Drawings
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amend_01.pdf | ||
| PreBid mtg_ROCK RUN WATERLINE.docx | DOCX document | |
| Attachment 10001.pdf | ||
| PreBid mtg_ROCK RUN WATERLINE.pdf | ||
| 1442 Cont_0539.pdf | ||
| SF 1442.pdf | ||
| CIM-0914-05A-01_Specs.doc | DOC document | |
| DBA_WD.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EASTERN REGION
US Department of Agriculture Forest Service
UPSTREAM ROCK RUN COAL MINE REMEDIATION
Wayne National Forest Athens Ranger District
SHEET SHEET TITLE
PROJECT
LOCATION
Region Nine
FEBRUARY 4 , 2010
(WATERLINE RELOCATION)
GENERAL NOTES
CIM-0914-05A-01
USFS APPROVALS
STATEMENT OF QUANTITIES
LOCATION PLAN:
THE SITE IS ACCESSED FROM OHIO STATE ROUTE 93 IN PERRY COUNTY, OHIO.
N.T.S.
N.T.S.VICINITY PLAN:
Perry County, Ohio Coal Township
PROJECT SITE
PROJECT LOCATION
970980
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W
W W
W
W
SWEEP
OPEN CUT OR
DIRECTIONAL BORE
EXISTING 4" O SDR21 PVC WATERLINE
880 890
S.
R.
C.R. 41 C.R. 41
1+
6+00
0+
2+00
3+00
4+00
5+00
7+00
8+00
9+00
13+00
14+00
W
W
W
W
W
W
W
W
W
W
W
W
W
0+00 1+00 2+00 3+00 4+00 5+00 6+00 7+00 8+00 9+00 10+00 11+00 12+00 13+00 14+00 15+00 16+00 17+00
CONNECTION #1
EXISTING GROUND LINE
NEW 4" O HDPE PIPE CONNECTION #24' MIN.
W W
W
W W
W W W
W
W W W
W
W
W W
W W
W
W
MIN. 4' DEPTH TO TOP OF PIPE IN THIS AREA DEPTH ELEV. AS SHOWN IS MIN. MIN. 4' DEPTH TO TOP OF PIPE IN THIS AREA
Upstream_Waterline_plan.dwg
( IN FEET )
GRAPHIC SCALE
0100 100 200 40050
Drawing Title
Scale
Date
CAD File No.
Checked
Drawn
Drawing No.
Project
Date
Project Name
No.
Revision/Issue
Sheet of
DWS
TCW
1 2PLOT ARCH SIZE "D"
SWEEP
OPEN CUT OR
DIRECTIONAL BORE
EXISTING 4" O SDR21 PVC WATERLINE
S.
R.
C.R. 41
1+
6+00
0+
2+00
3+00
4+00
5+00
7+00
8+00
9+00
13+00
14+00
Upstream_Waterline_plan.dwg
PLOT ARCH SIZE "D"
( IN FEET )
GRAPHIC SCALE
0100 100 200 40050
Drawing Title
Scale
Date
CAD File No.
Checked
Drawn
Drawing No.
Project
Date
Project Name
No.
Revision/Issue
Sheet of
DWS
TCW
2 2
NEW 4" O HDPE PIPE
SADDLE WITH 1" O CORP STOP
NEW MJ 4" GV
EXISTING 4" O PIPE
SDR21 PVC WATERLINE
FLANGE CONNECTION
EXISTING 4" O PIPE
SDR21 PVC WATERLINE
NEW MJ 4" GV
FLANGE CONNECTION
SADDLE WITH 1" O CORP STOP
NEW 4" O HDPE PIPE
NEW 4" HDPE
SWEEP
2'
2'
POUR IN PLACE CONCRETE
THRUST BLOCK
HDPE FUSED SADDLE
SILT FENCE DETAIL
NO SCALE
CONTRACTOR SHALL FOLLOW MANUFACTURER'S INSTRUCTIONS ON INSTALLATION.
FENCE AND ALL COMPONENTS SHALL BE BIODEGRADABLE, AND SHALL BE FUNCTIONAL FOR A MINIMUM OF
2 TO 2 YEARS.
SILT FENCES SHALL BE INSPECTED IMMEDIATELY AFTER EACH RAINFALL AND AT LEAST DAILY DURING PROLONGED RAINFALL EVENTS. ANY REPAIRS THAT ARE NECESSARY SHALL BE MADE IMMEDIATELY.
IF THE FABRIC OF THE SILT FENCE SHOULD DECOMPOSE OR BECOME INEFFECTIVE DURING THE EXPECTED
LIFE OF THE FENCE, THE FABRIC SHALL BE REPLACED PROMPTLY.
SEDIMENT DEPOSITS SHOULD BE INSPECTED AFTER EVERY STORM EVENT. THE DEPOSITS SHOULD BE REMOVED WHEN DEPOSITS HAVE REACHED APPROXIMATELY ONE-HALF THE HEIGHT OF THE BARRIER.
SEDIMENT DEPOSITS THAT ARE REMOVED SHALL BE GRADED AND VEGETATED TO CONFORM WITH THE
EXISTING TOPOGRAPHY.
EXISTING GRADE
FLOW
FLOW
FLOW
FLOW
MINIMUM HEIGHT FROM
GROUND SURFACE IS 3 FEET
BIODEGRADABLE FILTER FABRIC
SHALL EQUAL TO BIOFENCE
BY ERC/BIOMASS FARMS
OF EAST FREETOWN, MA
EXCAVATE 6"x6" TRENCH UPSLOPE
FROM AND ALONG THE LINE OF POSTS,
EXTEND SILT FENCE INTO TRENCH,
BACKFILL AND COMPACT EXCAVATED SOIL
8'
MAX.
POLES
SECTION A SECTION B
SECTION A SECTION B
SILT FENCE
ENDS COUPLED
JOINING SILT FENCE SECTIONS
PLACE THE END POST OF ONE FENCE INSIDE THE END POST OF THE NEXT FENCE.
ROTATE BOTH POSTS AT LEAST 180 DEGREES IN A CLOCKWISE DIRECTION TO CREATE A TIGHT SEAL WITH
THE FABRIC MATERIAL.
DRIVE BOTH POSTS 12 INCHES INTO THE GROUND AND BURY THE FLAP IN THE TRENCH.
NOTES:
1.
2.
3.
NOTES:
1.
2.
MAINTENANCE:
1.
2.
3.
4.
FILTER FABRIC
EMBEDDED 6"
INTO GROUND
MINIMUM BURIED DEPTH
IS 1.0 FOOT
SEDIMENTSTOP INSTALLATION
USA 1-800-772-2040 CANADA 1-800-448-2040
14649 HIGHWAY 41 NORTH, EVANSVILLE, INDIANA 47725
www.nagreen.com
DIAGRAM A
DIAGRAM B
3.
1.
7.
1. BEGIN AT THE LOCATION WHERE THE SEDIMENTSTOP (Patent Pending) IS TO BE INSTALLED BY EXCAVATING A 3" DEEP X 9" WIDE TRENCH ALONG THE CONTOUR OF THE SLOPE. EXCAVATED SOIL SHOULD BE PLACED UP-SLOPE FROM THE ANCHOR TRENCH.
2. UNROLL THE SEDIMENTSTOP SO THE SECTION WITH THE 2' WIDE TOP NETTING IS THE DOWN SLOPE END (SPLASH APRON). THE SPLASH APRON OF THE SEDIMENTSTOP SHOULD COVER THE ANCHOR TRENCH ENSURING THAT APPROXIMATELY 12" (30 CM) IS EXTENDED BEYOND THE LOWER EDGE OF THE ANCHOR TRENCH. NOTE: SEEDING MUST BE CONDUCTED PRIOR TO INSTALLATION OF THE SEDIMENT STOP.
3. SECURE THE SEDIMENTSTOP IN THE ANCHOR TRENCH BY PLACING A ROW OF STAPLES/STAKES ON 12" (30 CM) CENTERS ACROSS THE ENTIRE LENGTH OF THE SEDIMENTSTOP. A SECOND ROW OF STAPLES/STAKES MUST BE PLACED ACROSS THE ENTIRE LOWER EDGE OF THE SEDIMENTSTOP SPLASH APRON ON APPROXIMATELY 12" (30 CM) CENTERS, STAGGERED WITH THE FIRST ROW OF STAPLES/STAKES.
4. BEGIN ROLLING THE SEDIMENTSTOP FROM ITS UPPER EDGE (UP-SLOPE EDGE) INTO A CONSISTENT ROLL DIAMETER UNTIL THE ROLL IS LOCATED IN THE ANCHOR TRENCH. IF A LARGER DIAMETER STRUCUTRE IS DESIRED, PLACE ADDITIONAL ORGANIC MATERIAL (I.E. STRAW, LEAVES, PINE NEEDLES OR LAWN CLIPPINGS) ACROSS THE ENTIRE WIDTH OF THE SEDIMENTSTOP PRIOR TO ROLLING. SEE DIAGRAM 4a FOR SEAMING OF ADJACENT
SEDIMENTSTOP ROLLS.
5. STOP ROLLING THE SEDIMENTSTOP WHEN THE ROLL IS LOCATED IN THE ANCHOR TRENCH.
6. SECURE THE SEDIMENTSTOP STRUCTURE TO THE SLOPE SURFACE BY DRIVING APPROXIMATELY 18" - 24" (45-60 CM) STAKES THROUGH THE CENTER OF THE ROLL EVERY 3' (0.9 M) ON CENTER. IF TWO SEDIMENTSTOP STRUCTURES ARE SEAMED TOGETHER ENSURE A STAKE IS DRIVEN THROUGH THE SEAM. THE FINAL STRUTURE'S DIAMETER WILL DICTATE STAKE LENGTH. LEAVE A SUFFICIENT AMOUNT OF STAKE EXPOSED ABOVE THE SEDIMENTSTOP TO ENSURE THE STRUCUTRE IS NOT COMPRESSED. BOTH LONGITUDINAL ENDS SHOULD BE ANGLED UP SLOPE.
7. BACKFILL AND COMPACT SOIL INTO THE UP-SLOPE PORTION OF THE ANCHOR TRENCH. SMOOTH AND LEVEL ANY SOIL REMAINING ABOVE THE SEDIMENTSTOP NOT USED TO FILL THE ANCHOR TRENCH. PLACE SEED ALONG UP-SLOPE PORTION OF SEDIMENTSTOP IF REQUIRED.
4a
NO SCALE