Specifications_Low Gap Road No. 2 .doc
DOC document 297 KB Posted
- Attached to
- Patching and Overlay Paving Low Gap Road, Rabun County, GA Federal contract opportunity
- Solicitation number
- AG-435H-S-10-0015
About this file
Specifications
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bid Abstract Low Gap Paving.pdf | ||
| BidAmendmentNo1.pdf | ||
| Drawings_Low Gap Road No. 2.pdf | ||
| OF-17 Offer | — | |
| IFB_Low Gap Road No. 2.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATION MANUAL
FOR
CHATTOOGA RIVER RANGER DISTRICT
LOW GAP ROAD IMPROVEMENTS
PREPARED BY:
USDA FOREST SERVICE
SOUTHERN REGION
CHATTAHOOCHEE-OCONEE NATIONAL FOREST
Table of Contents
1Table of Contents
Preface 101 - Terms, Format, and Definitions
101.01 Meaning of Terms
101.03 Abbreviations.
101.04 Definitions.
102 - Bid, Award, and Execution of Contract 102 Bid, Award, and Execution of Contract 103 - Scope of Work Deletions 104 - Control of Work Deletions
104.06 Use of Roads by Contractor
105 - Control of Material
105.02 Material Sources.
105.02(a) Government-provided sources.
105.05 Use of Material Found in the Work.
106 - Acceptance of Work
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims.
107.06 Contractor’s Responsibility for Work.
107.09 Legal Relationship of the Parties.
107.10 Environmental Protection.
108 - Prosecution and Progress 108 Delete.
109 - Measurement and Payment 109 Deletions
109.02 Measurement Terms and Definitions.
152 - Construction Survey and Staking
152.02 General.
Table 152-1 Tolerances for reestablishing P-line, traverse, and elevations.
Table 152-2 Cross section and slope stake tolerances.
155 - Schedules for Construction Contracts 155 Delete.
156 - Public Traffic
156.03 Accommodating Traffic During Work.
156.04 Maintaining Roadways During Work.
156.08 Traffic and Safety Supervisor.
203 - Removal of Structures and Obstructions
203.01 Description.
203.04 Removing Material.
203.05 Disposing of Material.
204 - Excavation and Embankment
204.09 Preparing Foundation for Embankment Construction.
204.10 Embankment Construction.
204.11 Compaction.
204.13 Sloping, Shaping, and Finishing.
Table 204-2 Construction tolerances.
204.13 Sloping, Shaping, and Finishing.
204.14 Disposal of Unsuitable or Excess Material.
204.15 Acceptance
Table 204-1 Sampling and Testing Requirements.
301 - Untreated Aggregate Courses 301 Title Change.
301.01 Work.
301.02 Material.
301.03 General.
301.04 Mixing and Spreading.
301.05 Compacting
301.06 Surface Tolerance.
Table 301-1 Field Density Requirements.
Table 301-1—Acceptance Sampling and Testing Requirements.
301.08(b) Plasticity Index.
401 - Superpave Hot Asphalt Concrete Pavement
401.16 (b)International roughness index (IRI).
Table 401-4 Type IV Pavement Roughness 412 - Asphalt Tack Coat 430 - Asphalt Pavement Patching 635 - Temporary Traffic Control
635.03 General.
718 - Traffic Signing and Marking Material
Preface
Preface_wo_03_15_2004_m Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
| mp |
| Milepost |
| ppm |
| Part Per Million |
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
· Exact time and location of spill including a description of the area involved.
· Containment procedures.
· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
152 - Construction Survey and Staking
152.00_nat_us_08_05_2005
Description 152.01(c) Material.
Add the following:
Use required stake dimensions and materials. Pre-paint the top 2 inches of all stakes and lath, or mark them with plastic flagging. Use designated colors for paint or flagging. Mark all stakes with a stake pencil that leaves a legible imprint, or with waterproof ink.
Do not use aerosol spray paints.
Use moisture-resistant paper for survey notes. Keep notes in books with covers that will protect the contents and retain the pages in numerical sequence.
Construction Requirements
152.02 General.
Delete the first two sentences.
Add the following:
When indicated on the plans, a preliminary survey line has been established on the ground. The project location line is established by offsets from this preliminary line.
Delete second sentence in second paragraph and replace with the following:
Reestablish missing reference, control lines, or stakes as necessary to control subsequent construction staking operations
152.03 Survey and Staking Requirements.
(b) Roadway cross-sections.
Replace the first two sentences with the following:
Take roadway cross-sections normal to centerline. When the centerline curve radius is less than or equal to 200 feet, take cross-sections at a maximum centerline spacing of 25 feet. When the centerline curve radius is greater that 200 feet take cross-sections at a maximum centerline spacing of 80 feet.
c) Slope Stakes & References:
Replace section with the following:
Slope stakes and references. When required, locate slope stakes on designated portions of the road. Locate the slope stake catch points and use them to establish clearing limits and slope stake references.
Mark slope stakes with the station, the amount of cut or fill, the horizontal distance to centerline, and the slope ratios.
Place slope reference stakes at least 10 feet outside the clearing limit and mark with the offset distance to the slope stake. Place sight stakes when required.
Prior to clearing and grubbing operations, move the slope stake outside the clearing limit to the slope reference stake. After clearing and grubbing and before excavation, reset the slope stakes in their original position.
Use the designated method to establish the slope stake catchpoint.
· Method I—Computed Method. Use the template information shown in the plans or other Government-provided data to calculate the actual location of the catchpoint. The slope stake “catchpoint distance” provided may be used as a trial location to initiate slope staking. Recatch slope stakes on any section that does not match the staking report within the tolerances established in Table 152-2.
· Method II—Catchpoint Measurement Method. Determine the location of slope stake catchpoints by measuring the catchpoint distances shown in the plans or other Government-provided data.
(d) Clearing and grubbing limits.
Add the following:
Establish clearing limits on each side of the location line by measuring the required horizontal or slope distances shown in the stake notes. Mark the clearing limits with flagging or tags on trees to be left standing, or on lath. Make markings intervisible, and no more than 90 feet apart.
After establishing clearing limits, move the location line stake outside the clearing limits for station identification purposes, and mark it with horizontal distance to location line
(e) Centerline reestablishment.
Replace with the following:
Reestablish centerline from instrument control points. The maximum spacing between centerline points is 25 feet when the centerline curve radius is less than or equal to 200 feet. When the centerline curve radius is greater than 200 feet, the maximum distance between centerline points is 80 feet.
(g) Culverts.
Replace subsection with the following:
Set culvert reference stakes at all culvert locations. Set a culvert reference stake on the centerline of the culvert 10 feet from each end or beyond the clearing limit, whichever is greater. Record the following on culvert reference stakes:
(1) Diameter, actual field measured length, and type of culvert.
(2) The vertical and horizontal distance from the reference stake to the invert at the ends of the culvert.
(3) Station of actual point where culvert intersects centerline.
When required, stake headwall for culverts by setting a hub with a guard stake on each side of the culvert on line with the face of the headwall. Perform this work after clearing is completed.
152.03 (l) Miscellaneous Survey and Staking.
Add the following:
(11) Cattleguards
(12) Drain Dips
(13) Erosion Control Measures
Replace Table 152-1 with the following two tables:
Table 152-1 Tolerances for reestablishing P-line, traverse, and elevations.
| Precision Class |
| Minimum Position Closure |
| Angular Accuracy (±) |
| L-Line Tangent Control Pointsa (±) |
| Vertical Closureb (±) |
A
(Bridges)
| 1/10,000 |
| 2 sets, direct/reverse |
10 second rejection limit
| N/A |
| 0.02 ft or |
0.02ft/1000ftc
| B |
| 1/5,000 |
| 2 sets, direct/reverse |
20 second rejection limit
| 0.1 ft |
| 0.02 ft or |
0.02ft/1000ftc
| C |
| 1/1,000 |
| 1 set, direct/reverse |
1 minute rejection limit
| 0.2 ft |
| 0.5ft/1000ftc |
| D |
| 1/300 |
| Foresight and backsight; 15 minute rejection limitc |
| 0.4 ft |
| 1.0ft/1000ftc |
| E |
| 1/100 |
| Foresight and backsight; 30 minute rejection limitc |
| 0.8 ft |
| 1.0ft/1000ftc |
a. Accuracy of offset measurement.
b. Determine vertical closures at intervals not to exceed 2000 ft as measured along centerline.
c. Use greater value.
Table 152-2 Cross section and slope stake tolerances.
| Item |
| Tolerances |
| A |
| B |
| C |
| D |
| E |
| Allowable deviation of cross-section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves |
| (±)2o |
| (±)3o |
| (±)3o |
| (±)5o |
| (±)5o |
| Take cross-sections topography measurements so that variations in ground from a straight line connecting the cross-section points will not exceed |
| 0.5 ft |
| 1.0 ft |
| 2.0 ft |
| 2.0 ft |
| 3.0 ft |
| Horizontal and vertical accuracy for cross-sections, in feet or percentage of horizontal distance measured from traverse line, whichever is greater. |
| 0.1 ft or 0.4% |
| 0.15 ft or 0.6% |
| 0.2 ft or 1.0% |
| 0.2 ft or 1.0% |
| 0.3 ft or 1.0% |
Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured from centerline or reference stake, whichever is greater.
| Slope reference stakes and slope stakes. |
| 0.1 ft or 0.4% |
| 0.15 ft or 0.6% |
| 0.2 ft or 1.0% |
| 0.2 ft or 1.0% |
| 0.3 ft or 1.0% |
| Clearing limits |
| 1.0 ft |
| 1.0 ft |
| 1.0 ft |
| 1.5 ft |
| 2.5 ft |
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
156 - Public Traffic
156.03_nat_us_02_24_2005
156.03 Accommodating Traffic During Work.
Delete the following from the last paragraph:
according to Subsection 106.07(b)
156.04_nat_us_02_24_2005
156.04 Maintaining Roadways During Work.
(a) Add the following:
Do not construct detours outside of the clearing limits or use alternate route detours without the approval of the CO.
156.08_nat_us_02_24_2005
156.08 Traffic and Safety Supervisor.
Delete this subsection in its entirety.
203 - Removal of Structures and Obstructions
203.01_nat_us_02_25_2005
203.01 Description.
Delete and replace with the following:
This work consists of disposing of construction slash and debris, salvaging, removing, and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions.
203.04_nat_us_02_18_2005
203.04 Removing Material.
Replace the fourth and fifth paragraphs with the following:
Where part of an existing culvert is removed, remove the entire culvert upstream from the removal. The remaining downstream culvert may be left in place if no portion of the culvert is within 12 inches of the subgrade, embankment slope, or new culvert or structure; and the culvert ends are sealed with concrete.
Remove structures and obstructions in the roadbed to 12 inches below subgrade elevation. Remove structures and obstructions outside the roadbed to 12 inches below finished ground or to the natural stream bottom.
203.05_nat_us_02_18_2005
203.05 Disposing of Material.
Add the following:
(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toeline of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees. Obtain approval for pioneer roads. A pioneer road may be constructed to provide an area for placement of windrows, provided the excavated material is kept within the clearing limits and does not adversely affect the road construction.
(f) Scattering. Scatter construction slash outside the clearing limits without damaging trees. Limb all logs. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations.
(g) Chipping or Grinding. Use an approved chipping machine to grind slash and stumps greater than 3 inches in diameter and longer than 3 feet. Deposit chips or ground woody material on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.
(i) Decking Firewood Material. Remove brush from decks. Limb and deck logs that do not meet Utilization Standards according to Subsection 201.04 as directed by the CO. Cut logs to lengths less than 30 feet. Ensure that logs stacks are stable and free of brush and soil.
(j) Removal to designated locations. Remove construction slash to designated locations.
(k) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps. Cut unmerchantable logs into lengths of less than 20 feet.
(l) Placing Slash on Embankment Slopes. Place construction slash on completed embankment slopes to reduce soil erosion. Place construction slash as flat as practicable on the completed slope. Do not place slash closer than 2 feet below subgrade. Priority for use of available slash is for: (1) through fills; (2) insides of curves; and (3) ditch relief outlets.
(m) Hydrological Sensitive Placement. Where required use this method in combination with other designated methods to dispose of material to reduce erosion and to aid in re-vegetation:
1. Place windrow segments on contours, wrap in type I geotextile.
2. Place logs as log erosion barriers on contours. Place logs so that 80% of their length is on the ground surface.
3. Scatter slash on bare or disturbed areas within or outside the clearing limits as directed.
4. Scatter chips or ground woody material on bare or disturbed areas within or outside the clearing limits as directed.
Place stumps in swales or on sites to form planting pockets. Place windrow segments on contours, wrap in type I geotextile.
204 - Excavation and Embankment
204.05_nat_us_02_18_2005
204.05 Conserved Topsoil
Delete the entire paragraph.
204.09_nat_us_03_02_2005
204.09 Preparing Foundation for Embankment Construction.
Delete subsection (a) and replace it with the following:
(a) Embankment less than 4 feet high over natural ground. When designated, remove topsoil and break up the ground surface to a minimum depth of 6 inches by plowing or scarifying. Compact the ground surface according to Subsection 204.11.
204.10_nat_us_03_02_2005
204.10 Embankment Construction.
Add the following:
Obtain written approval before beginning construction of embankments over 6 feet high at subgrade centerline.
(a) General.
Delete the third paragraph and add the following:
Compact embankment side slopes flatter than 1V:1.75H with a tamping type roller or by walking with a dozer. For slopes 1V:1.75H or steeper, compact the slopes as construction of the embankment progresses.
204.11_nat_us_04_11_2005
204.11 Compaction.
Delete the first paragraph and replace it with the following:
For compaction according to method (a), (b), or (c), use AASHTO T 27 to determine the amount of material retained on a Number. 4 sieve. For compaction methods (d) or (e) no sieve test is required.
Add the following compaction methods:
(d) Layer Placement Method (Hauling and Spreading Equipment). Place material by end dumping to the minimum depth needed for operation of spreading equipment. Level and smooth each embankment layer before placing the next layers. Operate hauling and spreading equipment uniformly over the full width of each layer. Construct a solid embankment with adequate compaction by working smaller rock and fines in with the larger rocks to fill the voids, and by operating hauling and spreading equipment uniformly over the full width of each layer as the embankment is constructed.
(e) Layer Placement (Roller Compaction) Method. Place material by end dumping to the minimum depth needed for operation of spreading equipment. Adjust the moisture content of the material to obtain a mass that will not visibly deflect under the load of the hauling and spreading equipment. Operate compaction equipment over the full width of each layer until visible deformation of the layer ceases or, in when a sheepsfoot roller is used, the roller “walks out” of the layer. Make at least three complete passes.
204.13_nat_us_03_02_2005
204.13 Sloping, Shaping, and Finishing.
Delete section (d) and add the following:
(d) Finishing. For surfaced roads, remove all material larger than 6 inches from the top 6 inches of the roadbed. For all roads, finish the roadbed to be smooth and uniform, and shaped to conform to the typical sections. Remove unsuitable material from the roadbed and replace it with suitable material. Finish roadbeds to the tolerance class shown in table 204-2.
Ensure that the subgrade for both surfaced and unsurfaced roads is visibly moist during shaping and dressing. Scarify to 6 inches below the bottom of low sections, holes, cracks, or depressions and bring back to grade with suitable material. Maintain proper ditch drainage.
For unsurfaced roads, use one of the following methods to finish the roadbed:
(1) Method A. Remove all material larger than 6 inches from the top 6 inches of the roadbed and replace with suitable material.
(2) Method B. Use a vibratory grid roller or approved equal with a minimum weight of 10 tons. Roll at least 5 full-width passes or until visible displacement ceases.
(3) Method C. For roads designated as Construction Tolerance Class K, L, or M, finish the roadbed by spreading the excavation. Eliminate rock berms.
Add Table 204-2—Construction Tolerances:
Table 204-2 Construction tolerances.
Tolerance Class(a)
| A |
| B |
| C |
| D |
| E |
| F |
| G |
| H |
| I |
| J |
| K |
| L |
| M |
| Roadbed width (ft) |
| +0.5 |
| +0.5 |
| +1.0 |
| +1.0 |
| +1.0 |
| +1.0 |
| +1.5 |
| +1.0 |
| +2.0 |
| +2.0 |
| +2.0 |
| +2.0 |
| +2.0 |
Subgrade elevation
(ft)
| +0.1 |
| +0.2 |
| +0.2 |
| +0.5 |
| +0.5 |
| +1.0 |
| +1.0 |
| +1.5 |
| +2.0 |
| +3.0 |
| +2.0 |
| +3.0 |
| (c) |
| Centerline alignment (ft) |
| +0.2 |
| +0.2 |
| +0.5 |
| +0.5 |
| +1.0 |
| +1.0 |
| `+1.5 |
| +1.5 |
| +2.0 |
| +3.0 |
| +3.0 |
| +5.0 |
| (c) |
| Slopes, excavation, and embankment (% slope(b) |
| +3 |
| +5 |
| +5 |
| +5 |
| +5 |
| +5 |
| +10 |
| +10 |
| +10 |
| +10 |
| +20 |
| +20 |
| +20 |
a. Maximum allowable deviation from construction stakes and drawings.
b. Maximum allowable deviation from staked slope measured from slope stakes or hinge points.
c. Unless otherwise shown the centerline alignment and subgrade elevation, as built, have no horizontal curves with a radius of less than 80 feet, and no vertical curves with a curve length of less than 80 feet when the algebraic difference in the grade change is less than 10 percent, or a curve length of less than 100 feet when the algebraic difference of the grade change is greater than or equal to 10 percent. The centerline grade is not to exceed 20 percent in 100 feet of length.
204.13_nat_us_03_02_2005
204.13 Sloping, Shaping, and Finishing.
(a) Sloping.
Add the following:
Slope rounding is not required on tolerance class D though M roads.
204.14 Disposal of Unsuitable or Excess Material.
Delete the text of the first paragraph and substitute the following:
Dispose of unsuitable or excess material legally off of the project.
204.15_nat_us_02_07_2007
204.15 Acceptance
Table 204-1 Sampling and Testing Requirements.
Add the following note to the table:
(2) When compaction methods (d) or (e) are used AASHTO M 145, T 99, T 180, and T 310 are not required for earth embankment test methods.
301 - Untreated Aggregate Courses
301.00_nat_us_03_03_2005
301 Title Change.
Change the title to: Section 301 Aggregate Courses 301.01_nat_us_03_03_2005
301.01 Work.
Add the following:
Work includes producing aggregate by pit-run, grid rolling, screening, or crushing methods, or placing Government-furnished aggregate. Work may include additive mineral filler, or binder.
301.02_nat_us_05_16_2005
301.02 Material.
Add the following:
| Bentonite |
| 725.30 |
| Calcium Chloride Flake |
| 725.02 |
| Lignon Sulfonate |
| 725.20 |
| Magnesium Chloride Brine or Calcium Chloride Liquid |
| 725.02 |
301.03_nat_us_09_14_2005
301.03 General.
Add the following:
Written approval of the roadbed is required before placing aggregate.
For pit run or grid-rolled material, furnish material smaller than the maximum size. No gradation other than maximum size will be required for pit-run or grid-rolled material. For grid rolling, use all suitable material that can be reduced to maximum size. After processing on the road, remove all oversize material from the road and dispose of it as directed by the CO.
Provide additives or binder, if required, at the proportions specified.
Develop and use Government furnished sources according to Section 105.
If the aggregate is produced and stockpiled before placement, handle and stockpiled according to Section 320. Establish stockpile sites at locations approved. Clear and grub stockpile sites according to Section 201.
301.04_nat_us_03_03_2005
301.04 Mixing and Spreading.
Delete the first sentence of the first paragraph and add the following:
Ensure that aggregate and any required additives, water, mineral filler, and binder are mixed by the specified method except, if crushed aggregate products are being produced and mineral filler, binder, or additives are required, uniformly blend following crushing. Control additive proportions to 0.5 percent dry weight.
(a) Stationary Plant Method. Mix the aggregate with other required materials in an approved mixer. Add water during the mixing operation in the amount necessary to provide the moisture content for compacting to the specified density. After mixing, transport the aggregate to the jobsite while it contains the proper moisture content, and place it on the roadbed or base course using an aggregate spreader.
(b) Travel Plant Method. After placing the aggregate for each layer with an aggregate spreader or windrow-sizing device, uniformly mix it with other required materials using a traveling mixing plant. During mixing, add water to provide the necessary moisture content for compacting.
(c) Road Mix Method. After placing the aggregate for each layer, mix it with other required materials at the required moisture content until the mixture is uniform throughout. Mix aggregate, water, and all other materials until a uniform distribution is obtained.
Spread the aggregate in a uniform layer, with no segregation of size, and to a loose depth that will provide the required compacted thickness.
When placing aggregate over geotextile, place aggregate in a single lift to the full depth specified.
Route and distribute hauling and leveling equipment over the width and length of each layer.
301.05_nat_us_05_17_2005
301.05 Compacting
Delete and replace with the following:
Compact each layer full width. Roll from the sides to the center, parallel to the centerline of the road. Along curbs, headers, walls, and all places not accessible to the roller, compact the material with approved tampers or compactors.
Compact the aggregate using one of the following methods as specified:
Compaction A. Operating spreading and hauling equipment over the full width of the travelway.
Compaction B. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction C. Moisten or dry the aggregate to a uniform moisture content between 5 and 7 percent based on total dry weight of the mixture. Operate rollers and compact as specified in Subsection 204.11(a)(1).
Compaction D. Compact to a density of at least 95 percent of the maximum density, as determined by AASHTO T 99, method C or D.
Compaction E. Compact to a density of at least 96 percent of the maximum density, as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).
Compaction F. Compact to a density of at least 95 per-cent of the maximum density, as determined by AASHTO T 180, method C or D.
Compaction G. Compact to a density of at least 100 percent of the maximum density as determined by the Modified Marshall Hammer Compaction Method (available upon request from USDA Forest Service, Regional Materials Engineering Center, P.O. Box 7669, Missoula, MT 59807).
For all compaction methods, blade the surface of each layer during the compaction operations to remove irregularities and produce a smooth, even surface. When a density requirement is specified, determine the in place density and moisture content according to AASHTO T 310 or other approved test procedures.
301.06_nat_us_03_03_2005
301.06 Surface Tolerance.
Add the following:
Thickness and Width requirements:
The maximum variation from the compacted specified thickness is ½ inch. The compacted thickness is not consistently above or below the specified thickness and the average thickness of 4 random measurements for any ½ mile of road segment is within + ¼ inch of the specified thickness.
The maximum variation from the specified width will not exceed +12 inches at any point. The compacted width is not consistently above the specified width and the average of any four random measurements along any ½ mile of road segment is within +4 inches of the specified width.
301.08_nat_us_02_07_2007
Table 301-1 Field Density Requirements.
Table 301-1: Delete laboratory and field density requirements for base, subbase, and surfacing and replace with the following:
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Base and Subbase |
| Measured and tested conformance (Subsection 106.04) |
| Moisture Density |
| --- |
| Method C |
| --- |
| AASHTO T 99 |
| 1 per type and source of material |
| Source of material |
| Yes |
| Before using in work |
| Method C-1 |
| --- |
| R-1 Marshall |
| “ |
| “ |
| “ |
| “ |
| Method D |
| --- |
| AASHTO T 180 |
| “ |
| “ |
| “ |
| “ |
| Method D-1 |
| --- |
| R-1 Marshall |
| “ |
| “ |
| “ |
| “ |
| Compaction |
| --- |
| Method C, C-1, D, D-1 |
| --- |
| AASHTO T 310 or other approved procedures |
| 1 per 500 t |
| In-place |
| --- |
| Before placing the next layer |
| Surfacing |
| Measured and tested conformance (Subsection 106.04) |
| Moisture Density |
| Method C-1 |
| --- |
| R-1 Marshall |
| “ |
| “ |
| “ |
| Before using in work |
| Method D |
| --- |
| AASHTO T 180 |
| “ |
| “ |
| “ |
| “ |
| Method D-1 |
| --- |
| R-1 Marshall |
| “ |
| “ |
| “ |
| “ |
Compaction
| Method C, C-1, D, D-1 |
| --- |
| AASHTO T 310 or other approved procedures |
| 1 per 500 t |
| In-place |
| --- |
| Before placing the next layer |
301.08_nat_us_03_03_2005
Table 301-1: Add the following:
Table 301-1—Acceptance Sampling and Testing Requirements.
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Subbase & Base Courses L, M, N, O, P, Q, R |
| Measured and tested conformance (Subsection 106.04) |
| Plastic Limit |
| - |
| AASHTO T 90 |
| 1 per each 1,000 T |
| From the windrow or roadbed after processing |
| Yes |
| 4 Hours |
Table 301-1—Acceptance Sampling and Testing Requirements.
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Aggregate Width |
| Measured and tested conformance (Subsection 106.04) |
| Width |
| - |
| - |
| 4 per each 0.5 mi |
| Roadbed after processing |
| - |
| 4 Hours |
| Aggregate Thickness |
| Measured and tested conformance (Subsection 106.04) |
| Thickness |
| - |
| - |
| 4 per each 0.5 mi |
| Roadbed after processing |
| - |
| 4 Hours |
| Additive |
| Measured and tested conformance (Subsection 106.04) |
| Amount of Additive |
| - |
| 1 per each 1,000 T |
| From the windrow or roadbed after processing |
| No |
| 4 Hours |
301.08_nat_us_03_30_2005
301.08(b) Plasticity Index.
Add the following to the first sentence:
“and under 703.05(c)(1)”.
Chattahoochee-Oconee_06-01-2009
301.09 Measurement
Add the following after the first paragraph
Measure aggregate by the ton in the hauling vehicle.
301.10_nat_us_03_03_2005
301.10 Payment
Delete the following:
adjusted according to Subsection 106.05
401 - Superpave Hot Asphalt Concrete Pavement
401.01_nat_us_08_12_2004
401.16 (b)International roughness index (IRI).
Delete the first sentence of subsection 401.16(b) and substitute the following:
For type III or IV pavement roughness, furnish an inertial profiler conforming to AASHTO PP 50 and validated according to AASHTO PP 49.
401.04_nat_us_08_12_2004
Delete Table 401-4 and substitute the following:
Table 401-4 Type IV Pavement Roughness
Table 401-4
Type IV Pavement Roughness
Single Lift (1)
Percent Improvement Pay Adjustment
Factor (1) Multi-Lift (2) Percent Improvement
Pay Adjustment
Factor (2)
| Greater than 48.4 |
| PAF = 12.50 |
| Greater than 61.1 |
| PAF = 12.50 |
| 24.8 to 48.4 |
| PAF = 0.5274(%) – 13.027 |
| 43.3 to 61.1 |
| PAF = 0.6983(%) – 30.168 |
| 12.4 to 24.7 |
| PAF = 0.00 |
| 34.0 to 43.2 |
| PAF = 0.00 |
| 0.9 to 12.3 |
| PAF = 13.2609(%) – 40.435 |
| 25.4 to 33.9 |
| PAF = 4.3605(%) – 148.260 |
| Less than 0.9 |
| Reject (3) |
| Less than 25.4 |
| Reject (3) |
(1) For single lift overlays with no other corrective work such as milling, grinding or preleveling in excess of 25 percent of the surface area the of existing pavement.
(2) For multiple lift operations such as milling, grinding or preleveling followed by one or more lifts of pavement or two or more lifts of pavement without milling, grinding or preleveling.
(3) Pay adjustment factor when corrections are not allowed equals minus 37.5.
412 - Asphalt Tack Coat
412.07_nat_us_07_03_2007
Measurement
412.07 Acceptance
Delete the first paragraph and replace with the following:
Emulsified asphalt will be evaluated under Subsections 106.02, 106.03, and 702.07.
430 - Asphalt Pavement Patching
430.00_nat_us_07_27_2007
Description
430.01 This work consists of performing full depth patching, patching with geotextiles, skin patching, spray-injection patching, and removal and replacement of asphalt berms.
Material
430.02 Conform to the following Subsections:
| Minor Hot Asphalt Pavement |
| 404.02 |
| Asphalt Binder |
| 702.01 |
| Cutback Asphalt |
| 702.02 |
| Emulsified Asphalt |
| 703.03 |
| Application Temperatures |
| 702.04 |
| Cold Asphalt Mix |
| 702.10 |
| Aggregate |
| 703.07 (a) and (b) |
| Choker Aggregate |
| 703.12 |
| Geotextile Type VI |
| 714.01 |
| Sand |
| 703.15 |
Construction
430.03 Composition of Mix (Job-Mix Formula). Furnish either Minor Hot Asphalt Pavement or Minor Cold Asphalt Mix as approved by the CO.
430.04 Full Depth Patch.
Remove material to a minimum depth of 4 inches, or as necessary to reach firm support. If firm support for a patch is unavailable, notify the CO prior to placing any material.
Trim or mill the edges of the prepared hole to form a vertical face in un-fractured asphalt surfacing. Make the prepared hole rectangular, and clean it of all loose material. When the hole is dry, apply emulsified asphalt to the bottom and faces of the hole. Barricade prepared sites. Patch the sites immediately after the emulsified asphalt breaks. Place the asphalt concrete mixture in layers not exceeding 4 inches. Thoroughly compact each layer with hand or mechanical tampers or rollers. For hot asphalt concrete mixtures, compact the mix while it is above 230 °F.
Compact the finished surface with a steel-wheel roller or vibratory plate compactor. Ensure that the compacted patch is approximately 1/8 to 1/4 inches above the level of the adjacent pavement. Seal the edges of the completed patch with emulsified asphalt, and blot with fine sand.
430.05 Patching with Geotextile. Prepare the surface by digging out and patching according to Subsection 430.04 or by cleaning the surface, removing vegetation, and filling all cracks more than 1/4 inch wide with an approved crack-filling material. Remove excess crack-filling material. Spray the prepared surface with asphalt cement or emulsified asphalt according to the geotextile manufacturer’s direction. Immediately place the geotextile over the repaired area. Allow emulsified asphalt to break before placing geotextile. Extend the fabric a minimum of 6 inches beyond the repaired or patched area onto sound adjoining pavement. Use a minimum of 2 inches overlap where adjacent fabric panels are needed to cover the repaired area.
Do not place the asphalt concrete mixture until authorized by the CO. Uniformly distribute asphalt concrete mixture in layers not to exceed 2 inches compacted depth. Feather the edges of skin patches. When placing more than one layers, offset all joints at least 6 inches between layers. Compact each layer with an 8 to 10 ton steel roller. For hot asphalt concrete mixtures, compact the mix while it is above 230°F. Ensure that the completed patch does not have abrupt transitions that could adversely affect the steering of a passenger car traveling across the area. Provide transition tapers for skin patches that are 12 inches long per 1/8 inch thickness of patch in the direction on travel.
430.06 Skin Patches. Prepare the surface on which the skin patch is placed by cleaning the surface, removing vegetation, and filling all cracks more than 1/4 inch wide with an approved crack-filling material. Remove excess crack-filling material. Spray the surface with emulsified asphalt at the rate approved by the CO.
Apply the asphalt concrete mixture according to Subsection 430.05.
430.07 Spray-Injection Patching. Use an approved continuous process that cleans and dries the area to be patched, sprays a tack coat of binder on the sides and bottom of the pothole, place aggregate coated with emulsified asphalt, and covers the area with a choker aggregate.
430.08 Asphalt Berm. Remove damaged segments of berm and bevel exposed ends at approximately 45 degrees from vertical. Clean and patch the berm foundation as necessary. Coat the foundation and joining surfaces with emulsified asphalt. Place and compact asphalt mix to conform to the shape of the undamaged segment.
430.09 Waste Material. Dispose of all materials removed from potholes, patches, and berms in accordance with Subsection 203.05(a).
430.10 Acceptance. Asphalt concrete mixtures will be evaluated under Subsections 106.02 and 106.03. Geotextiles will be evaluated under Subsection 106.03. Spray-injection patching will be evaluated under Subsections 106.02 and 106.03.
Measurement
430.11 Measure the Section 430 items listed in the bid schedule according to Subsection 109.02.
Payment
430.12 The accepted quantities will be paid at the contract unit price per unit of measurement for Section 430 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05
635 - Temporary Traffic Control
635.03_nat_us_05_13_2004
635.03 General.
Add the following:
Install temporary traffic control signs to temporary posts or approved temporary sign mounts.
718 - Traffic Signing and Marking Material
718.05_nat_us_02_25_2008
718.05 Aluminum Panels
Delete the third paragraph and replace with the following:
Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM B-449.