and Hazardous Waste Removal.
GROUP 2: Plaster Tenders; Mason Tenders; Mortar Mixers;
Welders (Acetylene or electric); Cutting Torch or Burner;
Cement Nozzle Laborers; Cement Gun Operator; Scaffold Builders when working for Plasterers and Masons; Water Blast Machine.
GROUP 3: Dynamite men, Drillers-air track or wagon drilling for explosives.
LABO0204-001 06/01/2010
FOUNTAIN, HENDRICKS, and WARREN COUNTIES
Rates Fringes
Laborers:
Caisson and Tunnel Work in Compressed and Free Air
GROUP 1....................$ 20.32 10.25
GROUP 2....................$ 20.52 10.25
GROUP 3....................$ 20.62 10.25
GROUP 4....................$ 21.32 10.25
LABORERS
GROUP 1....................$ 21.17 10.65
GROUP 2....................$ 21.92 10.65
GROUP 3....................$ 22.17 10.65
LABORER CLASSIFICATIONS
GROUP 1: Building and Construction Laborers; Scaffold Builders (other than for Masons and Plasterers); Mechanic Tenders; Window Washers and cleaners; Railroad Workers;
Masonry Wall Washers; Portable Water pumps with discharge up to (3) inches; Flag & Signal Person; Waterproofing;
Handling of Creosot Lumber or like treated material (excluding railroad material); Asphalt Rakers and Lutemen;
Kettlemen; Air Tool Operators; Pneumatic Tool Operators;
Air and Electric Vibrators and Chipping Hammer Operators;
Earth Compactors Jackmen and Sheetmen working Ditches deeper than (6) ft.in depth; Laborers working in ditches
(6) ft.in depth or deeper; Assembly of Unicrete Pump;
Chain Saw and Demolition Saw; Tile Layers (sewer or field) and Sewer Pipe Layer (metallic or non-metallic); Motor driven Wheelbarrows and Concrete Buggies; Hyster Operators;
Pump Crete Assemblers; Concrete Conveyor Assemblers; Core Drill Operators; Cement, Lime or Silica Clay Handlers (bulk or bag); Handling of Toxic Materials damaging to clothing;
Pneumatic Spikers; Deck Engine and Winch Operators; Water Main and Cable Ducking (metallic and non- metallic);
Screed Man or Screw Operator on Asphalt Paver, Asbestos Removal, Hazardous Waste Removal.
GROUP 2: Plaster Tenders; Mason Tenders; Mortar Mixers;
Welders (Acetylene or electric); Cutting Torch or Burner;
Cement Nozzle Laborers; Cement Gun Operator; Scaffold Builders when working for Plasterers and Masons; Water Blast Machine.
GROUP 3: Dynamite men, Drillers-air track or wagon drilling for explosives.
LABORER CLASSIFICATIONS For CAISSON AND TUNNEL WORK In COMPRESSED and FREE AIR
GROUP 1: Cage Tenders, Dump Men, Flagman, Signalman, Top Laborers, Rod Men.
GROUP 2: Concrete Repairmen, Lock Tenders (pressure side), Motor men, Muckers, Grout Machine, Track Layers, Air Hoist, Key Board, Agitator Car, Car Pushers, Concrete Laborers, Grout Laborers, Lock Tenders (free air side), Steel Setters, Tuggers, Switchmen.
GROUP 3: Mucking Machine, Laser Beam, Liner Plate & Ring Setter, Shield Drivers, Power Knife, Welders Burners, Pipe Jacking Machine, Skinners, Maintenance Technician, Miner, Bricklayer Tenders, Concrete Blowers, DRillers, Erectors, Form Men, Jackhammermen, Mining Machine.
GROUP 4: Dynamite Men, Drillers air track or wagon drilling for explosives.
LABO0213-001 06/01/2010
ADAMS, ALLEN, DEKALB, HUNTINGTON, NOBLE, STEUBEN, WABASH, WELLS
AND WHITLEY COUNTIES
Rates Fringes
Laborers:
GROUP 1.....................$ 18.75 10.55
GROUP 2.....................$ 19.25 10.55
GROUP 3.....................$ 19.75 10.55
LABORERS CLASSIFICATION
GROUP 1: Building and Construction Laborers; Scaffold
Builders (other than for Masons and Plasterers); Mechanic Tenders; Window Washers and cleaners; Railroad Workers;
Masonry Wall Washers; Portable Water pumps with discharge up to (3) inches; Flag & Signal Person; Waterproofing;
Handling of Creosot Lumber or like treated material (excluding railroad material); Asphalt Rakers and Lutemen;
Kettlemen; Air Tool Operators; Pneumatic Tool Operators;
Air and Electric Vibrators and Chipping Hammer Operators;
Earth Compactors Jackmen and Sheetmen working Ditches deeper than (6) ft.in depth; Laborers working in ditches
(6) ft.in depth or deeper; Assembly of Unicrete Pump; Tile Layers (sewer or field) and Sewer Pipe Layer (metallic or non-metallic); Motor driven Wheelbarrows and Concrete Buggies; Hyster Operators; Pump Crete Assemblers; Core Drill Operators; Cement, Lime or Silica Clay Handlers…