Supplemental Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Children's_Forest_Road_PLANS.pdf | ||
| AG-3395-S-15-0018 _Children's_Forest.pdf | ||
| Children's_Forest_Description_of_Work_rev.docx | DOCX document | |
| Contractor's_Experience_questionnaire 1 .pdf | ||
| VA128_dvb.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FP-03 SUPPLEMENTAL SPECIFICATIONS FOR
FS 351 CHILDREN’S FOREST ROAD
GEORGE WASHINGTON- JEFFERSON NATIONAL FOREST
JAMES RIVER RANGER DISTRICT
Table of Contents
| Table of Contents | 2 |
| Preface | 4 |
| 101 - Terms, Format, and Definitions | 5 |
| 101.01 Meaning of Terms | 5 |
| 101.03 Abbreviations. | 5 |
| 101.04 Definitions. | 5 |
| 102 - Bid, Award, and Execution of Contract | 8 |
| 102 Bid, Award, and Execution of Contract | 8 |
| 103 - Scope of Work | 9 |
| Deletions | 9 |
| 104 - Control of Work | 10 |
| Deletions | 10 |
| 104.06 Use of Roads by Contractor | 10 |
| 105 - Control of Material | 11 |
| 105.02 Material Sources. | 11 |
| 105.02(a) Government-provided sources. | 11 |
| 105.05 Use of Material Found in the Work. | 11 |
| 106 - Acceptance of Work | 12 |
| 106.07 Delete | 12 |
| 107 - Legal Relations and Responsibility to the Public | 13 |
| 107.05 Responsibility for Damage Claims. | 13 |
| 107.06 Contractor’s Responsibility for Work. | 13 |
| 107.09 Legal Relationship of the Parties. | 13 |
| 107.10 Environmental Protection. | 13 |
| 108 - Prosecution and Progress | 15 |
| 108 Delete. | 15 |
| 109 - Measurement and Payment | 16 |
| 109 Deletions | 16 |
| 109.02 Measurement Terms and Definitions. | 16 |
| 151 - Mobilization | 17 |
| 155 - Schedules for Construction Contracts | 18 |
| 155 Delete. | 18 |
| 301 - Untreated Aggregate Courses | 19 |
| 301 Title Change. | 19 |
| 301.01 Work. | 19 |
| 301.02 Material. | 19 |
| 301.03 General. | 19 |
| 301.06 Surface Tolerance. | 20 |
| Table 301-1—Acceptance Sampling and Testing Requirements. | 21 |
| 301.08(b) Plasticity Index. | 22 |
| Table 301-1 Field Density Requirements. | 23 |
| 301.09 Measurement. | 24 |
| 303 - Road Reconditioning | 25 |
| 303.01 Work. | 25 |
| 303.06 Aggregate Surface Reconditioning. | 25 |
| 303.06 Asphalt and Aggregate Surface Reconditioning. | 25 |
| 303.10 Measurement | 26 |
| 602 - Culverts and Drains | 27 |
| 602.03 General. | 27 |
| 625 - Turf Establishment | 28 |
| 625.03 General. | 28 |
| 625.04 Preparing Seedbed. | 28 |
| 625.05 Watering | 28 |
| 625.06 Fertilizing. | 28 |
| 625.07 Seeding. | 29 |
| 625.08 Mulching. | 30 |
| 718 - Traffic Signing and Marking Material | 31 |
| 718.05 Aluminum Panels | 31 |
Preface Preface_wo_03_15_2004_m Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions 101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
| mp |
| Milepost |
| ppm |
| Part Per Million |
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S. Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract 102.00_nat_us_02_16_2005 102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work 103.00_nat_us_02_16_2005 Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work 104.00_nat_us_06_16_2006 Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005 Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material 105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work 106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public 107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
· Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
· Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
· Exact time and location of spill including a description of the area involved.
· Containment procedures.
· Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
· Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress 108.00_nat_us_02_16_2005 108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment 109.00_nat_us_02_17_2005 109 Deletions Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
151 - Mobilization 151.03_nat_us_08_05_2005
151.03 Payment
Delete the entire subsection and add the following:
151.03 Payment
Mobilization is considered an indirect cost of this contract and will not be compensated as a separate work item.
155 - Schedules for Construction Contracts 155.00_nat_us_05_11_2004 155 Delete.
Delete Section 155 in its entirety.
301 - Untreated Aggregate Courses 301.00_nat_us_03_03_2005 301 Title Change.
Change the title to: Section 301 Aggregate Courses
301.01_nat_us_03_03_2005
301.01 Work.
Add the following:
Work includes producing aggregate by pit-run, grid rolling, screening, or crushing methods, or placing Government-furnished aggregate. Work may include additive mineral filler, or binder.
301.02_nat_us_05_16_2005
301.02 Material.
Add the following:
| Bentonite |
| 725.30 |
| Calcium Chloride Flake |
| 725.02 |
| Lignon Sulfonate |
| 725.20 |
| Magnesium Chloride Brine or Calcium Chloride Liquid |
| 725.02 |
301.03_nat_us_02_28_2013
301.03 General.
Add the following:
Written approval of the roadbed is required before placing aggregate.
For pit run or grid-rolled material, furnish material smaller than the maximum size. No gradation other than maximum size will be required for pit-run or grid-rolled material. For grid rolling, use all suitable material that can be reduced to maximum size. After processing on the road, remove all oversize material from the road and dispose of it as directed by the CO.
Provide additives or binder, if required, at the proportions specified.
Develop and use Government furnished sources according to Section 105.
If the aggregate is produced and stockpiled before placement, handle and stockpiled according to Section 320. Establish stockpile sites at locations approved. Clear and grub stockpile sites according to Section 201.
301.06_nat_us_03_03_2005
301.06 Surface Tolerance.
Add the following:
Thickness and Width requirements:
The maximum variation from the compacted specified thickness is ½ inch. The compacted thickness is not consistently above or below the specified thickness and the average thickness of 4 random measurements for any ½ mile of road segment is within + ¼ inch of the specified thickness.
The maximum variation from the specified width will not exceed +12 inches at any point. The compacted width is not consistently above the specified width and the average of any four random measurements along any ½ mile of road segment is within +4 inches of the specified width.
301.08_nat_us_03_03_2005 Table 301-1: Add the following:
Table 301-1—Acceptance Sampling and Testing Requirements.
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Subbase & Base Courses L, M, N, O, P, Q, R |
| Measured and tested conformance (Subsection 106.04) |
| Plastic Limit |
| - |
| AASHTO T 90 |
| 1 per each 1,000 T |
| From the windrow or roadbed after processing |
| Yes |
| 4 Hours |
Table 301-1—Acceptance Sampling and Testing Requirements.
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Aggregate Width |
| Measured and tested conformance (Subsection 106.04) |
| Width |
| - |
| - |
| 4 per each 0.5 mi |
| Roadbed after processing |
| - |
| 4 Hours |
| Aggregate Thickness |
| Measured and tested conformance (Subsection 106.04) |
| Thickness |
| - |
| - |
| 4 per each 0.5 mi |
| Roadbed after processing |
| - |
| 4 Hours |
| Additive |
| Measured and tested conformance (Subsection 106.04) |
| Amount of Additive |
| - |
| 1 per each 1,000 T |
| From the windrow or roadbed after processing |
| No |
| 4 Hours |
301.08_nat_us_03_30_2005 301.08(b) Plasticity Index.
Add the following to the first sentence:
“and under 703.05(c)(1)”.
301.08_nat_us_10_14_2011 Table 301-1 Field Density Requirements.
Table 301-1: Delete laboratory and field density requirements for base, subbase, and surfacing and replace with the following:
| Material or Product |
| Type of Acceptance (Subsection) |
| Characteristic |
| Category |
| Test Methods Specifications |
| Sampling Frequency |
| Point of Sampling |
| Split Sample |
| Reporting Time |
| Base and Subbase |
| Measured and tested conformance (Subsection 106.04) |
| Moisture Density |
| --- |
| Method C |
| --- |
| AASHTO T 99 |
| 1 per type and source of material |
| Source of material |
| Yes |
| Before using in work |
| “ |
| “ |
| “ |
| “ |
| Method D |
| --- |
| AASHTO T 180 |
| “ |
| “ |
| “ |
| “ |
| “ |
| “ |
| “ |
| “ |
| Compaction |
| --- |
| Method C, D |
| --- |
| AASHTO T 310 or other approved procedures |
| 1 per 500 t |
| In-place |
| --- |
| Before placing the next layer |
| Surfacing |
| Measured and tested conformance (Subsection 106.04) |
| Moisture Density |
| “ |
| “ |
| “ |
| Before using in work |
| Method D |
| --- |
| AASHTO T 180 |
| “ |
| “ |
| “ |
| “ |
| “ |
| “ |
| “ |
| “ |
Compaction
| Method C, D |
| --- |
| AASHTO T 310 or other approved procedures |
| 1 per 500 t |
| In-place |
| --- |
| Before placing the next layer |
301.09_nat_us_07_07_2005
301.09 Measurement.
Replace the second paragraph with the following:
Measure aggregate by cubic yard compacted in place when payment is by contract quantities.
301.10_nat_us_03_03_2005
301.10 Payment
Delete the following:
adjusted according to Subsection 106.05
303 - Road Reconditioning 303.01_nat_us_03_02_2005
303.01 Work.
Delete and add the following:
This work consists of reconditioning ditches, shoulders, roadbeds, cattleguards, asphalt surfaces, and aggregate surfaces.
303.06_nat_us_08_05_2008
303.06 Aggregate Surface Reconditioning.
Delete and replace with the following:
303.06 Asphalt and Aggregate Surface Reconditioning.
Repair soft and unstable areas to the full depth of the aggregate surface and according to Subsection 204.07. Scarify to the depth of the aggregate surface or to a depth of 6 inches, whichever is less, and remove surface irregularities. Reshape, finish, and compact the entire aggregate surface according to Subsection 301.05, Subsection 321.05, or Subsection 322.05 as applicable.
For asphalt surfaces, clean the existing surface of all loose material, dirt, or other deleterious substances by approved methods. Remove and dispose of unsuitable material that shows evidence of distress, excess asphalt material, or settlement in the roadbed. Patch the areas with approved material that conforms to and is compatible with the adjacent pavement structure. Perform the patch work according to Section 301, 404, 430, or other sections as applicable for the layer or courses being repaired. Clean and seal cracks in the existing asphalt surface according to Subsection 414.05. Correct surface irregularities exceeding 6 inches in depth with a specified aggregate. Place and compact the aggregate according to Subsections 301.04 and 301.05. Prelevel other dips, depressions, sags, excessive or nonexistent crown, or other surface irregularities with asphalt concrete according to Section 404. Spread and compact the asphalt concrete in layers parallel to the grade line not to exceed 2 inches in compacted depth.
Delete Table 303-1 and replace with the following:
Table 303-1 Sampling and Testing Requirements Reporting Time
| Before using in work |
| “ |
| “ |
| “ |
| Before placing next layer |
| (1) Minimum of 5 points per proctor. |
Split Sample
| Yes, when requested |
| “ |
| “ |
| “ |
| — |
| Point of Sampling |
| Processed material before incorporating in work |
| “ |
| “ |
| “ |
| In-place |
Sampling Frequency
| 1 per each mixture or change in material |
| “ |
| “ |
| “ |
| 1 per 3000 yd2 |
| Test Methods Specifications |
| AASHTO T 99 (1) |
| R-1 Marshall |
| AASHTO T 180(1) |
| R-1 Marshall |
| AASHTO T 310 or other approved procedures |
| Category |
| — |
| — |
| — |
| — |
| — |
| Characteristic |
| Moisture-density Method D |
| Moisture-density Method E |
| Moisture-density Method F |
| Moisture-density Method G |
| In-place density & moisture content |
| Type of Acceptance (Subsection) |
| Measured and tested |
for conformance (106.04)
| Material or Product |
| Existing Roadway |
303.11_nat_us_03_29_2005
303.10 Measurement
Modify the second paragraph as follows:
Measure ditch reconditioning and shoulder reconditioning by the mile, station, or foot horizontally along the centerline of the roadway for each side of the roadway.
602 - Culverts and Drains 602.03_nat_us_09_06_2005
602.03 General.
Add the following:
Ensure that the final installed alignment of all pipe allows no reverse grades, and does not permit horizontal and vertical alignments to vary from a straight line drawn from center of inlet to center of outlet by more than 2 percent of pipe center length or 1.0 feet, whichever is less.
625 - Turf Establishment 625.03_gwj_nf_08_12_2009
625.03 General.
Delete this subsection and replace with the following:
Apply turf establishment to prepared ground or any disturbed area between Jan1 and Dec 31. Apply turf establishment to the areas shown on the plans or worklists within 30 days after completion of ground disturbing activities. Unless otherwise specified in writing by the CO apply turf establishment after each 1,000 foot section of road has been constructed to template lines. Seeded areas damaged by construction activities shall be reseeded within 10 days of the damage. Do not seed during windy weather or when the ground is excessively wet, frozen, or snow covered.
Assure that all seed and mulch used in the work conforms to the weed free requirements of Section 713.
625.04 Preparing Seedbed.
Delete entire subsection and replace with the following:
Ensure that the surface soil is in a roughened condition favorable for germination and growth.
625.05 Watering
Delete entire subsection.
625.06 Fertilizing.
Delete entire subsection and replace with the following:
Apply fertilizer having a chemical analysis as listed below by the following methods.
(a) Dry Method. Apply the fertilizer with approved mechanical equipment. Hand operated methods are satisfactory on areas inaccessible to mechanical equipment.
(b) Hydraulic method. Use hydraulic-type equipment capable of providing a uniform application using water as the carrying agent. Add fertilizer to the slurry and mix before adding seed. Add the tracer material when designated by the CO.
Fertilizer. Apply fertilizer at the rate of 1,500 pounds per acre. Insure that the fertilizer meets the following chemical analysis:
| Nutrient | Percent | |
| Nitrogen, N . . . . . . . . . . . . . | 10 | |
| Phosphorus, P205 . . . . . . . . . | 10 | |
| Potassium, K . . . . . . . . . . . . . | 10 |
625.07 Seeding.
Delete the first sentence and add the following.
Apply seed mix by the following methods:
(a) Dry method. Delete the third sentence.
Add the following after subsection (b).
Seed Mix. Furnish and uniformly apply the following kinds and amounts of pure live seed:
| Quantity of Pure | ||
| Type of Seed | Live Seed (Lbs/Acre) | |
| 1. Perennial Rye Grass (Manhattan, Pennfire, or Linn) | 40 lb. | |
| 2. *Flatpea (Lathco) | 30 lb. | |
| 3. *White Dutch Clover | 4 lb. | |
| 4. Creeping Red Fescue | 10 lb. | |
| 5. Annual Ryegrass | 10 lb. | |
| 6. Agricultural Lime | 3000 lb. |
* To be inoculated per manufacturer. Germination plus hard seed must be equal to or greater than 75% and the percentage of hard seed no greater than 15%.
Determine the pounds of seed to be furnished per acre by dividing the pounds of pure live seed required per acre by the product of the percent purity and percent germination.
When seeding from October 15 to March 1, 50 lb/acre of Cereal Rye (Abruzzi) shall be added to the seed mixture.
625.08 Mulching.
Delete the entire subsection and replace with the following:
Apply Mulch within 12 hours after seeding by the following methods.
(a) Dry Method. Apply mulch with a hand spreader or a spreader utilizing forced air at a rate of 4,000 pounds per acre.
(b) Hydraulic Method. Apply mulch in a separate application from the seed using hydraulic-type equipment according to Subsection 625.07(b).
Apply wood fiber or grass straw cellulose fiber mulch at a rate of 1,500 pounds per acre.
Apply bonded fiber matrix hydraulic mulch at a minimum rate of 3,000 pounds per acre. Apply so no hole in the matrix is greater than 0.04 inches. Apply so that no gaps exist between the matrix and the soil.
718 - Traffic Signing and Marking Material 718.05_nat_us_08_05_2009
718.05 Aluminum Panels
Delete the third paragraph and replace with the following:
Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM B-449.