About this file

The purpose of this Amendment is to update the following a. Delete all references to FR25 Bridge Reconstruction in the existing RFP and replace with FR45 Bridge Reconstruction . b. The contractor shall not begin construction on bridge no. 45.00.2 before August 15 2010. c. Extend proposal due date from April 23 2010 to April 30 2010. *PROPOSALS ARE DUE APRIL 30 2010 NO LATER THAN 2 00 PM EST*

View the file

Other files

File Type Posted
FSR 45 Geotech Report.pdf PDF
AG-4419-S-10-0520 Q A.pdf PDF
Finalized RFP.pdf PDF
Attachment D.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .