Q A AG-4419-S-10-0448.pdf

PDF 82 KB Posted

Attached to
RECOVERY** - TIMBER CRUISING AND MARKING, HURON NATIONAL FOREST
Solicitation number
AG-4419-S-10-0448
Issued by

View the file

Other files

File Type Posted
AMEND RFQ AG-4419-S-10-0448 FINALrev1.pdf PDF
SOL AG-4419-S-10-0448.pdf PDF
RFQ AG-4419-S-10-0448 FINAL.pdf PDF
SOL AG-4419-S-10-0448.pdf PDF
RFQ AG-4419-S-10-0448 FINAL.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS SOL # AG-4419-S-10-0448

Q- Bid requires certificate of insurance and a farm license. Not sure what is meant by farm license. Do you mean a auto license of some type? Never saw this requirement on any solicitation before. Please inform. Thanks, Mary Jo McGinnis Cedar Ridge Forestry, Inc.

A - A farm license is needed only if you are hiring any Migrant or Seasonal Agricultural workers for this project. It can be obtained from the Department of Labor. A certificate of insurance is also a requirement.

Q - Will you make separate awards for the line items or will one contractor get both?

Is the Price range 25,000 - 100,000 per line item or per the contract?

Does the Forest Service Provide the paint? Tracer or non-tracer?

A - Award could go to one contractor or we may award per item; price is for whole contract; Forest Service supplies tracer paint

Q - Contractor wanted to know if he is able to use subcontractors on this task. And can he include that within his response to the RFQ?

A – Contractors can be used as long as they cruise to our standards which we go over at the pre-work meeting.