Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or

(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

BY

(Signature of Contracting Officer)

16C. DATE SIGNED

PREVIOUS EDITION UNUSABLE STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

This form was electronically produced by USDA/ARS/OCIO/ADB.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date,etc.)

SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

J 1 3

Amendment 5 04/23/2010

USDA-ARS-MWA

1815 N. University Street Peoria, IL 61604

Same as Block 6

AG-5114-S-10-AA06

02/13/2010

N/A

RECOVERY-DFRC-Repair Mechanical Systems; CCRU-Repair Greenhouse Cooling System, Madison, WI

Pages two and three reflects clarifications to the specification.

Midwest Area Engineer, 1815 North University Street, Peoria, IL 61604

Phone 309-681-6124 Fax: 309-681-6683 email:wayne.myers@.ars.usda.gov

Research, Education and Economics Agricultural Research Service

April 23, 2010

SUBJECT: AMENDMENT NO. 5 TO THE BIDDING DOCUMENTS FOR:

DFRC – Repair Mechanical Systems; CCRU- Repair Greenhouse Cooling System

USDA-ARS

Madison, Wisconsin

General: The following items reflect modifications and clarifications to the Bidding Documents and to part of the Work for the above project. Acknowledge receipt of this Amendment on Bid Form. Failure to acknowledge receipt of Amendment may subject the Bidder to disqualification. All requirements of the original drawings and specifications shall remain in force except as modified by Amendment.

Clarifications to Contractor Questions:

Question #1: There is concern about trying to feed the new DDC wiring through the existing pathways for the pneumatic control system, particularly since some appear to go through the concrete structure to unknown locations. This was noted in particular in the lab we walked through. Is it required that the existing pathways be reused, or that the wiring be installed in conduit within the walls? Or is surface-mounted wire mold acceptable in these instances?

USDA Response: General Note 2 on drawing MV201C addresses the routing of temperature control wiring to thermostats. Temperature control wiring shall meet the requirements of 23 09 00-C. The pneumatic pathways may be re-used if 23 09 00-C requirements are met, otherwise new pathways shall be provided.

Question #2: Since we were not able to get into all areas of the building, we would like a representative from the facility to verify the number of VAV boxes, making note of those with reheat.

USDA Response: VAV boxes are shown on the floor plans and are denoted as "AT- *-**" and "CV-**".

Question #3: There are some existing VFDs. Is it acceptable to reuse the existing VFDs, or shall they all be replaced? If they are to be replaced, who is to provide the VFDs?

USDA Response: VFD's are shown to be replaced on the electrical drawings.

Midwest Area Engineer, 1815 North University Street, Peoria, IL 61604

Phone 309-681-6124 Fax: 309-681-6683 email:wayne.myers@.ars.usda.gov

Question #4: Is it the intent to include the fume hood exhaust system in the scope of work for bid option #5?

USDA Response: Fume hood exhaust system is shown included for bid option #5 on sheet MV204C.

Question #5: Is it the intent to include the toilet room exhaust system in the scope of work for bid option #5?

USDA Response: Toilet room exhaust system is shown included for bid option #5 on sheet MV204C.

Question #6: Is the existing JCI Metasys system currently installed in the building connected to any type of external monitoring system?

USDA Response: No.

Question #7: Is the existing JCI Metasys system connected to a building access system?

Question #8: Is the existing JCI Metasys system connected to a lighting control system?

Question #9: Is any work at the CCRU included in bid option #5, or is it the intent to reuse the existing control system at that facility?

USDA Response: CCRU work is not included in bid option #5. New FCU's added at CCRU are to be connected to the existing control system at the CCRU under Base Bid.

Question #10: Is the existing JCI Metasys system front-end being reused or being replaced?

USDA Response: Front end controls system to be replaced under Bid Option #5.

Question #11: Will the existing VAV dampers be reused or replaced?

USDA Response: Existing VAV dampers are to be reused under Bid Option #5.