Site_Visit_Questions-Raven_Cliff_.docx

DOCX document 13 KB Posted

Attached to
Raven Cliff Road Repairs (FSR 4052) George Washington & Jefferson NFs in VA
Solicitation number
AG-3395-S-16-0019
Issued by

About this file

Answers to questions from 5/11/16 site visit

View the file

Other files

File Type Posted
Description_of_Work.docx DOCX document
Davis_Bacon_Wage_Determination.docx DOCX document
Request_For_Quotation_Raven_Cliff.doc DOC document
FS_Supplemental_Specifications_-_Raven's_Cliff_Road_Repair.docx DOCX document
RD_RPR_PLNS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Raven Cliff Site Visit Questions/Answers 5/11/16

1) What are the Contractors supposed to do with the existing bituminous material once it is removed?

The existing bituminous material removed from the roadbed becomes the property of the Contractor and is to be properly disposed of off-site at the Contractors expense. Some or all of the material may possibly be used as filler material or stockpiled for use by the district at a later date, but those are possibilities and should not be counted as part of the bidding process.

2) How wide is the asphalt section of the road?

The asphalt section of the road will be 14’ in width. Rock used on the shoulders to maintain this uniformity will be incidental to paving.

3) How wide is the reconditioned (graveled) section of the road?

The reconditioned section of the road varies in width and shall be covered by aggregate according to those variances as directed by the Engineer.