About this file

Davis-Bacon Wage Determination

View the file

Other files

File Type Posted
M-2 Work Site Locations.jpg JPG image
SF 1449 Cont_0652.pdf PDF
SF 1449.pdf PDF
CIM-0915-11F-188-0915-01 SPECIFICATIONS.pdf PDF
M-4 Group 27 Index map.jpg JPG image
Experience_Capability Statement.doc DOC document
M-3 Group 62 Index Map.jpg JPG image
M-1 Vicinity Map.jpg JPG image
DT-1 Material Disposition Table.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General Decision Number: IL100011 03/19/2010 IL11

Superseded General Decision Number: IL20080011

State: Illinois

Construction Types: Heavy and Highway

Counties: Boone, De Kalb, Du Page, Kane, Kendall, Lake, McHenry and Will Counties in Illinois.

WILL COUNTY

HEAVY AND HIGHWAY CONSTRUCTION PROJECTS (does not include landscape projects).

Modification Number Publication Date

0 03/12/2010

1 03/19/2010

CARP0555-003 06/01/2009

DUPAGE ANE LAKE COUNTIES

Rates Fringes

CARPENTER........................$ 40.77 20.13

CARP0555-008 06/01/2009

Carpenter and Piledriver.........$ 40.77 22.44

CARP0555-011 06/01/2009

KANE, McHENRY (North of Hwy 52), AND KENDALL COUNTIES

Carpenter and Piledriver.........$ 40.77 20.13

CARP0790-003 08/01/2009

DE KALB COUNTY

CARPENTER........................$ 31.43 17.64

CARP0790-004 08/01/2009

CARROLL, JO DAVIESS, LEE, OGLE (Oregon and South thereof), STEPHENSON, and WHITESIDE COUNTIES

4/29/2010http://www.wdol.gov/wdol/scafiles/davisbacon/IL11.dvb

CARPENTER........................$ 31.43 17.64

CARP0792-003 08/01/2009

BOONE COUNTY

CARPENTER........................$ 33.17 15.90

ELEC0009-002 05/25/2009

Line Construction

Groundman...................$ 31.08 58.18%

Lineman and Equipment

Operator....................$ 39.85 58.18%

ELEC0117-001 01/01/2010

KANE (Northern Half) and McHENRY COUNTIES

ELECTRICIAN......................$ 42.60 50.94%

ELEC0150-001 06/01/2009

LAKE COUNTY

ELECTRICIAN......................$ 38.35 25.09

* ELEC0196-001 03/02/2010

BOONE, DEKALB, DUPAGE, KANE, KENDALL, LAKE, and MCHENRY COUNTIES

Line Construction

Equipment Operator..........$ 33.14 14.28+A

Groundman Truck Driver......$ 26.52 12.38+A

Groundman...................$ 25.68 12.13+A

Lineman, Substation

Technician, Cable Splicing

Technician, Digger

Operator, Crane Opertor 20 tons and above, and Signal

Technician..................$ 39.42 16.09+A

FOOTNOTE: A. PAID HOLIDAYS: Memorial Day, Independence

Day, Labor Day, and Thanksgiving Day

ELEC0364-003 06/01/2009

ELECTRICIAN......................$ 38.52 24.12

ELEC0701-001 06/01/2009

DUPAGE COUNTY

ELECTRICIAN......................$ 36.20 27.28

ENGI0150-015 06/01/2009

BOONE and DE KALB COUNTIES

OPERATOR: Power Equipment

(Undefined)

Group 1.....................$ 39.00 23.20

Group 2.....................$ 38.45 23.20

Group 3.....................$ 37.15 23.20

Group 4.....................$ 35.70 23.20

Group 5.....................$ 34.25 23.20

POWER EQUIPMENT OPERATOR CLASSIFICATIONS

GROUP 1: Asphalt Plant; Asphalt Heater and Planer combination; Asphalt Spreader; Asphalt Silo Tender;

Autograder, GOMACO or similar; Belt Loader; Caisson Rigs;

Car Dumper, Central Redi-Mix Plant; Combination Backhoe

Front End Loader Machine (1 cu yd or over Backhoe bucket with attachments); Backhoe with Shear attachment; Concrete

Breaker (truck mounted); Concrete Conveyor; Concrete Paver over 27E cu ft; Concrete Placer; Concrete Tube Float;

Cranes, all attachments; Cranes, Hammerhead, Linden, Peco and machines of a like nature; Creter Crane; Crusher, stone; Derricks; Derrick Boats; Derricks, traveling;

Dredges; Field Mechanic Welder; Formless Curb and Gutter

Machine; Gradall and machines of a like nature; Grader, Elevating; Grader, Motor Grader, Motor Patrol, Auto Patrol, Form Grader, Pull Grader, Subgrader; Guard Rail Post Driver mounted; Hoists, one, two, and three Drum; Hydraulic

Backhoes; Locomotive, all Mucking Machine; Pile Drivers and

Skid Rig; Pre-Stress Machine; Pump Cretes Dual Ram; Rock

Drill-Crawler or Skid Rig; Rock Drill truck mounted; Roto

Mill Grinder, 36" and over; Roto Mill Grinder, less than

36"; Slip- Form Paver; Soil Test Drill Rig, truck mounted;

Straddle Buggies; GCI Crane and similar; Hydraulic

Telescoping Form (tunnel); Tie Back MAchine; Tractor Drawn

Belt Loader: Tractor Drawn Belt Loader with attached

Pusher; Tractor with boom; Tractaire with attachment;

Traffic Barrier Conveyor Machine; Raised or Blind Hoe Drill

(Tunnel & Shaft); Trenching Machine; Truck Mounted Concrete

Pump with boom; Truck mounted Concrete Conveyor;

Underground Boring and/or Mining Machines under 5 ft; Wheel

Excavator & Widener (Apsco)

GROUP 2: Batch Plant; Bituminous Mixer; Bobcats over .75 cu yd; Boiler and Throttle Valve; Bulldozer; Car Loader

Trailing Conveyors; Combination Backkhoe Front End Loader

Machine, less than 1 cu yd Backhoe Bucket with attachments;

Compressor and Throttle Valve; Compressor, common receiver

(3); Concrete Breaker or Hydro Hammer; Concrete Grinding

Machine; Concrete Mixer or Paver 7S series to and including

27 cu ft; Concrete Spreader; Concrete Curing Machine, Burlap Machine; Belting Machine and Sealing Machine;

Conveyor Muck Cars (Haglund or similar type); Finishing

Machine-Concrete; Greaser Engineer; Highlift Shovels or

Front End Loader; Hoist-Sewer Dragging Machine; Hydraulic

Boom Trucks, all attachments; Locomotives, Dinky; Pump

Cretes, Squeeze Cretes-Screw Type pumps, Gypsum Bulker and

Pump; Roller Asphalt; Rotary Snow Plows; Rototiller, Seaman, etc self-Propelled; Scoops-Tractor Drawn;

Self-propelled Compactor; Spreader-Chip- Stone etc;

Scraper; Scraper-Prime Mover in Tandem regardless of size

(add $1.00 to to Group 2 hourly rate for each hour and for each machine attached thereto); Tank Car Heater; Tractors, Push, pulling Sheeps Foot, Disc, or Compactor, etc; Tug

Boats

GROUP 3: Boilers; Brooms, all power propelled; Cement Supply

Tender; Compressor, Common Receiver (2); Concrete Mixer, two bag and over; Conveyor, Portable; Farm type Tractors used for mowing, seeding, etc; Fireman on Boilers; Forklift

Trucks; Grouting Machines; Hoists, Automatic; Hoists, all

Elevators; Hoists, Tugger single Drum; Jeep Diggers; Pipe

Jacking Machines; Post- hole Digger; Power Saw, Concrete, Power Driven; Pug Mills; Rollers, other than asphalt; Seed and Straw Blower; Steam Generators; Stump Machine; Winch

Trucks with A-Frame; Work Boats; Tamper-Form motor driven

GROUP 4: Air compressor - Small 185 and under (1 to 5 not to exceed a total of 300 ft); Air Compressor - Large over 185;

Asphalt Spreader Backend Man; Combination - Small Equipment

Operator; Generators - Small 50 kw and under; Generators -

Large , over 50 kw; Heaters, Mechanical; Hydraulic power unit (Pile Driving, Extracting or Drilling); Light Plants

All (1 to 5); Pumps, over 3" (1 to 3, not to exceed a total of 300 ft); Pumps, Well Points; Tractaire; Welding Machines

(2 through 5); Winches, 4 small electric drill winches;

Bobcats up to and including .75 cu yd

GROUP 5: Oilers

PREMIUM PAY:

Long Boom :

Cranes & Derricks 90' to 150' including jib receive an extra

$.50 per hour. Cranes & Derricks over 150' including jib receive an extra $.50 per hour plus an additional $.10 for each additional 10' of boom or jib.

Capacity Pay: Cranes & Derricks with maximum capacity exceeding 50 ton with less than 90' of boom or jib shall be compensated $.01 per hour for each ton of the rated capacity in excess of 50 ton.

Long Boom pay and Capacity pay cannot be combined.

Crane mounted earth auger, raised and blind hole drills, and truck mounted drill rigs receive an extra $.50 per hour.

Creter Cranes:

When the Creter Crane is equipped with a conveyor system capable of extending 70' or more, the engineer shall receive an extra $.50 per hour.

Truck Mounted Concrete Pumps:

When the Truck Mounted Concrete Pump is equipped with a boom, which is capable of extending 90' or more, the engineer shall receive $.50 per hour extra.

Truck Mounted Concrete Conveyor:

Truck Mounted Concrete Conveyors equipped with conveyors that are capable of extending 90' or more, the engineer shall receive an extra $.50 per hour.

Underground Work:

Employees working in tunnels, shafts, etc. shall be paid an additional $.40 per hour. Employees working under air pressure 1/2 pound to 7 pounds shall receive an additional

$.50 per hour. Employees working under air pressure of 7 pounds or over shall receive $.65 per hour more.

Mining Machines- Boring Machines:

The crew operating and maintaining the Mining Machines shall be compensated an additional $.50 per hour.

* ENGI0150-024 06/01/2009

DUPAGE, KANE, KENDALL, LAKE, McHENRY, and WILL COUNTIES

OPERATOR: Power Equipment

(Undefined)

GROUP 1.....................$ 43.30 22.80

GROUP 2.....................$ 42.75 22.80

GROUP 3.....................$ 40.70 22.80

GROUP 4.....................$ 39.30 22.80

GROUP 5.....................$ 38.10 22.80

POWER EQUIPMENT OPERATOR CLASSIFICATIONS

GROUP 1: Asphalt Plant*; Asphalt Heater and Planer combination; Asphalt Heater Scarfire*, Asphalt Spreader;

Autograder/ GOMACO or similar; ABG Paver*, Backhoes with

Caisson attachment*, Ballast Regulator, Belt Loader*;

Caisson Rigs*Car Dumper, Central Redi-Mix Plant*, Combination Backhoe; Front End Loader Machine (1 cu yd or over Backhoe bucket or with attachments); Concrete Breaker

(truck mounted); Concrete Conveyor; Concrete Paver over 27E cu ft*; Concrete Placer*; Concrete Tube Float; Cranes, all attachments*; Cranes, Hammerhead, Linden, Peco and machines of a like nature*; Creter Crane; Crusher, stone; All

Derricks; Derrick Boats; Derricks, traveling*; Dowell

Machine with Air Compressor ($1.00 above Class 1);

Dredges*; Field Mechanic Welder; Formless Curb and Gutter

Machine*; Gradall and machines of a like nature*; Grader, Elevating; Grader, Motor Grader, Motor Patrol, Auto Patrol, Form Grader, Pull Grader, Subgrader; Guard Rail Post Driver mounted*; Hoists, one, two, and three Drum; Hydraulic

Backhoes*; Backhoes with Shear attachments*; Mucking

Machine; Pile Drivers and Skid Rig*; Pre-Stress Machine;

Pump Cretes Dual Ram (requires frequent lubrication and water)*; Rock Drill- Crawler or Skid Rig*; Rock Drill truck mounted*; Rock/ Track Tamper; Roto Mill Grinder, (36" and over)*; Slip-Form Paver*; Soil Test Drill Rig, truck mounted*; Straddle Buggies; Hydraulic Telescoping Form

(tunnel); Tractor Drawn Belt Loader*; Tractor Drawn Belt

Loader with attached Pusher (two engineers); Tractor with boom; Tractaire with attachment; Traffic Barrier Transfer

Machine*; Trenching Machine; Truck Mounted Concrete Pump with boom*; Underground Boring and/or Mining Machines 5 ft in diameter and over tunnel, etc.*; Wheel Excavator* &

Widener (Apsco); Raised or Blind Hoe Drill, Tunnel & Shaft*

GROUP 2: Batch Plant*; Bituminous Mixer; Boiler and Throttle

Valve; Bulldozer; Car Loader Trailing Conveyors;

Combination Backkhoe Front End Loader Machine, (less than 1 cu yd Backhoe Bucket with attachments); Compressor and

Throttle Valve; Compressor, common receiver (3); Concrete

Breaker or Hydro Hammer; Concrete Grinding Machine;

Concrete Mixer or Paver 7S series to and including 27 cu ft; Concrete Spreader; Concrete Curing Machine; Burlap

Machine; Belting Machine and Sealing Machine; Concrete

Wheel Saw; Conveyor Muck Cars (Haglund or similar type);

Drills (all); Finishing Machine-Concrete; Greaser Engineer;

Highlift Shovels or Front End Loader; Hoist- Sewer Dragging

Machine; Hydraulic Boom Trucks, all attachments;

Hydro-Blaster (requires two operators); Laser Screed*;

Locomotives, Dinky; Off-Road Hauling Units (including articulating); Pump Cretes; Squeeze Cretes-Screw Type pumps, Gypsum Bulker and Pump; Roller Asphalt; Rotary Snow

Plows; Rototiller, Seaman, self-Propelled; Scoops-Tractor

Drawn; Self- propelled Compactor; Spreader-Chip-Stone;

Scraper; Scraper-Prime Mover in Tandem regardless of size

(add $1.00 to Group 2 hourly rate for each hour and for each machine attached thereto add $1.00 to Group 2 hourly rate for each hour); Tank Car Heater; Tractors, Push, pulling Sheeps Foot, Disc, or Compactor, etc; Tug Boats

GROUP 3: Boilers; Brooms, all power propelled; Cement Supply

Tender; Compressor, Common Receiver (2); Concrete Mixer, two bag and over; Conveyor, Portable; Farm type Tractors used for mowing, seeding, etc; Fireman on Boilers; Forklift

Trucks; Grouting Machines; Hoists, Automatic; Hoists, all

Elevators; Hoists, Tugger single Drum; Jeep Diggers; Low

Boys; Pipe Jacking Machines; Post-hole Digger; Power Saw, Concrete, Power Driven; Pug Mills; Rollers, other than asphalt; Seed and Straw Blower; Steam Generators; Stump

Machine; Winch Trucks with A-Frame; Work Boats; Tamper-Form motor driven

GROUP 4: Air compressor - Small 250 and under (1 to 5 not to exceed a total of 300 ft); Air Compressor - Large over 250;

Combination - Small Equipment Operator; Directional Boring

Machine; Generators - Small 50 kw and under; Generators -

Large , over 50 kw; Heaters, Mechanical; Hydraulic power unit (Pile Driving, Extracting or Drilling); Light Plants

(1 to 5); Pumps, over 3" (1 to 3, not to exceed a total of

300 ft); Pumps, Well Points; Tractaire; Welding Machines (2 through 5); Winches, 4 small electric drill winches;

GROUP 5: Bobcats (All); Brick Forklifts; Oilers; Directional

Boring

*Requires Oiler

IRON0001-014 06/01/2009

DU PAGE (Eastern 1/4), LAKE, AND MCHENRY (Hebron, Woodstock, and East thereof) COUNTIES

IRONWORKER

Sheeter.....................$ 41.00 27.24

Structural and Reinforcing..$ 40.75 27.24

IRON0063-003 06/01/2009

LAKE, DUPAGE (Eastern 1/4) and McHENRY (HEBRON, WOODSTOCK &

EAST THEREOF) COUNTIES

IRONWORKER, ORNAMENTAL...........$ 39.20 22.99

IRON0498-003 06/01/2009

BOONE, DEKALB (EXCEPT Southeast), and MCHENRY (Northwest)

COUNTIES

IRONWORKER.......................$ 35.00 27.66

LABO0002-004 06/01/2008

LABORER - UNDEFINED (SEWER

CONSTRUCTION)

GROUP 1.....................$ 34.75 15.27

GROUP 2.....................$ 34.88 15.27

GROUP 3.....................$ 34.98 15.27

GROUP 4.....................$ 35.10 15.27

GROUP 5.....................$ 35.75 15.27

LABORER CLASSIFICATIONS

GROUP 1: Signalmen Top Laborers, and all other Laborers not

Mentioned.

GROUP 2: Concrete Laborers; Steel Setters.

GROUP 3: Cement Carriers; Cement Mixers; Concrete Repairmen;

Mortar Men; Scaffold Men; and Second Bottom Men.

GROUP 4: Bottom Men; Bracers-Bracing; Bricklayer's Tender;

Catch Basin Digger; Drainlayer; Dynamiter; Form Men;

Jackhammermen; Powerpac; Pipelayers; Rodders; Welders &

Burners; Well Point System Men.

GROUP 5: Asbestos Abatement Laborers, Toxic and Hazardous

Waste Removal Laborers & Dosimeter use (any device)

Monitoring Nuclear Exposure.

LABO0002-009 06/01/2008

DU PAGE COUNTY

LABORER - UNDEFINED

(Compressed Air)

0 - 15 lbs..................$ 35.75 15.27

16 - 20 lbs.................$ 36.25 15.27

21 - 26 lbs.................$ 36.75 15.27

27 - 33 lbs.................$ 37.75 15.27

34 lbs and over.............$ 38.75 15.27

LABORER - UNDEFINED (Tunnel and Sewer)

GROUP 1.....................$ 34.75 15.27

GROUP 2.....................$ 34.875 15.27

GROUP 3.....................$ 34.975 15.27

GROUP 4.....................$ 35.10 15.27

GROUP 5.....................$ 35.75 15.27

LABORER CLASSIFICATIONS (TUNNEL)

GROUP 1: Cage tenders; Dumpmen; Flagmen; Signalmen; Top laborers

GROUP 2: Air hoist operator; Key board operator; concrete laborer; Grout; Lock tenders (Free Air Side); Steel setters; Tuggers; Switchmen; Car pusher

GROUP 3: Concrete repairmen; Lock tenders (pressure side);

Mortar men; Muckers; Grout machine operators; Track layers

GROUP 4: Air trac drill operator; Miner; Bricklayer tenders;

Concrete blower operator; Drillers; Dynamiters; Erector operator; Form men; Jackhammermen; Powerpac; Mining machine operators; Mucking machine operator; Laser beam operator;

Liner plate and ring setters; Shield drivers; Power knife operator; Welder- burners; Pipe jacking machine operator;

skinners; Maintenance technician

GROUP 5: Asbestos abatement laborer; Toxic and hazardous waste removal laborer; Dosimeter (any device) monitoring nuclear exposure

LABORER CLASSIFICATIONS (SEWER)

GROUP 1: Signalmen; Top laborers and All other laborers

GROUP 2: Concrete laborers and Steel setters

GROUP 3: Cement carriers; Cement mixers; Concrete repairmen;

Mortar men; Scaffold men; Second Bottom men

GROUP 4: Air trac drill operator; Bottom men;

Bracers-bracing; Bricklayer tenders; Catch basin diggers;

Drainlayers; dynamiters; Form men; Jackhammermen; Powerpac;

Pipelayers; Rodders; Welder-burners; Well point systems men

GROUP 5: Asbestos abatement laborer, Toxic and hazardous waste removal laborer; Dosimeter (any device) monitoring nuclear exposure

LABO0032-007 05/01/2009

DE KALB COUNTY

General Laborer.............$ 27.66 18.50

Skilled Laborer.............$ 29.51 18.50

General Laborer: Carpenter Tender, Tool Cribman, Fireman or

Salamander Tender, Flagman, Gravel Box Man, Dumpman &

Spotter, Form Handler, Material Handler, Fencing Laborer, Cleaning Lumber, Pit Man, Material Checker, Unloading

Explosives, Asphalt Workers with Machine & Layers, Asphalt

Plant Laborer, Wrecking, Fireproofing, Janitors; Driving

Stakes, Stringlines for all Machinery, Window Cleaning, Demolition Workers

Skilled Laborer: Asbestos Abatement Worker; Hazardous Waste

Worker Handling any Materials with any Foreign Matter

Harmful to Skin or Clothing, Track Labor, Cement Handler, Chloride Handler, Unloading & Laborers with Steel Workers &

Re-bars, Wet Concrete Workers, Tunnel Tenders in Free Air, Batch Dumper, Mason Tender, Kettle & Tar Man, Tank Cleaner, Plastic Installer, Scaffold Worker, Motorized Buggies or

Motorized Unit Used For Wet Concrete or Handling of

Building Materials, Laborers With De-Watering Systems, Sewer Workers Plus Depth, Vibrator Operator; Cement Silica, Clay, Fly Ash, Lime & Plasters Handlers (Bulk or Bag);

Cofferdam Worker Plus Depth, Concrete Paving, Placing, Cutting & Tying of Reinforcing, Deck Hand, Dredge Hand and

Shore Laborer, Bankman on Floating Plant, Grade Checker, Power Tools, Front End Man on Chip Spreader, Caisson Worker

Plus Depth, Gunnite Nozzleman, Leadman on Sewer Work, Welder, Cutter, Burner & Torchman, Chain Saw Operator, Jackhammer & Drill Operator, Layout Man and/or Tile Layer, Steel Form Setter - Street & Highway, Air Tamping

Hammerman, Signal Man On Crane, Concrete Saw Operator, Screenman on Asphalt Paver, Tending Masons with Hot

Material or Where Foreign Materials are used, Mortar Mixer

Operator, Multiple Concrete Duct - Leadman, Luteman, Asphalt Raker Curb Asphalt Machine Operator, Ready Mix

Scaleman Permanent Portable or Temporart Plant, Laborer

Handling Masterplate or Similar Materials, Laser Beam

Operator, Concrete Burning Machine Operator, Coring Machine

Operator, Plaster Tender, Underpinning & Shoring of

Buildings, Pump Man, Manhole & Catch Basin, Dirt & Stone

Tamper, Hoseman on Concrete Pump.

LABO0075-002 06/01/2008

GROUP 1.....................$ 34.75 15.27

GROUP 2.....................$ 34.85 15.27

GROUP 3.....................$ 34.95 15.27

GROUP 4.....................$ 35.00 15.27

GROUP 5.....................$ 35.25 15.27

GROUP 6.....................$ 35.60 15.27

GROUP 7.....................$ 35.75 15.27

GROUP 1 - Mortar mixers, handling asphalt shingles;

Scaffolds; Sewer and trench work (ground level down to 8 feet); Catch basin and manhole diggers, mesh handling on road work; Cement and mineral filler handler; Concrete puddlers; Batch dumpers (cement & asphalt); Vibrator operators; Sand and stone wheelers to mixer Handlers);

Concrete wheelers; Airtamping hammermen; Concrete & paving breakers; Rock drillers/Jackhammermen; Chipping hammermen

1-Bag mixer; Asphalt laborer; Chain and power saws; Pit men; Fencing laborers; Mason tenders (mortar and brick wheeler); Kettlemen & tarmen, tank cleaners; Scaffold and staging laborers; Pot Firemen (tarmen); Heaters tender for any purpose; Water pumps (portable water pumps shall be tended by laborers if the employer determines tending is required); Rip rap; Handling of slab steel road forms in any manner, except road form setting, setting center strips, Contraction and expansion joints (road work);

Unloading and handling of lumber, brick, transite materials, cast iron water pipe, reinforced concrete rods, sewer and drain tile, railroad tiles and all other creosoted materials; paving blocks and concrete forms;

Handling of insulation of any type; all work involving the unloading of materials, fixtures, or furnishing, whether crated or uncrated; all mortar and composition mixers of sewer work; track laborers; Chimney and silo laborers working at a height of 1 to 48 feet; All laborers working on swinging suspended, or any type or make of scaffolding 1 to 48 feet; All laborers working inside a sphere or any type or make of tank; Working inside a sphere or any type or make of tank from bottom to a height of 48 feet; Form strippers (any type); Mechanical or motorized buggies, for concrete or masons employers; Use of skid steer loads or any other machinery which replaces the wheelbarrow or buggy; Handling multiple concrete duct or any other type of pipe used in public utility work unless otherwise specified herein; Snapping of wall ties and removal of rods; drilling of anchor bolt holes; Concrete or asphalt clipper type saws and self-propelled saws; Shoulder and grade laborers; All hydraulic electric and air or any other type of tools;

Grouting and caulking; Cleaning lumber, Nail pulling, Deck hand; Dredgehand; Shore laborer; Bankmen on Floating Plant;

Tool and material checkers; Signalmen and Flagmen on all construction work; Cleaning of debris; Removal of trees;

Concrete curing, temporary concrete protection regardless of manner or materials used; Laborers on Apsco; Janitorial;

Wrecking and demolition laborers

GROUP 2 - Sewer and drain pipe layers and multiple concrete duct or any other type of pipe used, on public utility work

(ground level to 8 feet); Pumpcrete pipe handlers

GROUP 3 - Asphalt rakers; Hod carriers; Plasterer laborers;

Gunnite laborers, Slab for setters on roads, highways, streets, airport runaways, and radii (any type of form) stringline men for all aforementioned work; Wagon and tower drillers on land and floating plant used on dredging;

Asphalt gunners and plug men (undercoating on road work);

Mortar pump laborers; Plaster pump laborers

GROUP 4 - Tunnel miners, and all laborers inside tunnel; Air blow pipemen; Torchmen (burners); Mortaring men on sewer and drain pipe (the applying of mortar and composition mixes); All bottom men on sewer work-all sewer and drain pipelayers-multiple concrete duct or any other type of pipe used on public utility work-8 feet or more below ground level, and all other sewer and trench laborers 8 feet or more below ground level regardless of excavation area; All labor work inside cofferdam; Use of a 10 foot or more drill steel for hand held drills; Caisson laborers ground level down 15 feet; All air tools 8 feet or more below ground level; All laborers working on swinging-suspended or any type or make of scaffolds, 48 feet to 100 feet; All chimney and silo laborers working at a height of 48 to 100 feet;

All tamping hammers over 150 lbs.; All laborers working inside of a sphere or any type or make of tank at a height of 48 feet to 100 feet; all hydraulic, electric and air tools or any other type 8 feet or more below ground level;

Vibrators-any type-8 feet or more below ground level

GROUP 5 - Gunnite nozzle men; Caisson laborers and all tamping hammers from 150 lbs and over; from 15 feet below ground level down to 50 feet; and all laborers working inside of a sphere or any type of tank for every additional

50 feet or part thereof above 100 feet in height

GROUP 6 - All underground cavern laborers; Caisson laborers

50 feet or more below ground level; Laborers working under radio active conditions (suiting up); Blasting men

(Powdermen)

GROUP 7 - Dosimeter (any device) used for monitoring nuclear exposure; Asbestos abatement worker; Toxic and hazardous waste removal laborer; and chimney and silo laborers for every additional 50 feet or any part thereof above 100 feet high

LABO0149-002 06/01/2008

BOONE, KANE, KENDALL, AND McHENRY COUNTIES

GROUP 1.....................$ 34.75 15.52

GROUP 2.....................$ 34.85 15.52

GROUP 3.....................$ 34.90 15.52

GROUP 4.....................$ 34.75 15.52

GROUP 5.....................$ 35.00 15.52

GROUP 6.....................$ 35.10 15.52

GROUP 7.....................$ 35.25 15.52

GROUP 8.....................$ 34.75 15.52

GROUP 9.....................$ 35.75 15.52

GROUP 1: Common laborer, Asphalt laborer, Asphalt plant laborer, Stripping laborer, Clipper type concrete saw, Self-propelled saws

GROUP 2: Air tampers & Vibrators

GROUP 3: Mortar & Concrete mixers

GROUP 4: Stringline & form setter; Torchman (demolition), Sheeting & Cribbing, Black top rakers & lutemen, Machine screwmen

GROUP 5: Chain saw man, Jackhammer man, Drillman, Concrete breaders & air spade, GROUP 6: Tunnel laborers, Tile layers & bottom men

GROUP 7: Caisson diggers, Dynamiters

GROUP 8: Flagman

GROUP 9: Asbestos apatement laborers, Toxic & hazardous waste removal laborers & Dosimeter (any device) monitoring nuclear exposure

LABO0152-003 06/01/2008

GROUP 1.....................$ 34.75 15.52

GROUP 2.....................$ 34.85 15.52

GROUP 3.....................$ 35.025 15.52

GROUP 4.....................$ 35.025 15.52

GROUP 5.....................$ 34.90 15.52

GROUP 6.....................$ 34.15 15.52

GROUP 1: General laborers; Asphalt

GROUP 2: Cement gun laborers

GROUP 3: Asphalt Tampers and Smoothers

GROUP 4: Rakers and Lutemen; Machine screwman; Kettlemen;

Mixermen, Drum-Men; Jackhammermen (Asphalt); Mite Box

Spreaders; Laborers on birch overman and similar spreader equipment; Laborers on apsco; Laborers on Air Compressors;

Paving Form Setters; Jackhammerman (Concrete); Power Drive

Concrete Saws

GROUP 5: Cement Gun Nozzle (Gunite)

GROUP 6: Asbestos abatement laborers; Toxic and hazardous waste removal laborers; Dosimeter (any device monitoring nuclear exposure)

PAIN0014-003 06/01/2009

LAKE and WILL COUNTIES

PAINTER: Brush Only.............$ 38.00 18.44

PAIN0030-003 05/01/2009

DE KALB, DUPAGE, KANE, KENDALL, AND McHENRY COUNTIES

PAINTER

Brush, Sandblaster, and

Spray.......................$ 39.68 15.55

PAIN0030-006 05/01/2009

PAINTER

Brush, Roller, Sandblasting, and Spray.....$ 34.50 15.55

PLAS0011-008 07/01/2004

DE KALB, KANE, KENDALL, AND McHENRY COUNTIES

CEMENT MASON/CONCRETE FINISHER...$ 31.50 13.91

PLAS0011-011 06/01/1993

IROQUOIS AND KANKAKEE COUNTIES

CEMENT MASON/CONCRETE FINISHER...$ 17.95 3.75

PLAS0011-013 06/01/2004

CEMENT MASON/CONCRETE FINISHER...$ 31.50 13.91

PLAS0011-015 06/01/2005

CEMENT MASON/CONCRETE FINISHER...$ 28.70 12.49

PLASTERER........................$ 28.19 12.33

PLAS0803-001 06/01/2008

CEMENT MASON/CONCRETE FINISHER...$ 38.00 15.84

* TEAM0179-002 09/01/2009

KENDALL and WILL COUNTIES

TRUCK DRIVER

2 or 3 Axle Trucks..........$ 35.65 6.67+a

4 Axle Trucks...............$ 35.80 6.67+a

5 Axle Trucks...............$ 36.00 6.67+a

6 Axle Trucks...............$ 36.20 6.67+a

All Lowboy Trucks...........$ 37.20 6.67+a

FOOTNOTE: a. $189.00 per week.

FOOTNOTE: An additional $.20 per axle shall be paid for all vehicles with more than six (6) axles.

CLASSIFICATIONS:

Group 1 - Frame Truck when used for transportation purposes;

Air Compressor and Welding Machines, including those pulled by cars, pick-up trucks and tractors; Ambulances;

Articulated Dumps; Batch Gate Lockers; Batch Hopperman; Car and Truck Washers; Carry Alls; Forl Lifts and Hoisters;

Helpers; Mechanics Helpers and Greasers; Oil Distributors, two-man operation; Pavement Breakers; Pole Trailer, up to

40 feet; Pothole Repair Trucks; Power Mower Tractors; Quick

Change Barrier; Self-Propelled Chip Spreader; Shipping and

Receiving Clerks and Checkers; Skipman; Slurry Trucks, two-man operation; Slurry Trucks, Conveyor Operated - 2 or

3 man operation; Teamsters; Unskilled Dumpmen; Warehousemen and Dockmen; Truck Drivers hauling warning lights, barricades, and portable toilets on the job site

Group 2 - Dispatcher; Dump Crets and Adgetators under 7 yards; Dumpsters, Track Trucks, Euclids, Hug Bottom Dump

Turnapulls or Turnatrailers when pulling other than self-loading equipment or similar equipment under 16 cubic yards; Mixer Trucks under 7 yards; Ready-Mix Plant Hopper

Operator; Winch Trucks, 2 Axles

Group 3 - Dump Crets and Adgetators, 7 yards and over;

Dumpsters, Track Trucks, Euclids, Hug Bottom Dump

Turnapulls or Turnatrailers when pulling other than self-loading equipment or similar equipment over 16 cubic yards; Explosives and/or Fission Material Trucks; Mixer

Trucks 7 yards or over; Mobile Cranes while in transit; Oil

Distributors, one-man operation; Pole Trailer, over 40 feet; Pole and Expandable Trailers hauling material over 50 feet long;

Slurry Trucks, one-man operation; Winch Trucks, 3 axles or more; Mechanic - *Truck Welder and *Truck Painter*These classifications shall only apply in areas where and when it has been a past area practice; Asphalt Plant Operators in areas where it has been past practice

Group 4 - Dual-purpose vehicels, such as mounted crane tucks with hoist and accessories; Foreman; Master Mechanic;

Self-loading equipment like P.B. and trucks with scoops on the front

* TEAM0301-001 06/01/2008

LAKE AND MCHENRY COUNTIES

2-3 AXLES...................$ 32.20 .15+a

4 AXLES.....................$ 32.35 .15+a

5 AXLES.....................$ 32.50 .15+a

6 AXLES.....................$ 32.75 .15+a

FOOTNOTE: a. $448.00 per week

An additional $.20 per axle shall be paid for all vehicles with more than six (6) axles.

Paid Holidays: New Year's Day, Memorial Day, Independence

Day, Labor Day, Thanksgiving Day, and Christmas Day.

900 straight time hours or more in 1 calendar year for the same employer shall receive 1 week paid vacation; 3 years -

2 weeks paid vacation; 10 years - 3 weeks paid vacation; 20 years - 4 weeks paid vacation.

by cars, pick-up trucks and tractors; Ambulances;

Articulated Dumps; Batch Gate Lockers; Batch Hopperman; Car and Truck Washers; Carry Alls; Forl Lifts and Hoisters;

Helpers; Mechanics Helpers and Greasers; Oil Distributors, two-man operation; Pavement Breakers; Pole Trailer, up to

40 feet; Pothole Repair Trucks; Power Mower Tractors; Quick

Change Barrier; Self-Propelled Chip Spreader; Shipping and

Receiving Clerks and Checkers; Skipman; Slurry Trucks, two-man operation; Slurry Trucks, Conveyor Operated - 2 or

3 man operation; Teamsters; Unskilled Dumpmen; Warehousemen

Turnapulls or Turnatrailers when pulling other than self-loading equipment or similar equipment under 16 cubic

Turnapulls or Turnatrailers when pulling other than self-loading equipment or similar equipment over 16 cubic yards; Explosives and/or Fission Material Trucks; Mixer

Trucks 7 yards or over; Mobile Cranes while in transit; Oil

Distributors, one-man operation; Pole Trailer, over 40 feet; Pole and Expandable Trailers hauling material over 50 feet long;

Slurry Trucks, one-man operation; Winch Trucks, 3 axles or more; Mechanic - *Truck Welder and *Truck Painter*These classifications shall only apply in areas where and when it

Self-loading equipment like P.B. and trucks with scoops on the front

* TEAM0325-004 06/01/2009

BOONE and WINNEBAGO COUNTIES

2 - 3 Axles.................$ 31.86 14.07

4 Axles.....................$ 32.01 14.07

5 Axles.....................$ 32.21 14.07

6 Axles.....................$ 32.32 14.07

FOOTNOTE: An additional $.20 per axle shall be paid for all vehicles with more than six (6) axles.

by cars, pick-up trucks and tractors; Ambulances; Batch

Gate Lockers; Batch Hopperman; Car and Truck Washers; Forl

Lifts and Hoisters; Helpers;

Mechanics Helpers and Greasers; Oil Distributors, two-man operation; Pavement Breakers

Pole Trailer, up to 40 feet; Power Mower Tractors; Skipman;

Slurry Trucks, two-man operation; Teamsters; Truck Drivers hauling warning lights, barricades, and portable toilets on the job site

Group 2 - Dump Crets and Adgetators under 7 yards; Dumpsters, Track Trucks, Euclids, Hug Bottom Dump Turnapulls or

Turnatrailers when pulling other than self-loading equipment or similar equipment under 16 cubic yards; Mixer

Trucks under 7 yards; Ready-Mix Plant Hopper Operator;

Winch Trucks, 2 Axles

Turnapulls or Turnatrailers when pulling other than self-loading equipment or similar equipment over 16 cubic yards; Explosives and/or Fission Material Trucks; Mixer

Trucks 7 yards or over; Mobile Cranes while in transit; Oil

Distributors, one-man operation

Pole Trailer, over 40 feet; Pole and Expandable Trailers hauling material over 50 feet long, additional $0.50 per hour; Slurry Trucks, one-man operation; Winch Trucks, 3 axles or more

*Mechanic*Truck Welder and Truck Painter; *Winter Rate:

Between Dec. 15 and Feb. 28 the mechanic and welder rate shall be $2.00 less than the scheduled scale. Truck Painter and Truck Welder classifications shall only apply in areas where and when it has been a past area practice;

Dual-purpose vehicels, such as mounted crane tucks with hoist and accessories

Group 4 - Foreman; Master Mechanic; Self-loading equipment like P.B. and trucks with scoops on the front

* TEAM0330-002 06/01/2008

DEKALB COUNTY

2-3 AXLES...................$ 32.55 .15+a

4 AXLES.....................$ 32.70 .15+a

5 AXLES.....................$ 32.90 .15+a

6 AXLES.....................$ 33.10 .15+a

FOOTNOTE: a. $434.00 per week by cars, pick-up trucks and tractors; Ambulances;

Articulated Dumps; Batch Gate Lockers; Batch Hopperman; Car and Truck Washers; Carry Alls; Forl Lifts and Hoisters;

Helpers; Mechanics Helpers and Greasers; Oil Distributors, two-man operation; Pavement Breakers; Pole Trailer, up to

40 feet; Pothole Repair Trucks; Power Mower Tractors; Quick

Change Barrier; Self-Propelled Chip Spreader; Shipping and

Receiving Clerks and Checkers; Skipman; Slurry Trucks, two-man operation; Slurry Trucks, Conveyor Operated - 2 or

3 man operation; Teamsters; Unskilled Dumpmen; Warehousemen

Turnapulls or Turnatrailers when pulling other than self-loading equipment or similar equipment under 16 cubic

Turnapulls or Turnatrailers when pulling other than self-loading equipment or similar equipment over 16 cubic yards; Explosives and/or Fission Material Trucks; Mixer

Trucks 7 yards or over; Mobile Cranes while in transit; Oil

Distributors, one-man operation; Pole Trailer, over 40 feet; Pole and Expandable Trailers hauling material over 50 feet long;

Slurry Trucks, one-man operation; Winch Trucks, 3 axles or more; Mechanic - *Truck Welder and *Truck Painter*These classifications shall only apply in areas where and when it

Self-loading equipment like P.B. and trucks with scoops on the front

* TEAM0673-003 06/01/2008

DU PAGE and KANE COUNTIES

2-3 AXLES...................$ 32.55 .15+a

4 AXLES.....................$ 32.70 .15+a

5 AXLES.....................$ 32.90 .15+a

6 AXLES.....................$ 33.10 .15+a

FOOTNOTE: a. $434.00 per week.

by cars, pick-up trucks and tractors; Ambulances;

Articulated Dumps; Batch Gate Lockers; Batch Hopperman; Car and Truck Washers; Carry Alls; Forl Lifts and Hoisters;

Helpers; Mechanics Helpers and Greasers; Oil Distributors, two-man operation; Pavement Breakers; Pole Trailer, up to

40 feet; Pothole Repair Trucks; Power Mower Tractors; Quick

Change Barrier; Self-Propelled Chip Spreader; Shipping and

Receiving Clerks and Checkers; Skipman; Slurry Trucks, two-man operation; Slurry Trucks, Conveyor Operated - 2 or

3 man operation; Teamsters; Unskilled Dumpmen; Warehousemen

Turnapulls or Turnatrailers when pulling other than self-loading equipment or similar equipment under 16 cubic

Turnapulls or Turnatrailers when pulling other than self-loading equipment or similar equipment over 16 cubic yards; Explosives and/or Fission Material Trucks; Mixer

Trucks 7 yards or over; Mobile Cranes while in transit; Oil

Distributors, one-man operation; Pole Trailer, over 40 feet; Pole and Expandable Trailers hauling material over 50 feet long;

Slurry Trucks, one-man operation; Winch Trucks, 3 axles or more; Mechanic - *Truck Welder and *Truck Painter*These classifications shall only apply in areas where and when it

Self-loading equipment like P.B. and trucks with scoops on the front

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

In the listing above, the "SU" designation means that rates listed under the identifier do not reflect collectively bargained wage and fringe benefit rates. Other designations indicate unions whose rates have been determined to be prevailing.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the

Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

U.S. Department of Labor

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

U.S. Department of Labor

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION