J2 - Project Specifications

View the file

Other files

File Type Posted
AG-4419-S-10-0740.rtf RTF text file
J1 Statement of Work.docx DOCX document
J6 Davis-Bacon wage rates.pdf PDF
J3 Typical Cross Section Drawing.pdf PDF
J5 Progress Report.pdf PDF
SF18 Contractor Complete and Return.rtf RTF text file
J4 Roadside treatment details Drawing.pdf PDF
Technical Evaluation Forms.rtf RTF text file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CIM-0904/0907/0910-1R-429-0904-01 Forestwide Road Maintenance – West Side

- 17 - STANDARD SPECIFICATIONS FOR CONSTRUCTION OF ROADS AND BRIDGES ON FEDERAL HIGHWAY PROJECTS, FP-03, AS MODIFIED BY U.S. FOREST SERVICE SPECIAL PROJECT SPECIFICATIONS Table of Contents

Table of Contents1
Preface2
Submittals and Notifications3
101 - Terms, Format, and Definitions4
102 - Bid, Award, and Execution of Contract7
103 - Scope of Work8
104 - Control of Work9
105 - Control of Material10
106 - Acceptance of Work11
107 - Legal Relations and Responsibility to the Public12
108 - Prosecution and Progress14
109 - Measurement and Payment15
155 - Schedules for Construction Contracts16
201 - Clearing and Grubbing17
203 - Removal of Structures and Obstructions19
204 - Excavation and Embankment20
301 - Untreated Aggregate Courses22

Preface Preface_wo_03_15_2004_m Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.

Delete all but the first paragraph and add the following:

The Forest Service, US Department of Agriculture has adopted the Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03, U.S. Customary Units (FP-03) for construction of National Forest System Roads and other projects.

The full provisions of FP-03 shall apply as applicable on this contract, unless modified by these Special Project Specifications.

The full FP-03 specification documents are available online at:

http://www.wfl.fhwa.dot.gov/design/specs/fp03.htm The FP-03 Metric and U.S Customary versions are available in a 6¼" x 9¼" wire bound paper form. They are for sale by the U.S. Government Printing Office by contacting:

Superintendent of Documents U.S. Government Printing Office Internet: bookstore.gpo.gov Phone: (toll free) 866.512.1800 Fax: 202.512.2250 Mail: Stop SSOP, Washington, DC 20402-0001

ISBN 0-16-051430-4 (Metric Version) Stock Number: 050-001-00341-4 (U.S. Customary)

Submittals and Notifications Submittal Schedule:

The following required items need to be submitted according to the schedule shown to prevent delays or stoppages of work.

ITEM
ACTION
SCHEDULE
Construction Schedule
Approval by CO/COR
2 weeks before mobilization
List of Subcontractors and Suppliers
For Record*
2 weeks before mobilization
List of Emergency contact names, numbers and title of personnel.
Approval by CO/COR
2 weeks before mobilization
Letter of Contractor’s on-site superintendent
Approval by CO/COR
2 weeks before mobilization
Sieve Analysis of Aggregates (MI 23A & MI 4G)
Approval by CO/COR
7 days prior to use
Aggregate weigh slips
Approval by CO/COR
As delivered
Riprap weigh slips
Approval by CO/COR
As delivered
Geotextile spec sheet
Approval by CO/COR
7 days prior to use
Proper Invoices
Approval by CO/COR
As required
Certified Payroll
Approval by CO/COR
With invoices

* "For record" assumes that an Item which meets Specifications as written is supplied. Other "equal" products require review and approval by the CO/COR, and may take longer to review.

Notification Schedule:

The following events require an advance written notification to the COR. Notifications may be faxed, mailed, emailed, or hand delivered.

EVENT
PRIOR NOTICE REQUIRED
Change in Schedule
As soon as identified
Intent to mobilize
48 hours
Intent to start excavation
48 hours

101 - Terms, Format, and Definitions 101.00_nat_us_07_25_2005

101.01_nat_us_01_22_2009

101.01 Meaning of Terms

Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.

101.03_nat_us_06_16_2006

101.03 Abbreviations.

Add the following to (a) Acronyms:

AFPA

MSHA

NIST

NESC

WCLIB

American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau

Add the following to (b) SI symbols:

mp
Milepost
ppm
Part Per Million

101.04_nat_us_03_29_2007

101.04 Definitions.

Delete the following definitions and substitute the following:

Bid Schedule--The Schedule of Items.

Bridge--No definition.

Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.

Culvert--No definition.

Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.

Add the following:

Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.

Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.

Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.

Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.

Neat Line--A line defining the proposed or specified limits of an excavation or structure.

Pioneer Road--Temporary construction access built along the route of the project.

Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.

Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.

Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.

Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.

Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.

Add Figure 101-1—Illustration of road structure terms:

Figure 101-1—Illustration of road structure terms.

102 - Bid, Award, and Execution of Contract 102.00_nat_us_02_16_2005 102 Bid, Award, and Execution of Contract

Delete Section 102 in its entirety.

103 - Scope of Work 103.00_nat_us_02_16_2005 Deletions

Delete all but subsection 103.01 Intent of Contract.

104 - Control of Work 104.00_nat_us_06_16_2006 Deletions

Delete Sections 104.01, 104.02, and 104.04.

104.06_nat_us_02_17_2005 Add the following subsection:

104.06 Use of Roads by Contractor

The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.

105 - Control of Material 105.02_nat_us_01_18_2007

105.02 Material Sources.

105.02(a) Government-provided sources.

Add the following:

Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.

105.05_nat_us_05_12_2004

105.05 Use of Material Found in the Work.

Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:

Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.

106 - Acceptance of Work 106.07_nat_us_05_11_2004

106.07 Delete

Delete subsection 106.07.

107 - Legal Relations and Responsibility to the Public 107.05_nat_us_05_11_2004

107.05 Responsibility for Damage Claims.

Delete the entire subsection.

107.06_nat_us_06_16_2006

107.06 Contractor’s Responsibility for Work.

Delete the following from the first paragraph.

“except as provided in Subsection 106.07”.

107.09_nat_us_06_16_2006

107.09 Legal Relationship of the Parties.

Delete the entire subsection.

107.10_nat_us_06_16_2006

107.10 Environmental Protection.

Add the following:

Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.

Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:

· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).

· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.

· Exact time and location of spill including a description of the area involved.

· Containment procedures.

· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.

· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.

When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.

The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.

108 - Prosecution and Progress 108.00_nat_us_02_16_2005 108 Delete.

Delete Section 108 in its entirety.

109 - Measurement and Payment 109.00_nat_us_02_17_2005 109 Deletions Delete the following entire subsections:

109.06 Pricing of Adjustments.

109.07 Eliminated Work.

109.08 Progress Payments.

109.09 Final Payment.

109.02_nat_us_06_16_2006

109.02 Measurement Terms and Definitions.

(b) Contract quantity.

Add the following:

Contract quantities will be adjusted only when there are errors in the original design of 15% or more.

Change the following:

“(b) Cubic yard” to “(c) Cubic yard”.

Add the following definition:

(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.

155 - Schedules for Construction Contracts 155.00_nat_us_05_11_2004 155 Delete.

Delete Section 155 in its entirety.

201 - Clearing and Grubbing 201.01_nat_us_02_18_2005

201.01 Description

Replace with the following

This work consists of clearing and grubbing within clearing limits and other designated areas.

201.04_nat_us_02_22_2005

201.06 Disposal.

Merchantable timber is the Contractor’s property. Dispose of clearing and grubbing debris according to Subsection 203.05.

203 - Removal of Structures and Obstructions 203.01_nat_us_02_25_2005

203.01 Description.

Delete and replace with the following:

This work consists of disposing of construction slash and debris, salvaging, removing, and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions.

203.04_nat_us_02_18_2005

203.04 Removing Material.

Replace the fourth and fifth paragraphs with the following:

Where part of an existing culvert is removed, remove the entire culvert upstream from the removal. The remaining downstream culvert may be left in place if no portion of the culvert is within 12 inches of the subgrade, embankment slope, or new culvert or structure; and the culvert ends are sealed with concrete.

Remove structures and obstructions in the roadbed to 12 inches below subgrade elevation. Remove structures and obstructions outside the roadbed to 12 inches below finished ground or to the natural stream bottom.

203.05_nat_us_02_18_2005

203.05 Disposing of Material.

Delete entire section and replace with the following:

Dispose of debris and unsuitable and excess material utilizing one of the following methods:

(a) Remove from Project. Recycle or dispose of material legally off the project. Furnish the statement documenting the nature and quantity of material processed or sold for recycling. Otherwise, furnish a signed copy of the disposal agreement before disposal begins.

(b) Chipping or Grinding. Use an approved chipping machine to grind slash and stumps greater than 3 inches in diameter and longer than 3 feet. Deposit chips or ground woody material on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.

203.08 Payment.

Add the following:

Disposal of construction slash will be compensated under the designated pay item in Section 201.

204 - Excavation and Embankment 204.06_nat_us_03_02_2005

204.06 Roadway Excavation

(a) General.

Add the following:

Retrieve material deposited outside of the clearing limits as directed by the CO. Place unsuitable material in designated areas.

Roadway excavation material may be used as embankment in fill sections provided it is granular and free of organic materials.

204.10_nat_us_03_02_2005

204.10 Embankment Construction.

Add the following:

Obtain written approval before beginning construction of embankments over 6 feet high at subgrade centerline.

No additional embankment is anticipated to be imported. Materials will be balanced onsite or will be borrowed within close proximity to project site.

(a) General.

Delete the third paragraph and add the following:

Compact embankment side slopes flatter than 1V:1.75H with a tamping type roller or by walking with a dozer. For slopes 1V:1.75H or steeper, compact the slopes as construction of the embankment progresses.

204.11_nat_us_04_11_2005

204.11 Compaction.

Delete entire section and replace with the following:

Utilize the following method for compaction:

Compaction C. Place material by end dumping to the minimum depth needed for operation of spreading equipment. Level and smooth each embankment layer before placing the next layers. Operate hauling and spreading equipment uniformly over the full width of each layer. Construct a solid embankment with adequate compaction by working smaller rock and fines in with the larger rocks to fill the voids, and by operating hauling and spreading equipment uniformly over the full width of each layer as the embankment is constructed, and visual displacement ceases. No mechanical rollers will be required.

204.13_nat_us_03_02_2005

204.14 Disposal of Unsuitable or Excess Material.

Delete the text of the first paragraph and substitute the following:

Dispose of unsuitable or excess material at designated sites or legally off of the project.

301 - Untreated Aggregate Courses 301.00_nat_us_03_03_2005 301 Title Change.

Change the title to: Section 301 Aggregate Courses

301.01_nat_us_03_03_2005

301.01 Work.

Delete entire section and replace with the following:

Work includes furnishing, placement, and compaction of one or more courses of aggregate on a prepared surface.

301.02_nat_us_05_16_2005

301.03 General.

Add the following:

Written approval of the roadbed is required before placing aggregate.

For pit run or grid-rolled material, furnish material smaller than the maximum size. No gradation other than maximum size will be required for pit-run or grid-rolled material. For grid rolling, use all suitable material that can be reduced to maximum size. After processing on the road, remove all oversize material from the road and dispose of it as directed by the CO.

Provide additives or binder, if required, at the proportions specified.

Develop and use Government furnished sources according to Section 105.

If the aggregate is produced and stockpiled before placement, handle and stockpiled according to Section 320. Establish stockpile sites at locations approved. Clear and grub stockpile sites according to Section 201.

301.04_nat_us_03_03_2005

301.04 Mixing and Spreading.

Delete entire section and replace with the following:

Ensure that aggregate and any required additives, water, mineral filler, and binder are mixed by the specified method except, if crushed aggregate products are being produced and mineral filler, binder, or additives are required, uniformly blend following crushing. Control additive proportions to 0.5 percent dry weight.

Do not place the mixture in a layer exceeding 6 inches in compacted thickness. When more than one layer is necessary, compact each layer according to Subsection 301.05 before placing the next layer. Route hauling equipment uniformly over the full width of the surface to minimize rutting or uneven compaction.

After placing the aggregate for each layer, mix it with other required materials at the required moisture content until the mixture is uniform throughout. Mix aggregate, water, and all other materials until a uniform distribution is obtained.

Spread the aggregate in a uniform layer, with no segregation of size, and to a loose depth that will provide the required compacted thickness.

When placing aggregate over geotextile, place aggregate in a single lift to the full depth specified.

Route and distribute hauling and leveling equipment over the width and length of each layer.

301.05_nat_us_05_17_2005

301.05 Compacting

Delete the first and third paragraphs and add the following:

The Contractor shall compact the aggregate utilizing hauling and spreading equipment until visual deformation of the aggregate layer ceases, or a minimum of 3 complete passes has been made. The COR or Inspector will determine when deformation of the aggregate has ceased. Mechanical rollers will not be required.

For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface.

301.06_nat_us_03_03_2005

301.06 Surface Tolerance.

Add the following:

Thickness and Width requirements:

The maximum variation from the compacted specified thickness is ½ inch. The compacted thickness is not consistently above or below the specified thickness and the average thickness of 4 random measurements for any ½ mile of road segment is within + ¼ inch of the specified thickness.

The maximum variation from the specified width will not exceed +12 inches at any point. The compacted width is not consistently above the specified width and the average of any four random measurements along any ½ mile of road segment is within +4 inches of the specified width.

301.08_nat_us_03_30_2005

301.08 Acceptance.

Delete entire section and replace with the following:

Aggregate gradation and surface course plasticity index will be evaluated under Subsection 106.05. Other aggregate quality properties will be evaluated under Subsections 106.02 and 106.04.

1. Aggregate gradation. Aggregates shall be Michigan 23A and Michigan 4G, as defined in Michigan Department of Transportation (MDOT) 2003 Standard Specifications for Construction, Table 902-1, Grading RequirementsTable 902-2, Physical Requirements for Coarse Aggregates, Dense-Graded Aggregate, and Open Graded Aggregates.

1. Quality. Utilize MDOT 2003 Standard Specifications for Construction, Section 902 Aggregates.

Alternate gradations will be considered if a value is added to the project and should be presented in bid proposal.

Anticipated weight of aggregate is approximately 3000 pounds per cubic yard. Excessive moisture content will result in rejection of aggregate and/or reduction in payment.

301.09_nat_us_07_07_2005

301.09 Measurement.

Replace the second paragraph with the following:

Measure aggregate by cubic yard compacted in place when payment is by contract quantities.

301.10_nat_us_03_03_2005

301.10 Payment

Delete the following:

adjusted according to Subsection 106.05 image1.png