CIM-0919-8R-413-0919-05
(ANF DEFERRED ROAD MTCE & WATERSHED HEALTH II -
Brush Hollow Roads:
FR185, 185A, 239, 302, 302A, 302B, 304, 369, 497, 497A, 497B, 497C)
FR 185 Little Mill Creek (Level C)
Station Road Log/Work Description
0+00 Intersection with State Route 948
61+10 FR 499 left
108+85 FR 185E right
108+85 FR 185C left
131+88 FR 185F right
156+50-273+63 Recondition roadbed, see TYPICAL RECONDITION
SECTION, clean all culverts and ditches, perform roadside brushing, see TYPICAL BRUSHING DETAIL
156+50 FR 239 left
157+50 Remove 18” x 28’ CMP, install 18” x 30’ CMP, apply 12 CY pit run
163+00 Turnout right
166+00 OGM road right
172+50 Turnout left
175+20 FR 185D left
178+75 Remove 24” x 32’ CMP, install 24’ x 36’ CMP, apply 12 CY pit run
180+00 Parking area left
182+00 Turnout left
191+50 FR 185B left
191+50 FR 185G right (road to pit site), install road number sign right
(perform brushing on pit road, this work is incidental to PAY
ITEM 651 Pit Development)
FR 185 Little Mill Creek (Level C) (con’t)
192+00 Turnout left
196+10 Remove 24” x 30’ CMP, install 18” x 32’ CMP, apply 12 CY
199+50 Turnout right
207+00 Turnout left
211+00 Remove 24” x 31’ CMP, install 18” x 32’ CMP, apply 12 CY
216+09 Camping area left
217+00 18” x 30’ CMP
222+00 Turnout left
226+40 FR 369 left
226+75 Pipeline crossing
228+00 Remove 18” x 30’ CMP, install 18” x 30’ CMP, apply 12 CY
230+50 Turnout left
238+00 Turnout left
242+30 FR 185A left
248+00 Turnout left
250+25 Remove 18” x 30’ CMP, install 18” x 30’ CMP, apply 12 CY
252+53 OGM road right
258+00 Turnout left
260+75 18” x 28’ CMP
FR 185 Little Mill Creek (Level C) (con’t)
265+50 Turnout left
268+50 18” x 32’ CMP
273+12 STOP sign right
273+12 Road number sign left
273+63 Intersection with Township road 359, end road reconditioning
FR 185A - Little Mill Creek A
0+00 FR 185 Station 242+30
0+00-12+00 Recondition roadbed, see TYPICAL RECONDITION
SECTION, clean all culverts and ditches, apply 6” pit run surfacing, perform roadside brushing see TYPICAL
BRUSHING DETAIL (12’ from shoulder)
0+05 18” x 40’ steel casing, clean inlet and outlet
0+20 Install road number sign and post right, STOP sign left
0+60 Forest Service gate, re-paint and install lock open post (Forest
Service to provide gate pin and lock)
7+00 Install 15” x 20’ steel casing from 8+00, apply 12 CY pit run
8+00 Remove 15” x 20’ steel casing taking it to Station 7+00, apply
12 CY pit run
11+65 Turnaround left, old bermed road template, apply 24 CY pit run
12+44 Install 18” x 24’ CMP, apply 12 CY pit run
12+00-16+80 Recondition roadbed, see TYPICAL RECONDITION
SECTION, apply 9” pit run aggregate
FR 239 Cherry Mill Run
0+00 FR 185 Station 156+50
0+00-47+40 Recondition roadbed see TYPICAL RECONDITION SECTION, perform roadside brushing (light) see TYPICAL BRUSHING
DETAIL
0+00-47+40 Apply 6” pit run surfacing
0+35 Road number sign on carsonite post right, install STOP sign left
1+80 Forest Service gate, re-paint and install ROAD CLOSED sign and barricade markers
3+85 Remove 18” x 24’ CMP, install 18” x 24’ CMP, apply 12 CY pit run
4+60 CAUTION: BURIED PIPELINE left side of road (runs close to pipe outlets)
7+30 Install 18” x 24’ CMP, apply 12 CY pit run
7+40-8+70 Turnout right
9+65 Remove 18” x 22’ CMP on LFS, apply 12 CY pit run
11+45 18” x 24’ CMP on LFS, repair inlet
11+50-12+60 Turnout right
12+60-22+00 Spot surface with 120 CY pit run
13+23 Access road right
15+80 18” x 26’ CMP on LFS
16+00-17+25 Turnout right
22+00 FR 239A left
22+20 Existing dip, install 18” x 24’ CMP, apply 12 CY pit run
FR 239 Cherry Mill Run (con’t)
24+15 Existing dip, install 18” x 24’ CMP, apply 12 CY pit run, old lane or pipeline corridor left
27+20 Existing dip, install 18” x 24’ CMP, apply 12 CY pit run
28+00 Small turnout left
29+25 Remove 18” x 24’ CMP, install 18” x 26’ CMP, apply 12 CY pit run
33+30 Existing dip, install 18” x 24’ CMP, apply 12 CY pit run
33+50-40+00 Construct ditch right
40+00 Turnaround right
47+40 End reconditioning
FR 302 Ellithorpe
0+00 Edge of pavement SR 4009
0+00-100+85 Recondition roadbed, see TYPICAL RECONDITION brushing see TYPICAL BRUSHING DETAIL
0+00-100+85 Apply 6” pit run surfacing
0+10 21” x 15” x 40’ CMPA
0+20 STOP sign left, clean
0+50 Road number sign right
0+75 Road left
3+60 Reconstruct leadoff ditch right
3+80-4+40 5 car parking lot right
4+45 Repair Forest Service gate, bent cross bar, see TYPICAL
GATE DETAIL, replace all signs
5+00 FR 304 left
6+60 Remove 18” CMP, install 18” x 26’ CMP on left forward skew, apply 12 CY pit run
7+50 OGM road left to well 1314
7+75-9+25 Turnout right
11+95 Remove 18” x 24’ CMP, install 18” x 26’ CMP on left forward skew, apply 12 CY pit run
13+50 OGM road right to well 4460, maintain access
13+95 3” NFG pipeline crossing
FR 302 Ellithorpe (con’t)
18+60-19+35 Reconstruct turnout right, apply 24 CY pit run
23+75 FR 302A right
25+65 18” x 26’ CMP on left forward skew
26+20 Install 15” x 26’ steel casing in low spot (field locate), apply 12
CY pit run
26+75 FR 302B left
26+80 Clearing right, old well pad
27+40 Remove 21” x 15” x 30’ CMPA, install 18” x 32’ CMP, apply
29+40-30+75 Turnout left
31+00 Begin ditch left
33+50 Skid road or OGM road right
35+60 Old lane or pipeline corridor left
36+00 Turnout right
36+80-45+60 Apply 6” pit run surfacing
36+85 18” x 28’ CMP (sag vertical curve)
38+50-40+00 Turnout right
45+20 18” x 28’ CMP, jack open inlet
45+35 OGM road left
46+00 Plugged well left
46+85-48+20 Turnout left
51+80 18” x 34’ CMP, clean inlet and outlet
56+50 Turnaround left in excavated pit area (crest vertical curve)
58+25 18” x 30’ CMP, clean inlet and outlet
59+00 Tennessee Gas pipeline crossing (HIGH PRESSURE) Telephone
814-274-9393
59+25 Access road to pipeline left and right
60+60 Entrance road to pit site left, road covered with fallen trees, remove
61+20 21” x 15” x 30’ CMPA on right forward skew, ends buried, clean
61+25-63+75 Turnout left, brushing needed
66+25 Remove 21” x 15” x 32’ on right forward skew, install 18” x 34’
CMP, apply 12 CY pit run
66+50-68+00 Combination turnout/turnaround, remove branches, debris, wood, shallow turnaround
70+30 18” x 34’ CMP, clean woody debris from inlet and outlet
74+75 18” x 30’ steel casing
75+50-77+25 Turnout left
77+70 Remove 18” x 38’ CMP on right forward skew, install 24” x
38’ CMP, apply 24 CY pit run (spring)
80+45 Remove 24” x 30’ on right forward skew, install 30” x 32’
CMP, apply 24 CY pit run (live drain)
80+70 Combination turnout/turnaround right (remove vegetation)
82+00 Old road right and left, clean ditch on the upper side of road left
82+30 Remove culvert, install 18” x 24’ CMP, apply 12 CY pit run
84+70 Construct curve widening right, apply 12 CY pit run surfacing
85+00 Install 18” x 24’ CMP, apply 12 CY pit run
87+20 Old road left, blocked
89+10 Install 18” x 24’ CMP, apply 12 CY pit run
93+50 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
94+00 Construct turnout right, apply 24 CY pit run
99+40 Turnout right, apply 24 CY pit run
100+20 Turnaround left, apply 24 CY pit run
100+85 End road reconditioning, road continues
102+65 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
108+70 OGM turnaround left
114+55 OGM road left
117+00 OGM road and pipelines
117+85 End of road
FR 302A Ellithorpe Spur A
0+00 FR 302 station 23+75
0+00-71+00 Recondition roadbed to TYPICAL RECONDITION
SECTION, clean all culverts and ditches, perform heavy roadside brushing and small tree removal see TYPICAL
BRUSHING DETAIL
0+08 Remove 12” x 40’ casing plugged and buried not functional, install 18” x 42’ CMP, apply 24 CY pit run
0+60 Replace road number sign right, install STOP sign left
1+85 Plugged well site left
4+25 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP on right forward skew, apply 12 CY pit run
7+75 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP on right
9+50-11+00 Entrenched template, no ditch, widen right for ditch construction
11+50 Crest vertical curve
14+00-15+50 Entrenched template, no ditch, widen right for ditch
15+50 Construct leadoff ditch right and left
16+00 Well right, plugged
16+50-18+50 Minor rutting (2-3”) apply 6” pit run, begin entrenched template, needs widening for ditch construction left
19+80 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP on right
FR 302A Ellithorpe Spur A (con’t)
21+40 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP on right
24+40 Remove 12” x 20’ CMP, apply 12 CY pit run, 24+70 Road right
24+90 Y intersection, OGM spur straight ahead, FR 302A bends left uphill
25+00-29+00 Entrenched template, no ditch, widen left for ditch
25+50 Construct leadoff ditch right
30+25 Construct turnout right, apply 24 CY pit run
35+00 Construct leadoff ditch left and right
35+10 Well right
37+50-38+65 No ditch, widen right for ditch construction
38+65 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
38+70-47+50 No ditch, widen right for ditch construction, 3’ cut bank
40+50 Turnaround left
45+20 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
CY pit run (sag vertical curve)
46+55 Crest vertical curve, construct turnout left see TYPICAL
TURNOUT SECTION, apply 36 CY pit run
50+10 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
51+20-60+80 Minor rutting (2”), apply 6” pit run surfacing
FR 302A Ellithorpe Spur A (con’t)
53+70 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
59+10 TGT pipeline crossing
59+80-70+00 Apply 9” pit run surfacing
67+00 Install 18” x 24’ CMP, apply 12 CY pit run
70+00 Turnaround left, end reconditioning
72+00-72+25 NFG pipeline crossing
FR 302 B Ellithorpe Spur B
0+00 FR 302 station 26+50
0+00-13+60 Recondition roadbed, see TYPICAL RECONDITION brushing see TYPICAL BRUSHING DETAIL, apply 6” pit run surfacing
0+30 Install road number sign right
0+90 18” x 26’ CMP, clean inlet and outlet
2+50 Skid trail right
5+65-6+80 Construct turnout left, apply 36 CY pit run
8+95 Turnaround right
13+60 Road stops at waterbar, rough skid trail continues ahead
FR 304 Cherry Mill
0+00 FR 302 Station 5+10
0+00-58+82 Recondition roadbed see TYPICAL RECONDITION
SECTION, perform roadside brushing see TYPICAL
0+00-58+82 Apply 9” pit run surfacing
0+25 Road number sign right
0+30 Install STOP sign left (reverse)
6+15 NFG pipeline crossing
11+10 Remove 12” x 24’ steel casing, replace with 18” x 26’ CMP, 16+30 Remove 12” x 20’ steel casing, replace with 18” x 24’ CMP, 19+75 Old road location right, with blocked access
21+50 Remove 12” x 20’ culvert, replace with 18” x 24’ CMP, apply
25+50 Remove 12” x 20’ culvert, replace with 18” x 24’ CMP, apply
28+50 Old road right and railroad grade
38+00 Remove 12” x 20’ steel casing, replace with 18” x 24’ CMP, 41+20 Remove 12” x 20’ steel casing, replace with 18” x 24’ CMP, 44+00 Remove 12” x 20’ steel casing, replace with 18” x 24’ CMP, FR 304 Cherry Mill (con’t)
46+50 Spur road left
48+00 Remove 12” x 20’ steel casing, replace with 18” x 24’ CMP, 51+23 Remove 12” x 20’ steel casing, replace with 18” x 24’ CMP, 53+29 Remove 12” x 20’ steel casing, replace with 18” x 24’ CMP, 58+30 Construct turnaround left, apply 36 CY pit run
58+82 End of reconditioning, road continues
58+82-59+66 TGT pipeline crossing
FR 369 Wolf Run
0+00 FR 185 Station 226+40
0+00-11+60 Remove sod buildup, recondition roadbed to TYPICAL
RECONDITION SECTION, apply 6” pit run surfacing
0+00-6+00 Roadway centerline is aligned with the left side of pipeline right of way
0+72 Existing TGT farm gate in fenced right of way
6+00 Road leaves pipeline right of way to the left
11+48 Remove 12” x 28’ culvert, install 18” x 28’ CMP, apply 12 CY
11+60 Road continues, end of road reconditioning
14+00 Remove 12” x 20’ culvert, replace with 18” x 24’ CMP, apply
16+88 Outlet ditch right
20+58 Remove 12” x 20’ culvert, replace with 18” x 24’ CMP, apply
22+60 Remove 12” x 20’ culvert, replace with 18” x 24’ CMP, apply
25+00-26+00 Log landing
25+80-26+00 Turnaround left
FR 497 Ogrin Farm
0+00 Intersection with T326, 1.3 miles from SR948
0+00-67+05 Recondition roadbed to TYPICAL RECONDITION
0+00-17+00 Apply 6” pit run surfacing
0+30 Road number sign right
0+35 INSTALL STOP sign left
1+70-2+30 Parking lot right 30’ deep
2+50 Forest Service gate, replace all signs on gates
4+00 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
9+00 Install 18” x 24’ CMP, apply 12 CY pit run
10+80 Leadoff ditch right
12+00 Leadoff ditch left
13+75 Leadoff ditch right
16+80 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
17+00 FR 497A left, construct turnaround left, apply 36 CY pit run surfacing (field locate)
20+00 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
22+68 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
FR 497 Ogrin Farm (con’t)
23+00-24+50 Turnout left
29+00 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
34+58 18” x 22’ CMP
44+10 FR 497B left
47+00 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
53+50 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
55+55 FR 497C right
58+00 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
62+00 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
65+10 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
65+50-67+00 Turnout right
68+81 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
71+51 Remove 12” x 28’ CMP, replace with 18” x 30’ CMP, apply 12
73+81 Remove 12” x 20’ CMP, replace with 18” x 24’ CMP, apply 12
80+95 Pit right, end road reconditioning
85+31-86+81 Turnout right
FR 497 Ogrin Farm (con’t)
86+81 12” x 20’ CMP
98+81 12” x 20’ CMP
103+81 12” x 26’ CMP
108+31 12” x 20’ CMP
108+71 Turnaround right
109+81 End of road
FR 497A Ogrin Farm A
0+00 FR 497 station 17+00
0+00-10+50 Recondition roadbed, see TYPICAL RECONDITION
SECTION, perform roadside brushing see TYPICAL
0+00-10+60 Apply 6” pit run surfacing
0+30 Replace road number sign right, install STOP sign left
0+57 Remove 6” steel pipe, install 16” x 22’ steel pipe casing, apply
2+10 Leadoff ditch right
2+54 Leadoff ditch left
4+00 Leadoff ditch left
7+74 Remove 6” steel pipe, install 16” x 22’ steel pipe casing, apply
9+24 Remove 12” x 22’ culvert, replace with 16” x 26’ CMP, apply
9+60 Well opening
9+80 Turnaround left
10+50 End of road
FR 497B Ogrin Farm B
0+00 FR 497 Station 44+35
0+00-9+10 Recondition roadbed, see TYPICAL RECONDITION
SECTION, clean ditch right, perform roadside brushing see
TYPICAL BRUSHING DETAIL (12’ from shoulder)
0+00-9+10 Apply 6” pit run surfacing to road and turnaround
0+50 Road number sign right
7+00 Install 18” x 24’ CMP, apply 12 CY pit run
8+55 Turnaround right
9+10 End of road
FR 497C Ogrin Farm C
0+00 FR 497 station 55+55
0+00-17+00 Recondition roadbed see TYPICAL RECONDITION
SECTION, clean all culverts and ditch lines, perform roadside
0+00-17+00 Apply 6” pit run surfacing to road including turnaround
0+05 Remove 12” x 40’ culvert replace with 16” x 40’ steel casing, apply 24 CY pit run
7+00 Remove 12” x 22’ culvert, replace with 18” x 26’ CMP, apply
15+00 Remove 12” x 22’ culvert replace with 18” x 26’ CMP, apply
16+10 Turnaround right
17+00 End of road, end reconditioning