Solicitation: AG-4419-S-10-0520

FR45 Bridges Reconstruction

Pre-Proposal Meeting, April 5, 2010

Q: There are multiple contracts off from this road, how will these be coordinated?

A: The contractor will be required to complete bridge no 45.02.4 before beginning work on bridge 45.00.2 to allow the other contracts to be completed.

Q: Are there any weight restrictions on bridge 45.00.2?

A: Bridge 45.00.2 has no weight restrictions.

Q: Is there any boring information available?

A: Yes, boring information will be made available.

Q: Who will acquire the stream alterations permit?

A: The FS will acquire the stream alterations permit. The start date for in-stream work will be in compliance with the permit and can be assumed to be no earlier than July

15, 2010.

Q: Who will move the trash bins near bridge 45.02.4?

A: The FS will move the trash bins prior to construction.