Description_of_Work.docx

DOCX document 13 KB Posted

Attached to
Raven Cliff Road Repairs (FSR 4052) George Washington & Jefferson NFs in VA
Solicitation number
AG-3395-S-16-0019
Issued by

About this file

Description of Work - Raven Cliff Road

View the file

Other files

File Type Posted
Site_Visit_Questions-Raven_Cliff_.docx DOCX document
Davis_Bacon_Wage_Determination.docx DOCX document
Request_For_Quotation_Raven_Cliff.doc DOC document
FS_Supplemental_Specifications_-_Raven's_Cliff_Road_Repair.docx DOCX document
RD_RPR_PLNS.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Description of Work – Raven Cliff Road

BMP
EMP
Item Description
Quantity
Unit
0.00
0.15
Remove/repave w Bituminous Surface Treatment
0.15
MI
0.15
0.90
Aggregate Surface Replacement, Compaction Method B
600
TN
0.15
0.90
Road Reconditioning
0.75
MI

Pay item 303.07 consists of reconditioning of the roadway, ditches and aggregate surface according to FP-03 Section 303.07, Roadway Reconditioning. Reconditioning of ditches on the paved section of the road (M.P 0.00 to 0.015) is considered incidental to this item.

Pay item 403.01 consists of removing existing asphalt surface and subgrade from M.P. 0.0 to M.P. 0.15 in accordance with FP-03 Section 403. Excavate 6” below the existing asphalt and properly shape and compact the subgrade. Place and roller compact 6” (uncompacted depth) of VA #21B. Place 2” compacted depth of VA BM-25A and top with 1” compacted depth of VA SM-9.5A. Final surface shall be as close to the existing width, lines and grades as possible and shall provide a smooth transition at M.P 0.00 and M.P. 0.15. Aggregate and subgrade preparation related to pavement replacement is considered incidental to this item.

Pay item 322.01 consists of the placement of VA #26 aggregate in accordance with FP-03 Supplemental Specification 322. Roadway shall be prepared in accordance with item 303.07 prior to placement. Final depth of aggregate shall be 2” to 3” (compacted).

Pay item 625.08 consists of seeding and mulching all disturbed areas in accordance with FP-03 Supplemental Specification 625.

*A catalog of Forest Service typical drawings and construction details are included for reference.